Knocking down a load-bearing wall over 4 to 5 m: HEB beam calculation, propping and padstones

Calculate your HEB beam for a 4 to 5 m load-bearing wall. Run load rundown, padstone and shoring checks using this free tool directly in your browser.

RAM session: closing or reloading the page erases everything. Export before leaving.

Loading...

About this tool

Large span: why deflection governs over strength when selecting a section

Creating an opening of 4 to 5 metres in masonry fundamentally alters the behaviour of the building. Across such spans, raw mechanical strength at the ultimate limit state (ELU) rarely dictates the depth of the steel section. The governing criterion remains deflection under serviceability limit state (ELS) loading.

Excessive deflection immediately leads to structural defects on upper floors: cracking in partition walls, jamming of joinery or cracking of screeds. The studio applies a strict threshold for knocking down a load-bearing wall: permissible vertical deflection is capped at one five-hundredth of the span (L/500), with an absolute maximum set at 10 mm. Over a 4.20 m or 5 m span, this 10 mm ceiling restricts the calculation well before reaching the yield strength of the steel.

The calculation accounts for shear deformation in accordance with Timoshenko beam theory. Compared to more slender IPE sections, the HEB profile offers high stiffness and a broad flange, limiting local crushing and the risk of lateral-torsional buckling. The automatic search button scans S235 or S355 rolled sections and selects the lightest profile whose utilisation ratio remains equal to or below 95 % of the allowable value.

Two supported storeys: load rundown and action combinations under standard SIA 260

In the default benchmark scenario loaded in the studio, the lintel spans 4.20 m and supports two full storeys: an upper wall of 25 cm thick sand-lime bricks, two reinforced concrete slabs, and the associated live loads. The tool handles from zero to six storeys, differentiating floor spans on the left and right.

The accumulation of dead loads and variable imposed loads requires the application of action combinations under standard SIA 260. Load factors and companion factors ψ depend on the building's use (residential, office, commercial or storage) as well as the altitude of the construction site for snow loads.

Climatic actions are based on standard SIA 261. Elevation is imported from swisstopo's official list of municipalities. For Lausanne, Geneva, Sion, Verbier, Bulle, La Chaux-de-Fonds, Zurich or St. Moritz, the snow altitude adjustment Δh and reference wind pressure q_p0 are pre-configured. For all other locations, these two values default to 0 m and 0.9 kN/m² and must be entered using national zoning maps; above 2000 m altitude, an orange warning is displayed.

Distribution padstones and piers: can the masonry take the reaction?

The support reaction of a beam spanning 5 metres under two storeys frequently exceeds several dozen kilonewtons. Concentrating this point load directly on raw masonry inevitably leads to localised crushing. In accordance with standard SIA 266, direct compressive stress under the flange is checked against 1.25 times the design strength of the existing masonry.

If the masonry cannot support the concentrated load directly, the studio automatically calculates a reinforced concrete padstone in C25/30, specifying its required length and depth. This concrete block spreads the reaction across a greater length of the retained load-bearing wall.

Two critical limits require abandoning simple masonry bearing in favour of a complete steel portal frame:

  • The calculated length of the concrete padstone exceeds 600 mm.
  • The remaining masonry pier between the edge of the opening and the building corner is under 40 cm.

In these scenarios, the studio switches to a design incorporating tied vertical steel columns, preventing the instability of overstressed, narrow piers.

Double-sided heavy propping and handling sections weighing several hundred kilos

Before cutting even a single square centimetre of masonry, the entire load above must be transferred onto temporary shoring. Slabs must be supported on both sides of the wall using shoring towers or closely spaced props, typically installed at 0.80 m intervals, with sole plates on the floor to prevent punching through the lower slab. If the basement is neither vaulted nor reinforced, this shoring must be carried down through successive levels to the foundation slab.

Handling the steel beam represents the second practical challenge. An HEB section intended to bridge 5 metres commonly weighs between 200 and 450 kg. A site warning triggers whenever an element's mass exceeds 100 kg, signalling the need for an engine crane, a hoist or a mechanical beam lifter. Above 250 kg in an occupied building, installation becomes particularly demanding.

A practical site technique is to opt for paired profiles. Two narrower beams placed side by side and bolted together halve the lifting weight, while allowing each piece to be inserted sequentially into the chased wall.

