Installing a pipeline at depth requires sufficient space for workers and compaction of the bedding layer. The studio offers a configuration for a 2.60 m trench receiving a pipe with an external diameter of 300 mm. You can adjust the depth, pipe diameter, as well as the presence of an axle load along the excavation.
In the studio, the minimum clear width depends on the outer diameter of the pipe and the excavation depth. The calculation takes the greater of two minimums: the pipe diameter plus clearance on each side, and the width required by the depth for a person to pass. This working width at the bottom of the excavation allows pipes to be fitted and the vibrating plate to pass without hitting the shoring.
The construction work ordinance stipulates that beyond a depth of 1.50 m, an unproored or unshoring excavation wall must be sloped or secured by other measures. A vertical wall without shoring beyond 1.50 m is flagged as blocking by the tool. In addition, the ordinance text specifies that the edge of the excavation must remain clear for at least 50 cm if the wall is propped or shored, and at least 1 m if sloped.
Apparent earth pressure and truck surcharge at the edge of the excavation
To dimension a box, the studio applies Terzaghi-Peck's apparent earth pressure method. Six typical Swiss soils are proposed with modifiable starting values: sandy gravel from the Plateau, compact moraine, weathered or marly molasse, sound sandstone molasse or compact limestone, clayey silt or soft lacustre deposit, and heterogeneous old urban backfill. These indicative values must be confirmed by the construction site geotechnical report.
The ordinance specifies that shoring must withstand foreseeable loads and be dimensioned taking into account additional loads, such as vehicles, machines and material deposits. The studio takes into account the axle load of a truck or mechanical excavator positioned near the crest. The surcharge transmitted to the rigid wall is evaluated using Boussinesq's formula, distributing the axle over a length of 2 m along the trench.
Water is a classic cause of disorder and additional pressure. If the excavation crosses a wet area or undergoes heavy rain, pressures increase. The text of the ordinance also requires a certificate signed by a specialized engineer or geotechnical engineer, in particular beyond 4 m of slope height, or in the presence of additional loads and water inflows. Under these conditions, the studio displays a warning from 1.50 m and goes into red alert beyond 4 m.
Choosing the box class: light, standard or double slide rail
The choice of equipment depends on the depth and total lateral load. The studio incorporates several shoring classes for indicative purposes:
- Light aluminum box: suitable for shallow depths without heavy surcharges at the crest, manageable with a modest tonnage excavator.
- Standard steel box: retained for standard trenches, such as the typical 2.60 m depth case with nearby vehicle traffic.
- Double slide rail system: suitable for deeper trenches or unstable soils, allowing panels to be driven down step by step as earthwork progresses.
Allowable pressures and maximum depths provided in the studio are starting values taken from the specifications. The technical datasheet from the manufacturer or equipment rental company always takes precedence to check equipment resistance on site.
Struts, ladder, shoring protrusion and laying excavator
The calculation determines the compression force taken up by each bracing strut connecting the two box panels. The studio displays this calculated force in kN, to be compared with the capacity indicated by the manufacturer or rental company datasheet. If the force exceeds the component capacity, the strut spacing should be tightened or a more resistant shoring class adopted.
The studio also retains several practical construction site rules:
- The shoring box must protrude above the natural ground level by at least 0.15 m to retain falling stones or clods of earth towards the bottom.
- The access ladder for workers must exceed the excavation crest by at least 1 m to facilitate exit.
- A clear strip of at least 1 m is maintained along tracks used by construction site machinery.
- The mechanical excavator mobilized for placement must have sufficient tonnage to lift the box and extract it from the ground without tipping risk.
Bill of quantities: trench, shoring, bedding layer and disposal
The studio generates a complete and transparent bill of quantities without prices. The lines cover trench opening, applied shoring surface, gravel bedding thickness, compacted backfill as well as excavated earth volumes. The bulked volume is calculated from the modifiable soil bulking coefficient, making it possible to estimate four-axle truck rotations based on a modifiable payload of 18 tonnes.
Regarding disposal, the waste ordinance stipulates that earthy and excavation materials are sorted on the construction site and recovered as much as possible if not polluted. In addition, the client indicates in their permit application the type, quality, quantity and disposal channels for waste when the quantity is likely to exceed 200 m³ or in the presence of hazardous pollutants. The studio classifies disposal channels into types A, B and E according to the criteria of the specifications, subject to soil analysis and the agreement of the cantonal service.
Responsibility on a shored trench
We often see boxes on construction sites whose upper part is flush with the natural ground, without protruding. When a wheelbarrow passes or surroundings are cleaned, excavated materials then roll directly onto the pipe layers at the bottom of the trench. The action that avoids this incident consists of systematically wedging the top of the box at least 0.15 m above the terrain crest.
This studio operates 100% in your web browser, for free and without account creation. Nothing is sent to a server and nothing is stored in memory: closing or refreshing the page resets all data. Printed sheets feature a watermark and CSV exports mention the free version. The tool contains no pricing or ACIP code.
This tool provides pre-dimensioning assistance based on a cohesionless soil model and a load distributed over 2 m. It does not replace an on-site soil study or a note signed by a civil engineer according to SIA 267 standard. Final dimensioning engages the contractor's responsibility. To save your variants, work collaboratively and price your bills of quantities with cantonal prices, discover our Tenders, ERP and Art Construction Portail tools.
Frequently asked questions
From what depth must a trench compulsorily be shored?
The construction work ordinance requires that beyond a depth of 1.50 m, an excavation wall that is neither propped nor shored must be sloped or secured by other measures. A vertical excavation without shoring beyond this height is flagged as blocking by the studio.
What clear distance must be left at the crest of a shored trench?
The ordinance specifies that the edge of an excavation must remain clear for at least 50 cm if the wall is shored or propped, and at least 1 m if the wall is sloped. The studio retains a clear strip of at least 1 m along machinery traffic lanes.
When is it necessary to involve an engineer for excavation stability?
The ordinance requires a certificate signed by a specialized engineer or a geotechnical engineer in particular beyond 4 m of slope height, or in the presence of additional loads and water inflows. The 1.50 m threshold concerns the obligation to slope or shore, not this certificate.
How does the studio check the resistance of box struts?
The studio calculates the compression force resulting from apparent earth pressure and axle surcharge. It displays this force in kN: to be compared with the strut capacity indicated by the manufacturer or rental company datasheet, which the studio does not know.
What are the sorting obligations for excavated earth according to the waste ordinance?
The waste ordinance requires sorting unpolluted earthy materials on the construction site and recovering them as much as possible. The client declares the quality and channels if the volume is likely to exceed 200 m³ or in case of pollutants.
Is my shoring calculation data kept online?
No. The free version runs entirely in your browser. No data is sent to a remote server or kept in local memory. If you close or reload your tab, all entered dimensions and options are immediately erased.
How to value my shoring bill of quantities in a paid tender?
The free studio generates a bill of quantities without prices. To link these quantities to cantonal price base descriptions, save the file under your company account and export watermark-free reports, you can switch to the Tenders modules or Art Construction ERP.