Ground snow and roof snow: the SIA 261 formula by altitude
Sizing a roof in French-speaking Switzerland begins with an accurate assessment of climatic actions. Standard SIA 261 defines the characteristic value of the ground snow load using the formula:
s_k = max([1 + (h₀ / 350)²] · 0.4 ; 0.9)
In this equation, the reference altitude h₀ corresponds to the site altitude h plus an adjustment Δh. This adjustment accounts for local accumulation effects or Alpine microclimates. The studio loads the official swisstopo list of localities and takes the altitude of the chosen postcode. For eight typical localities taken from the specifications, Δh and q_p0 are also pre-filled: Bulle (altitude 771 m with a Δh of 200 m), Lausanne, Geneva, Sion, Verbier, La Chaux-de-Fonds, Zurich and St. Moritz. For a structure located outside these municipalities, Δh and q_p0 default to 0 m and 0.9 kN/m²: you overwrite them after checking the regional maps in standard SIA 261, and you adjust the altitude if the construction site is higher than the locality.
The load transferred to the purlin does not correspond directly to the ground value. It depends on the roof geometry. A shape coefficient applies depending on the roof pitch, supplemented by the possible presence of snow guards. For a 30-degree pitch, this coefficient reduces the gross load by accounting for the natural sliding of snow. However, retention by snow bars maintains a higher action on the structure. Above 2000 m altitude, an orange alert warns that exceptional conditions exceed the simplified standard model.
Roofing dead load and tributary width of a purlin
To establish the load rundown on a purlin, the quantity surveyor isolates a strip of roof known as the tributary width. On a common configuration with a centre-to-centre spacing of 1.50 m and a span between supports of 4.80 m, the beam carries all actions acting on this rectangular area.
The inventory of permanent actions combines several distinct layers:
- The external roof covering made of clay tiles, concrete tiles or fibre cement;
- Battens, counter-battens and waterproof sarking membranes;
- Thermal insulation between or over rafters, as well as vapour barriers;
- Internal lining beneath the rafters;
- The self-weight of the timber purlin itself.
These permanent actions are added to variable snow and wind actions according to the ultimate limit state (ULS) and serviceability limit state (SLS) combinations specified by standard SIA 260. The combination factors ψ weight the probability of simultaneous occurrence of maximum snow load and peak wind. The surface weights proposed in the tool remain editable starting values. You must adapt these loads to the technical data sheets provided by the manufacturers of the roofing materials selected for the project.
C24 solid timber or GL24h glulam: bending, shear and bearing
The choice of structural material dictates load-bearing capacity and section geometry. For intermediate spans, C24 solid timber remains an economical traditional solution, but its available dimensions are limited. As soon as the span exceeds four metres or the altitude imposes a heavy snow load, GL24h or GL28h homogeneous glulam is necessary to limit the beam depth.
Design follows the rules of standard SIA 265 using a linear elastic calculation on two simple supports:
- Pure bending: normal stress induced by the maximum mid-span bending moment must remain less than or equal to the design bending strength of the material.
- Shear: shear stress generated by the vertical shear force at supports must not exceed the design shear strength, evaluated considering Timoshenko beam deformations.
- Compression perpendicular to the grain: at the wall plate or support bearing, contact stress must not crush the transverse wood fibres.
The studio compares the utilisation ratio against 100% of the permissible design value and indicates whether it is less than, equal to, or greater than that limit. The automatic search function scans the section library to identify the minimum cross-section achieving a utilisation ratio of 95% or less.
Final deflection with creep and service class
On a timber construction site, raw structural capacity is not enough to prevent defects. Excessive deflection causes damage to the roof covering, failures in water tightness or jamming of roof windows. The calculation of deflections at the serviceability limit state (SLS) accounts for instantaneous elasticity and long-term deformation linked to timber creep.
Standard SIA 265 modulates this time-dependent behaviour according to the service class of the member, which reflects the average ambient humidity over the year. Components installed within an insulated and ventilated roof space do not undergo the same mechanical degradation as those placed under weather-exposed eaves. The final deflection thus combines the instantaneous elastic effect with long-term plastic growth.
