Retaining Wall Drainage and Water Pressure (Sickerleitung)

Check water pressure on your retaining wall and calculate complete drainage: pipe, membrane and gravel. Free online studio without account.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

Why water is a problem behind a retaining wall

On a civil engineering or masonry construction site, water accumulated behind a retaining wall is a classic cause of failure. When a body of soil becomes saturated with water following heavy rain or groundwater infiltration, the voids in the soil fill up. Without drainage, the hydrostatic pressure of the water adds entirely to the active soil pressure calculated according to Rankine.

This additional lateral load acts triangularly over the entire height of the wall. It modifies the static equilibrium of the structure. The overturning moment at the base of the wall increases sharply. In practice, water can also reduce friction under the footing (uplift pressure); the studio does not model this effect.

In the ground, the absence of a discharge device turns the backfill into a heavy mass pushing against the concrete. The contractor preparing the excavation must plan for the evacuation of this water to keep calculation forces below the allowable limit.

The rear drainage system: pipe, swale, gravel, geotextile and membrane

A complete rear drainage system includes several superimposed elements. These components capture, filter and evacuate gravity water towards an outlet planned for the construction site. Each element fulfills a specific function along the upstream facing:

  • Studded membrane: placed directly against the reinforced concrete wall, it creates a draining air gap and protects the waterproofing or support during backfilling.
  • Gravel filter bed: arranged behind the membrane, this permeable material collects infiltration water and channels it downwards without creating pressure on the wall.
  • Separation geotextile: it wraps the gravel bed to block fine particles from the surrounding soil and prevent clogging of the filter.
  • Concrete swale: arranged at the low point on the heel or footing, it guides flows towards the pipe.
  • Drainage pipe (Sickerleitung): perforated tube placed on the swale at the foot of the wall, intended to collect filtered water to evacuate it out of the structure.

The methodical arrangement of these layers prevents hydraulic loading behind the concrete.

With or without drain: reading the studio comparison

The studio makes it possible to analyze the behavior of an L-shaped reinforced concrete retaining wall under two configurations: with a functional drainage device or without water evacuation. In the comparison tab, the tool contrasts mechanical stresses for the same structure geometry and identical soil.

Without a drain, the entire hydrostatic pressure of the water adds to that of the soil. The studio shows that the overturning moment doubles or triples compared to a drained situation. The calculation of bearing capacity under the footing according to Meyerhof's method and the position of the resultant then change scale. The utilization rate can then exceed 100% of the design value.

The studio compares the utilization rate to 100% and displays whether the value is below, equal to or above the limit. To dimension the structure, the dedicated button searches for the most concrete-efficient footing where all rates remain below 95%. The tool also presents the sliding force with or without shear key as well as Coulomb's earth pressure coefficient for comparison.

Clogging, maintenance and inspection chambers

An underground drainage network loses its usefulness if it gets clogged. The migration of fine silt or clay particles through the backfill layers represents a classic threat to the Sickerleitung. Without a suitable textile filter or with inappropriate backfill material, the infiltration slots of the tube clog up.

The installation of inspection chambers at each change of direction and at the ends of the line allows visual inspection and regular flushing. These manholes make high-pressure rinsing of the perforated collector possible during the operation of the structure.

From a practical standpoint, we often see drains laid flat without a flow slope or crushed by the passage of heavy machinery during peripheral backfilling. The action that avoids disorder consists of checking the bedding slope on the swale before backfilling and wrapping the pipe in a first manually compacted protective layer of gravel.

Drainage take-off: pipe meters and membrane surface

The operational take-off directly extracts the quantities of works required to establish the quote or supplier order. The studio details items without unit price, with visible calculation formulas:

  • Rear drainage (linear meters): pipe on swale, gravel and geotextile, along the length of the wall.
  • Protection membrane (square meters): wall length multiplied by its total height.
  • Wall itself: lean concrete, formwork, structural concrete and reinforcing steel, counted separately.
  • Gravel and geotextile: they are not detailed separately in the free take-off, they are part of the drainage item.
  • Rear backfill: it is deduced from the excavation and is not included in the wall-only take-off.

To value these items with your canton's prices, integration is done via Tenders or the ERP software, which take over the quantities established by the tool.

Contractor liability in case of defects

The construction of a retaining structure engages the technical and legal liability of the executor. The Code of Obligations (CO) and SIA 118 standard govern the contractor's duties of diligence. The Construction Work Ordinance (OBauV) requires proof of slope safety signed by a specialized engineer or geotechnical engineer, particularly beyond 4 m of slope height, in the event of additional loads or water inflows.

The studio provides pre-dimensioning assistance based on initial soil values. These parameters remain indicative and do not replace the site's geotechnical report or the calculation notes of a civil engineering office. In particular, the model ignores downstream terrain passive resistance (except half of that of the shear key) and cancels soil cohesion on the pressure side. To save your files and collaborate on construction sites, access Art Construction's Portal.

Frequently asked questions

How does the free studio for wall calculation work?

The studio works 100% in your web browser, for free and without registration. No data is sent or saved on a server, and no memory is kept: closing or refreshing the page clears everything. Results are displayed instantly in the form of take-offs and charts, with a watermark on printing.

What technical difference does the absence of drainage produce?

Without an evacuation system, water accumulates behind the wall. Hydrostatic pressure adds to Rankine's earth pressure. This additional load increases the overturning moment at the foot of the wall, which can double or triple, while decreasing the sliding resistance of the footing.

What are the soil values integrated into the tool?

The tool offers six typical Swiss soils: sandy gravel of the Plateau, compact moraine, weathered or marly molasse, sandstone or limestone molasse, clayey silt or lacustre deposit, and old urban backfill. These initial notebook values are modifiable and must be confirmed by an actual geotechnical report.

When is it necessary to involve an engineer for the slope?

According to the text of the Construction Work Ordinance (OBauV), proof signed by a specialized engineer or geotechnical engineer is required in particular beyond 4 m of slope height, in the event of additional loads or water inflows on the construction site.

How are excavated soils managed according to the VVEA?

According to the Ordinance on the Waste (VVEA), earthy and excavation materials are sorted on the construction site and recycled if unpolluted. The project owner indicates type, quality, quantity and channels if the volume will likely exceed 200 m³ or in the presence of hazardous pollutants.

What are the studio's calculation simplifications for walls?

The studio applies Rankine's pressure with forced zero cohesion on the upstream side. It ignores earth on the toe and downstream passive resistance (excluding half-key). Uplift pressures under the footing are not modeled without a drain. Only simple bending is checked for reinforcement.

What advantages does the Pro version bring for structural work?

The Pro version allows you to save your projects to the cloud, load existing files and work as a team. It activates automatic take-off costing with the cantonal ACIP price base and allows exporting watermark-free PDF reports in your company colors.