The canton of Appenzell Outer Rhodes governs planning through the act on spatial planning and building law (Baugesetz, bGS 721.1) and its implementing ordinance (Verordnung zum Baugesetz, bGS 721.11). This ordinance defines the Baumassenziffer (BMZ, building mass ratio): the ratio between the above-ground building volume and the chargeable land area, that of the plot covered by the permit application. Municipalities set the BMZ value per zone in their zoning plan (Zonenplan) and their building regulations (Baureglement). The canton’s membership of the IVHB (AIHC) should be checked in the legislation in force.
The ground there is sloping almost everywhere, with scattered settlement and many streams. The Geo-Scanner shows the plot, its EGRID, its indicative area, the ARE harmonised building zone and the status of the cantonal ÖREB cadastre (cadastre of public-law restrictions on landownership), governed by a cantonal ordinance that came into force in 2021. Its slope profile gives the gradient between two points in figures, the starting point for buried volume and earthworks.
Worked example: checking the Baumassenziffer of a sloping plot
An 800 m² plot in a residential zone, at about 900 m above sea level. The municipality’s Baureglement sets a BMZ of 2.2 m³ per m² (example value). The project is a 14.00 m by 10.00 m building with an average above-ground height of 9.00 m.
| Data | Source | Calculation | Result |
|---|---|---|---|
| Chargeable area | Geo-Scanner (indicative) | geometry | 800 m² |
| Baumassenziffer BMZ | Baureglement (example) | zone value | 2.2 m³/m² |
| Max. above-ground volume | calculation | 800 × 2.2 | 1,760 m³ |
| Above-ground volume of the project | plans | 14.00 × 10.00 × 9.00 | 1,260 m³ |
| Volume reserve | calculation | 1,760 − 1,260 | 500 m³ |
| Height difference on profile A-B | Geo-Scanner | 40.0 m × 15.0 % | 6.00 m |
The 800 m² area multiplied by the example BMZ of 2.2 gives at most 1,760 m³ of above-ground building volume. The 14.00 × 10.00 × 9.00 m project represents 1,260 m³; a reserve of 500 m³ remains. The measurement of above-ground height depends on the natural ground, hence the importance of the profile.
Over 40.0 m, the profile gives an average slope of 15.0 %, i.e. 6.00 m of height difference. Part of the ground floor will be buried on the uphill side: depending on the cantonal definition, this volume may not count in the above-ground volume. The exact rule is found in the cantonal ordinance and the Baureglement; the surveyor provides the relevant natural ground level.
With an example BMZ of 2.2, the 800 m² plot allows 1,760 m³ above ground; the 1,260 m³ project leaves a 500 m³ reserve, to be confirmed with the surveyed natural ground.
3 frequent pitfalls on a plot in Appenzell Outer Rhodes
Thinking in area instead of volume
Where the Baureglement sets a Baumassenziffer, it is the above-ground volume that is limited, not the floor area. A tall top floor or a large storey height quickly uses up the reserve. Calculate in cubic metres from the sketch stage.
Measuring height on a map instead of the natural ground
The Geo-Scanner profile comes from the swisstopo terrain model: it gives an order of magnitude, not the relevant natural ground level. For above-ground volume and heights, only the surveyor’s survey counts.
Ignoring landslide and surface runoff hazards
Appenzell slopes are exposed to landslides and surface runoff. The Geo-Scanner’s federal layers are indicative; the cantonal hazard map and the ÖREB cadastre tell you whether restrictions apply to the plot.
How to use it in 3 steps in Appenzell Outer Rhodes
- Find the plot
Enter the address, the number and the municipality or the EGRID. Check the highlighted plot on the orthophoto and the cadastral map. - Read ÖREB status, zone and hazards
Note the harmonised building zone and the ÖREB status, open the cantonal cadastre through the link provided, then display the surface runoff and rockfall layers with their legend. - Quantify the slope and export
Draw a profile along the steepest slope, note altitude and height difference, then export the CSV for the BMZ calculation and the exchanges with the surveyor.
What the free Geo-Scanner does not do in Appenzell Outer Rhodes
The Geo-Scanner does not calculate the Baumassenziffer and does not know the municipality’s Baureglement. It does not show the relevant natural ground, detailed cantonal hazard maps, groundwater protection zones or easements. It does not read the content of the ÖREB restrictions and does no structural calculation and no snow load.
Once the project is under way, Portail chantier shares the ÖREB extract, the surveyor’s survey and the plans with the client, site by site. ERP Art Construction costs the earthworks and structural works, tracks the site and the invoicing, and produces a site opening sheet. Checking the BMZ remains a calculation to be done on the plans.
Frequently asked questions
What is the Baumassenziffer?
It is the ratio between the above-ground building volume and the chargeable land area. The canton defines it in the implementing ordinance of the Baugesetz; the value per zone is found in the municipality’s Baureglement.
Does the Geo-Scanner give the natural ground level?
It gives the altitude and a profile taken from the swisstopo terrain model, for guidance only. The relevant natural ground for heights and volumes is established by the surveyor.
Where can I read the restrictions that burden the plot?
In the ÖREB cadastre of Appenzell Outer Rhodes, available from the cantonal geoportal. Private-law easements are found in the land register.
Is a plot with no building zone shown buildable?
If no harmonised building zone appears, the plot is probably outside the zone. A project there falls under a special cantonal procedure: check this with the municipality and the canton before any bid.