For roof purlins and joists, the standard permissible limit is set at L / 300 of the span, a threshold the user can adjust according to project requirements. For lintels beneath load-bearing walls, the threshold is more stringent: L / 500 capped at 10 mm to prevent cracking in upper masonry. The calculation displays the net overall deflection including shear effects, allowing verification of sheet metal flashing details.
High altitude and site survey: calculation limitations
Using this preliminary sizing tool requires full awareness of its simplifying assumptions:
- 2D static model: the calculation assumes two simple supports without continuity, without 3D modelling or global interaction with the roof frame.
- Biaxial bending: a purlin laid parallel to the roof pitch on rafters experiences a component parallel to the slope. The studio considers loads solely in the vertical plane without calculating biaxial bending.
- Lateral stability: the risk of lateral-torsional buckling under bending is only flagged on screen without checking continuous bracing.
- Local data: altitude comes from the official swisstopo list of localities, but Δh and q_p0 are only pre-filled for eight localities. Wind and snow values for any other municipality must be obtained from the official maps in standard SIA 261.
- Nominal dimensions: geometric properties are calculated from nominal dimensions; they must be cross-checked against dimensions stated in the manufacturer’s certificate.
Above 2000 m altitude, exceptional snow overloads, drifting snow and the dynamic impact pressures of heavy snow require a dedicated on-site engineering assessment.
Responsibilities of the carpenter and civil engineer
The carpenter or primary contractor remains personally responsible for structural choices and execution on the construction site. Calculations produced by the studio provide operational decision support for preliminary estimates or evaluating the technical feasibility of options. They under no circumstances replace the involvement of a specialist consulting engineer.
A civil engineer's calculation report and workshop fabrication drawings remain mandatory to validate sections, mechanical connections, steel brackets and anchorage into existing masonry in accordance with standard SIA 266. In the case of major refurbishment or structural alterations, the statutory rules of the Code of Obligations (CO) (Code des obligations) and standard SIA 118 govern the respective liabilities of the parties.
This free tool runs entirely in the browser: no account is required, no data is sent to a server, and closing the tab resets the session. To integrate sizing into company project files, the Portail platform and ERP allow saving to a cloud construction site. To convert these quantities into a financial quote linked to cantonal specifications, consult our tender management module for tenders and explore the full suite via the pro offers page.
Frequently asked questions
How is the snow load calculated for a locality not listed in the studio?
For a Swiss locality outside the eight pre-set municipalities, the altitude is fetched from the official swisstopo list, but you must look up the adjustment Δh and wind pressure q_p0 on the maps in standard SIA 261, adjusting the altitude if the construction site is higher. Simply enter these values into the studio fields to determine the ground load.
What is the structural difference between C24 solid timber and GL24h glulam?
C24 timber is a solid member with natural characteristics such as knots. GL24h glulam consists of finger-jointed, glued timber laminations, which homogenises the material, increases its characteristic bending strength, and allows longer spans with more uniform sections.
Why is biaxial bending not considered for an inclined purlin?
The studio applies gravity loads vertically on two simple supports. When a purlin is installed tilted along the roof pitch without intermediate rafters to prevent sliding, biaxial bending occurs. This specific check must be performed separately by a civil engineer.
What does the roof snow shape coefficient correspond to?
This coefficient defined by standard SIA 261 converts the ground snow load into the load acting directly on the roof slope. It depends on the roof pitch, which facilitates natural snow shedding, and the presence or absence of snow retention bars that prevent shedding.
What data is stored when using the free version?
No data is transmitted or stored. The calculation runs entirely inside your web browser without contacting a remote server. Closing or refreshing your tab instantly clears all entered data and output diagrams.
What deflection limit is appropriate for a standard roof purlin?
For a roof purlin or floor joist, the permissible final deflection limit under serviceability loads is typically set at L / 300 of the span. For a lintel supporting a load-bearing wall, the requirement tightens to L / 500 capped at 10 mm to protect wall finishes.
Does this preliminary sizing replace a civil engineer’s calculation report?
No. The studio provides preliminary decision-support sizing for cost estimation and feasibility studies. It does not replace site inspections, formal structural calculations, or approved execution drawings, which must be signed off by a civil engineer prior to works.