How much does a load-bearing wall opening cost: why a price without a take-off is a trap
Quoting a lump sum to knock down or open a load-bearing wall without preparing a detailed bill of quantities exposes the contractor to heavy losses. On site, an opening is never just about breaking masonry and installing a lintel. The loads supported by the element vary according to the number of storeys above, the span of the slabs, the roof type and the building's altitude. An undersized steel section or timber beam leads to damage on the partitions above, while unnecessary oversizing complicates indoor handling.
The true cost of an opening project depends on execution constraints: the need for heavy propping across several floors, the cutting method to preserve the reveals, rubble removal without a hoist, or creating spreader padstones to avoid crushing existing masonry. A fixed-price quote prepared without quantity calculations exposes the contractor to disputes in the event of structural surprises. To set a fair price in a tender, every operational phase must be broken down into verifiable physical quantities.
The items in an opening quote: propping, sawing, demolition, padstones, beam, dry packing
A comprehensive quote for demolishing a load-bearing wall brings together seven inseparable basic items:
- Temporary propping: taking up loads on either side of the partition. This involves heavy two-sided propping consisting of shore towers or adjustable props with spreader timbers on the floor and ceiling, sometimes carried down to lower levels right down to the foundations.
- Diamond wall sawing: clean cutting along the boundaries of the opening to avoid destructive impacts from breaker hammers on the preserved reveals.
- Demolition and disposal: careful removal of the masonry, cutting blocks into manageable pieces, sorting mineral waste, and transport to the landfill.
- Spreader padstones: cast-in-place or precast concrete blocks at the bearings, designed to spread the point load across the remaining masonry in accordance with standard SIA 266.
- Transfer beam: supply and installation of a steel lintel (HEA, HEB, IPE, or HEM sections) or timber beam (solid C24, glulam GL24h or GL28h).
- Dry packing: packing underneath the retained masonry using non-shrink mortar to reload the structure without differential settlement.
From design sizing to quantities: the take-off formulas
In the Construction Site Structural Studio, the Take-off tab converts load run-downs into ordering quantities for a typical 3.80 m opening or any other entered span. The applied formulas remain visible within the interface:
- Propping: the take-off assumes a line of props spaced at 0.80 m on each face of the wall. The number of props is calculated by dividing the span by the spacing, multiplied by two for both sides, completed by the linear meterage of timber spreader beams.
- Wall sawing: measured in linear metres or cutting surface area (linear metres multiplied by wall thickness). The tool counts two vertical cuts over the height under the lintel and one initial horizontal cut.
- Demolition: calculated as strict geometric volume (opening length × height × wall thickness), to which a bulking factor is applied to plan removal skips.
- Concrete padstones: volume calculated according to wall width, bearing length determined by allowable masonry stress, and a minimum depth against crushing.
- Beam: clear span increased by bearing lengths at both ends, multiplied by the nominal linear mass of the section to obtain the steel tonnage or timber volume.
When the weight of a section exceeds 100 kg, an alert prompts you to arrange indoor lifting equipment. Beyond 250 kg, the practical tip is to select paired twin sections installed in two successive phases.
Fireproof encasement and engineering fees: the forgotten items
Two major budget items are frequently omitted from initial take-offs: fire protection and engineering studies. In indoor refurbishment, load-bearing steel elements quickly lose their load capacity under high heat. The quote must include an EI30 or EI60 fire protection cladding using specific plasterboards or encasement with RF1-rated materials, pursuant to VKF/AEAI fire protection guidelines. This quantity is calculated as the developed surface area across the three exposed faces of the steel section.
Furthermore, creating an opening in a load-bearing structure affects the overall stability of the building. Civil engineering fees must appear explicitly in the budget. The engineer carries out destructive or non-destructive on-site inspections, verifies feasibility, draws up the definitive structural calculation report, and provides reinforcement or installation drawings with bearing details. This professional service item is a prerequisite for project sign-off with authorities and insurers.
Costing with the ACIP database: what happens on the server
The in-browser tool runs without registration and without an account. All preliminary sizing calculations, load run-downs (according to standards SIA 260, SIA 261, SIA 262, SIA 263, SIA 265, and SIA 266), and quantity surveys run entirely on your workstation. Nothing is sent or stored on a remote server: if you close or refresh your tab, the entered data is cleared. The free CSV export carries an explanatory notice and printouts display a watermark.
In the free version, no unit price or catalogue code is assigned to the take-off lines. Financial costing is carried out via the Pro version linked to the Art Construction Soumissions, ERP, and Portail modules. On the Pro server, quantities from the studio are automatically matched to items and average prices from the relevant canton's ACIP database. This step allows you to generate a quote ready to send, save the project in the cloud, collaborate with your team, and output an unwatermarked dossier customized with your corporate branding.
Liability of the contractor submitting a price
Using a structural calculation studio provides technical support to compile realistic take-offs and assess project feasibility. However, this preliminary calculation is based on a simply supported beam model in a linear elastic domain. It cannot replace a visual site inspection, a global structural analysis, or the execution drawings required under standard SIA 118.
Under the Code of Obligations (CO) (Code des obligations) and the Swiss Criminal Code, the contractor remains liable for damage caused to third parties and to the structure during demolition and underpinning works. Opening a load-bearing wall without an official calculation report or installation drawing stamped by a civil engineer directly engages the civil liability and criminal liability of the contractor. Preliminary sizing allows you to price each item accurately without errors in material supplies, but physical wall opening must only commence once drawings are formally approved by the appointed engineering office. To discover the full business management environment, visit the Portail or prepare your projects using our module for the Pro offer.
Frequently asked questions
Does the online studio directly provide the price of an opening in Swiss francs?
No. The free in-browser version calculates exact dimensions and quantities for each item (linear metres of sawing, concrete volume, steel weight, number of props), but displays no amounts in francs or unit price. Pricing is applied server-side in the Pro version using the cantonal ACIP database.
Is my construction site data saved if I close my browser?
No. The tool runs 100% within your web browser without an account or registration. Nothing is transmitted to a server and no memory is stored locally. Closing or refreshing the page clears all entered data. Persistent saving is included in the features of the Pro version.
Why limit the deflection of a load-bearing wall lintel to L/500 and 10 mm?
A beam supporting masonry or partitions above must offer very high stiffness. Excessive deflection causes plaster cracking, sticking doors on upper floors, and damage to slabs. The studio enforces this strict limit to prevent such structural defects.
What should I do if my construction site locality is not among the eight built-in cities?
The studio retrieves altitude from the official swisstopo list of localities. Snow adjustment Δh and wind pressure q_p0 are pre-filled only for eight typical localities; for any other Swiss municipality, you enter them manually with reference to standard SIA 261 maps. An alert appears automatically whenever the altitude exceeds 2000 m.
When should concrete padstones be replaced by a steel goalpost frame?
The studio flags the requirement to switch to a goalpost frame with steel columns in two cases: when the calculated padstone length exceeds 600 mm, or when the remaining reveal on the existing masonry is less than 40 cm wide, which is insufficient to distribute the bearing pressure.
Can the generated take-off be used directly as a working drawing for sawing?
No. Results and take-offs serve as estimating aids and feasibility assessments. Carrying out a load-bearing wall opening strictly requires a final structural calculation report and execution drawings approved and signed by a civil engineer before work begins.
How do you handle a steel beam weighing over 100 kg inside a residential property?
For sections weighing over 100 kg, the tool highlights the need for suitable lifting gear, such as a beam lifter or floor crane. If the total weight exceeds 250 kg, the recommended option is to size paired twin sections, allowing two lighter beams to be placed side by side in sequence.