Opening an old stone or molasse wall: underpinning method with twin HEB beams

Size an opening in a 50 cm stone wall using twin HEB beams underpinning. Bearing structural analysis and free bill of quantities without sign-up.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

An old 50 cm wall: why twin sections rather than a single profile

In older buildings across Romandy, an external or internal load-bearing wall frequently reaches a thickness of 50 cm. Replacing such a pier with a single steel lintel poses two major challenges on the construction site: the self-weight of the steel member and the bearing width required to support both wall faces. A large HEB profile quickly exceeds 250 kg. Handling such a mass inside an existing dwelling, without a mobile crane, demands heavy lifting gear such as shear legs or workshop beam lifters.

The standard structural work solution consists of placing two twin HEB sections side by side. Two more compact beams provide the required bearing width to carry the entire thickness of the masonry, while halving the weight of each unit to be handled by the masons. The studio features a standard example featuring an opening of 3.60 m in a 50 cm rubble or molasse stone wall, on two simple supports. The tool checks whether the stress ratio of the twin section remains less than or equal to 100% of the design value.

Underpinning method: installing the two halves sequentially

The core advantage of paired beams lies in sequential installation via underpinning. Rather than demolishing the entire wall thickness under complete through-propping, the site manager coordinates the intervention in two distinct phases:

  1. Chasing the first face: diamond saw cutting and masonry removal across half the wall thickness, retaining the other half to support the upper floors and the roof.
  2. Installing the first profile: inserting the first HEB onto its prepared concrete padstones, dry packing, and ramming with non-shrink mortar.
  3. Switching to the second face: after the non-shrink mortar has cured, opening the second chase from the adjoining room, installing the second twin HEB, then bolting or tying according to technical specifications.
  4. Demolishing the central core: final clearing of the rubble masonry beneath the two beams now actively carrying load.

This approach minimises differential settlements and keeps preserved floor structures secure.

Lime-mortared rubble and molasse: delicate masonry, essential padstones

Natural stone, coarse rubble, and molasse laid with lime mortar display very low mechanical resistance in local compression. According to the principles of standard SIA 266 for masonry, setting a narrow steel flange directly on this material leads to immediate crushing under support reactions. In the studio, the design resistance of the existing masonry is editable to reflect the actual condition of existing structures in French-speaking Switzerland.

The software compares direct bearing pressure to 1.25 times the masonry resistance. As soon as this design value is exceeded, the calculation automatically sizes a C25/30 reinforced concrete distribution padstone, specified by its length and height. If the padstone length exceeds 600 mm or if the remaining masonry pier measures less than 40 cm, the tool flags the necessity to switch to a complete steel portal frame incorporating two vertical steel columns.

Twin beam design: bending moment, shear force, and lateral torsional buckling

The calculation applies ultimate limit state (ULS) and serviceability limit state (SLS) action combinations defined by standard SIA 260, incorporating dead loads, floor live loads, and climatic actions according to standard SIA 261. For wind and snow, the altitude is retrieved from swisstopo's official localities list; Δh and q_p0 are pre-filled for eight reference locations (Lausanne, Geneva, Sion, Verbier, Bulle, La Chaux-de-Fonds, Zurich, St. Moritz) and default to 0 m and 0.9 kN/m² for others. Above an altitude of 2000 m, a dedicated alert is displayed.

For steel (HEA, HEB, IPE, HEM sections in S235 or S355 grades), structural verification follows standard SIA 263: bending moment, shear force, moment-shear interaction, and lateral torsional buckling risk. Deflection is calculated using the Timoshenko beam model, accounting for shear deformation. To protect upper partition walls from cracking, the studio applies a strict deflection limit of L/500 capped at 10 mm under a load-bearing wall. The "Find minimal section" button selects the lightest member keeping the capacity utilization ratio less than or equal to 95%.

Propping, dry packing, and underpinning: the risk of cracking

On site, a frequent pitfall is underestimating the initial structural deflection during load transfer phases. Propping that is too slack or dry packing carried out with ordinary shrinking mortar causes delayed load transfer: the wall above settles by several millimetres, leading to visible cracks in plasterwork or sticking joinery on upper storeys.

Best practice on the construction site requires installing a line of heavy-duty props every 0.80 m, combined with meticulous dry packing using non-shrink mortar between the top flange of the sections and the overhead stone course. The unpriced bill of quantities generated by the studio incorporates all these execution items: double-sided heavy propping, wall sawing, demolition, concrete padstones, steelwork, non-shrink dry packing, and EI30 or EI60 fire protection.

Responsibilities before cutting an old wall

This structural studio operates free of charge, with no registration and no account required. Processing runs 100% in your browser: no files are uploaded to any server, and closing the tab clears your data. Printable reports include an Art Construction watermark.

The tool provides preliminary sizing to help prepare your tenders and check feasibility. Under no circumstances does it replace a qualified civil engineer. Any opening in a load-bearing rubble wall requires a definitive calculation note and engineer execution drawings before cutting begins. To save your variations across a construction site, price your quantities using the ACIP database, or export technical dossiers without watermarks, explore our pricing modules on notre outil de soumissions, comprehensive management via le portail de gestion, and advanced features on la page offre.

Frequently asked questions

Why choose twin HEB beams over a single section?

For an old 50 cm wall, a single section demands heavy lifting gear and immediate full-thickness demolition. Twin HEB sections divide the individual unit weight and allow sequential two-stage installation through chases without compromising structural stability.

What deflection limit is applied for an opening under masonry?

The studio applies by default a deflection limit of L/500 capped at 10 mm for load-bearing walls. This strict requirement limits residual settlements and prevents cracking in partitions or finishes on upper storeys.

How does the studio handle the low strength of molasse or rubble stone?

The design resistance of existing masonry is fully editable. The studio compares direct bearing pressure to 1.25 times this value pursuant to standard SIA 266. If exceeded, it automatically calculates the length and depth of a C25/30 reinforced concrete distribution padstone.

When should concrete padstones be replaced with a full steel frame?

An alert flags the need to switch to a two-column portal frame whenever the distribution padstone length exceeds 600 mm or when the remaining masonry pier width is less than 40 cm.

Is my calculation data saved within the free browser tool?

No. The free version operates 100% within your browser, without accounts or local storage. No files are transmitted to a server. Closing or refreshing the page clears all entered data.

Are unit prices for masonry and steel included in the generated bill of quantities?

The free version generates a detailed unpriced bill of quantities without costs or ACIP codes. Automated cost estimation using cantonal price books is performed server-side in the Pro version.

Does this calculation exempt me from obtaining an engineer-signed structural report?

No. The results serve as decision support for preliminary sizing and budget estimation. The contractor's liability remains fully engaged, and a calculation report alongside execution drawings from a civil engineer remains mandatory prior to demolition.