The costly mistake on site

On renovation construction sites, demolition is often seen starting as soon as props are wedged beneath the ceiling, without inspecting the condition of the floor under the jacks. The concentrated vertical force punches through the screed or deflects the ground-floor slab, causing damage on the floor below before the steel beam has even arrived on site.

To avoid this error, map the load rundown down to the foundations before making the slightest cut. If the opening is located on the ground floor over an unreinforced basement, install an identical line of props in the cellar, perfectly aligned and fitted with wooden sole plates at the floor and ceiling. Relieving the lower structure in this way guarantees the overall equilibrium of the building throughout cutting and dry-packing operations.

Contractor liability on wide openings

The online structural studio provides preliminary sizing assistance to verify technical feasibility quickly and draw up quotes. It calculates a simply supported beam with linear elastic behaviour, without modelling complex 3D building interactions. These outputs do not replace definitive calculation notes and working drawings signed by a qualified civil engineer.

The civil liability (responsabilité civile) and criminal liability of the contractor remain fully engaged on the construction site under the Code of Obligations (CO) and standard SIA 118. Altering a load-bearing structure directly affects the global stability of the building. The studio's default values (masonry densities, mechanical strengths, live loads) can be edited: always cross-check them against the actual building fabric before starting diamond cutting.

To learn more about organizing written specifications and managing structural work contracts, take a look at our dedicated modules for tenders and our site supervision portail.

Moving from structural sizing to takeoffs and quotes

Once the section has been selected, the tool generates a comprehensive, unpriced quantity takeoff: heavy double-sided shoring, linear metres of diamond sawing, demolition volumes, concrete padstone quantities, steel supply, non-shrink mortar dry packing, and EI30 or EI60 fire encasement in line with fire protection requirements.

The standard tool runs entirely within your browser: no data is sent to our servers, no user account is required, and closing the tab resets your entry. Printed documents display a discreet Art Construction watermark.

To convert this bill of quantities into a detailed commercial quote, the paid version built into our Soumissions, ERP and Portail software allows you to store variants by construction site, automatically price each item using the cantonal ACIP database, export a neutral PDF report with your branding, and share files across your team.

Frequently asked questions

What is the difference between an HEA and an HEB section when opening a wall?

For a given nominal height, an HEB beam features thicker flanges and a thicker web than an HEA profile. It delivers a higher second moment of area and deflects less under heavy loads. Over a 4 to 5 m opening supporting two upper storeys, the HEB profile is typically preferred because it minimises overall structural depth while keeping total deflection below the 10 mm serviceability threshold.

Why limit deflection to L/500 and 10 mm rather than L/300?

General floor design typically allows a deflection limit of L/300. Beneath a masonry load-bearing wall, however, such deflection would crack the mortar bed joints and cause cracking in upper partitions and tiled finishes. The L/500 cap combined with an absolute maximum of 10 mm protects the preserved masonry above from differential movements.

How can you handle a steel beam weighing more than 250 kg?

When access constraints rule out heavy lifting machinery, the standard solution is to specify paired profiles. Two parallel channels (UPN) or two smaller HEB sections set side by side jointly bear the overall load. Each half-beam is carried and slotted into the wall chase using an engine crane or a manual beam trolley before being bolted securely together.

When is a reinforced concrete padstone mandatory under the beam?

A padstone is required whenever the contact stress transferred by the beam flange exceeds the design strength of the existing masonry according to standard SIA 266. Cast in C25/30 concrete at the head of the pier, this padstone distributes concentrated bearing forces over a broader footprint to prevent local crushing or splitting of the bricks.

Which climatic parameters does the studio load by default?

The studio imports official swisstopo municipality elevations, alongside Δh snow adjustments and reference wind pressures q_p0 for eight benchmark towns in accordance with standard SIA 261. For any other Swiss municipality, these two values default to 0 m and 0.9 kN/m²: replace them with local regulatory values and adjust the elevation if the construction site sits higher than the municipality centre.

Are calculation details stored in the free browser tool?

No. The free studio runs entirely on the client side in your web browser. No data is transmitted to an external server or saved in local storage. If you refresh or close the tab, your entries are instantly discarded. The printable PDF export contains an identification watermark.

Can demolition start immediately using only the printout from the online studio?

No. The online tool is intended purely for preliminary sizing and technical decision-making to assist in drawing up quotes. Knocking down a load-bearing wall over this span requires a comprehensive calculation report, connection details, and working drawings validated and signed by a qualified civil engineer before diamond cutting begins.