Safety distance of a crane near a power line or an SBB track

Check the safety distance between a crane, power line and SBB track on your plan. Free online tool in the browser, without registration.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

Why the distance to a power line determines crane positioning

Setting up a crane on a construction site requires analyzing the immediate environment before placing ballast or the arrival of the transport truck. The presence of an overhead line or railway catenary immediately affects the location of the mast. The risk of direct contact or electric arc flash requires prohibiting any movement of the jib, lifting cable or load near energized conductors.

In the field, a site manager or construction supervisor cannot rely on simple visual estimation. Ground perspective tricks the eye regarding the actual position of cables relative to the slewing radius. A positioning error discovered during assembly blocks the crane on the ground, immobilizes assembly teams and delays all structural work trades. Plan analysis allows checking available space before starting earthworks or building the foundation platform.

This page opens the tool directly on a concrete situation: a plot of land, a building, a long-reach fast-erecting crane and a passing railway catenary. In this starting configuration, the jib passes too dangerously close to the line. The studio then displays a red visual warning with the measured distance and the entered clearance distance. This visual approach allows testing several mast positions on your site plan before incurring installation costs.

Measuring clearance: from mast to line, minus jib reach

The geometric calculation of free space relies on a clear method. The clearance distance represents the remaining space between the circle swept by the jib in full rotation and the electrical or railway line. To obtain it, the studio takes the measured distance between the axis of the crane mast and the line layout, then subtracts the total length of the jib.

On the workspace interface, you draw the power line or railway track directly on your site plan. Once the line is drawn, the studio displays a red hatched clearance strip on each side of the route. This hatched zone materializes the reserved space where the tip of the jib must not penetrate. You then move the mast of your crane to observe the behavior of the assembly.

The tool continuously compares the actual measured distance to the clearance distance value entered in the component settings. If the slewing circle enters the hatched strip, the alert turns red. The studio simply indicates whether the clearance value is reached or not reached. This method avoids interpretation errors during the preparation of site installation plans.

Line voltage and starting values

Separation distances depend directly on the nature of the encountered line. A railway catenary, a medium-voltage local distribution line or a high-voltage transmission line do not share the same physical constraints. The risk of electrical arcing increases with the voltage present in the conductors.

The studio offers starting values depending on the type of structure selected:

  • Local low or medium distribution voltage
  • Railway catenary (like an SBB track)
  • High-voltage main transmission

These distances come from the studio's parameterization manual. They serve as working benchmarks for sketching your installation plan. They are not set in stone: each value remains modifiable in project settings. You must systematically check and confirm these clearance distances with the concerned power grid operator or railway company before starting work. Only the operator has exact knowledge of the operating voltage and applicable limitation periods along its tracks or cables.

What to do when the alert is red

When the jib trajectory cuts the red hatched strip, the chosen positioning does not offer the required clearance. The tool immediately signals the alert. Several technical solutions allow resolving this situation on the construction site.

The first measure consists in moving the crane mast on the plan. By moving the device back relative to railway tracks or overhead lines, you move the slewing circle away from the critical zone. This operation requires checking that the crane retains the necessary reach to service the entire building, the batching plant and the truck delivery zone.

The second option consists in reducing the useful reach of the jib. Choosing a shorter jib sometimes allows keeping the mast in a favorable location for site access while remaining outside the safety strip.

If the space on the plot allows neither moving the crane back nor shortening the jib, you must contact the grid or railway operator. It is then a matter of studying the installation of a mechanical or electronic zone limitation system, or agreeing on specific arrangements formally validated by the operator. The studio never decides on these technical devices: they require direct technical exchange with the infrastructure manager's services.

Other crane checks on the same plan

The presence of an energized line is not the only obstacle when positioning lifting equipment. The site installation plan must integrate all geometric constraints of the terrain and surroundings. The studio allows grouping these verifications onto a single medium.

You can check the counter-jib rotation relative to existing buildings, trees or already erected scaffolding. A mast positioned too close to a facade risks blocking the counter-jib or its rear counterweights during free slewing outside working hours.

The tool also examines the overflight of neighboring plots or prohibited public spaces, as well as heavy load drop zones such as skip buckets or prefabricated elements. In the presence of two cranes on the same operation, you draw both devices to visualize their respective rotation circles and check overlapping zones. This complete visual check facilitates the preparation of the safety plan for all trades present on the site.

What the free version does not do

The free version runs entirely within your web browser. Nothing is sent to an external server and nothing is saved in a remote database. When you close your browser tab, all entered tracks and parameters are immediately erased. This version contains no prices or ACIP reference data.

It is important to keep in mind the technical limits of this drawing tool:

  • Flat top view only: the studio performs a flat top-down measurement. It does not take into account the actual height of cables, conductor sag under the effect of heat, the swinging of a suspended load or windage.
  • Modifiable starting values: integrated distances are not rechecked at the source with the network operator or SUVA. The final decision rests with the operator and the site safety manager.
  • No automatic authorization: the studio issues no administrative agreement. It replaces neither permit requests with railway or electrical authorities, nor the site safety and health plan.
  • Cut-off devices: activating a zone limiter or requesting a power outage fall under agreements made directly with the operator, outside the studio.

The tool is limited to comparing your measurements with reference values: it only indicates whether the distance is reached or not reached, without making legal or regulatory judgments.

Switching to Tenders

To keep your work beyond the current browser session, switching to the paid version is done in the Tenders software. This software constitutes the only paid tool associated with this positioning module.

Switching to Tenders brings extended features for administrative and technical management of your construction sites:

  • Save your plans on a cloud-hosted construction site with a history of successive versions.
  • Reload a previously saved project at any time to adapt positioning as construction stages progress.
  • Transfer quantities from the plan (mast assembly, crane rental duration) to a draft quote, then price these items using the ACIP price database.
  • Activate Team mode to enable collaborative work between the surveyor, site manager and management.
  • Generate watermark-free image exports, customized with your company's colors and header.

The quote sent from the studio to the tender module arrives in the form of a draft without prices. You then apply your own cost prices, margins and price schedules within the pricing interface.

Frequently asked questions

How does the tool calculate the clearance distance?

The studio measures the flat distance between the axis of the crane mast and the layout of the electrical or railway line. It then subtracts the length of the jib. The remaining value corresponds to the actual clearance distance, compared to the entered safety value.

Are my site data sent to your servers?

No. In the free version, the studio runs in your web browser. No file, track or plan is sent or saved on a server. As soon as you close your browser window or tab, all session data are erased.

Can the default safety distances be modified?

Yes. The starting values provided in the studio manual correspond to sketch benchmarks. You can modify these values directly in the configuration panel to apply the prescriptions of the concerned power grid operator or railway company.

Does the studio take into account live cable sag?

No. The tool operates in a flat top view. It calculates neither the altitude of cables, nor their deflection according to temperature, nor the sway of the load on the hook under the effect of wind. These elements must be analyzed on site with the operator.

Does the displayed result replace the railway company's agreement?

No. The result visualized in the studio constitutes a simple geometric aid for site preparation. It never replaces the official crossing or work authorization issued by the railway company or the electrical grid manager.

How can a crane installation plan be saved for later?

Project saving is done by switching to the paid Tenders software. You can then save your plans in the cloud, archive successive versions of the installation and resume positioning at any time from your work account.

Does the free version allow pricing crane rental?

No. The free version contains no prices or ACIP database data. To value assembly, disassembly and weekly rental items, the plan exports a draft quote without prices to be processed in the Tenders software.