The canton of Glarus governs planning and building through the Raumentwicklungs- und Baugesetz (RBG, spatial development and building act) of 2 May 2010. Since the merger of municipalities, the canton has only three municipalities, each with its own building regulations (Baureglement) and zoning plan. Their land-use measures differ: one of these regulations keeps the Ausnützungsziffer (AZ, floor area ratio), another has replaced it with other volume rules. The canton’s membership of the intercantonal agreement harmonising building terms (IVHB / AIHC) should be checked in the Glarus collection of laws.
The Geo-Scanner locates the plot by address, number and municipality, EGRID or coordinates. Its sheet gives the area calculated from the geometry, the status of the canton’s ÖREB cadastre (public-law restrictions on landownership) with the link to the extract when it is published, the ARE harmonised building zone, the nearest watercourse and its distance, and the national avalanche and rockfall hazard indications (SilvaProtect). The cantonal geoportal geo.gl.ch, run by the Fachstelle Geoinformation, then publishes the official layers, including the groundwater protection zones that are part of the Glarus ÖREB cadastre.
Worked example: usable area of a plot in Glarus next to a stream
A 900 m² plot in a residential zone, on the valley floor. The Geo-Scanner shows a stream about 18 m away. The applicable municipal regulations use an Ausnützungsziffer (AZ) here, with an example value of 0.50. We assume that a 70 m² strip lies within the space reserved for waters set by the canton and does not count in the relevant area: an assumption to be checked, as the exact rule is in the municipal regulations and the RBG.
| Item | Calculation | Value |
|---|---|---|
| Plot area | Geo-Scanner, indicative | 900 m² |
| Share within the space reserved for waters | assumption | 70 m² |
| Relevant area used | 900 − 70 | 830 m² |
| Chargeable floor area (AZ 0.50) | 830 × 0.50 | 415 m² |
| Difference with a calculation on the whole plot | 450 − 415 | 35 m² |
| Average ground slope | 6 m over 40 m | 15 % (8.5°) |
On the whole plot, the example index would give 900 × 0.50 = 450 m² of chargeable floor area. If the strip near the stream is excluded, 830 m² remain and 830 × 0.50 = 415 m², i.e. 35 m² less. The slope profile drawn over 40 m between the road and the foot of the slope shows 6 m of height difference: 6 ÷ 40 = 15 %, about 8.5°. The altitude read at the centre of the plot is 480 m.
A 15 % slope weighs on earthworks, retaining walls and machine access; the bid must take it into account. The exact area, the width of the space reserved for waters and the real index value are confirmed with the official extract, the cantonal geoportal and the municipality’s regulations.
Assuming a 70 m² strip linked to the watercourse, the plot goes from 450 to 415 m² of chargeable area: a difference to check before buying or costing.
3 frequent pitfalls before buying or costing a plot in Glarus
Applying a neighbouring municipality’s rule
The canton’s three municipalities do not have the same land-use measures: an Ausnützungsziffer in one, volume rules in another. Read the building regulations of the municipality concerned, in the version in force.
Underestimating the natural hazards of the slope
Avalanches, rockfall and floods mark the Glarus valleys. The Geo-Scanner’s SilvaProtect and surface runoff layers are indicative; the cantonal hazard map and a specialist’s opinion decide the protection measures and their cost.
Forgetting the distance to the watercourse
The space reserved for waters and groundwater protection zones can reduce the buildable area or impose conditions. The Geo-Scanner gives the distance to the watercourse; the exact width is checked in the canton’s ÖREB cadastre.
How to use it in 3 steps for a plot in the canton of Glarus
- Locate the plot and read its sheet
Search for the plot by address, number with the municipality or EGRID. Note the indicative area, the harmonised zone and the nearest watercourse. - Display the hazard layers
Turn on the avalanche, rockfall and surface runoff layers, read them with their official legend, then open the ÖREB cadastre and the cantonal geoportal for the official data. - Measure the slope and export
Draw a profile between the access and the high point of the plot, note the altitude, then copy the report or export the CSV for your file.
What the Geo-Scanner does not do for a plot in Glarus
The Geo-Scanner does not read the content of the ÖREB restrictions and does not show the canton’s groundwater protection zones, the cantonal hazard map, the noise sensitivity level or easements in the land register. It does not calculate any index: the calculation is done by hand with the municipal regulations. Searches go to the public swisstopo API and nothing is stored.
For the next stage of the project, Portail chantier gathers the file (extracts, plans, permits) and shares it with the client. ERP Art Construction costs bids, tracks the site and the invoicing, and opens each site with its own sheet.
Frequently asked questions
Which act applies to building in the canton of Glarus?
The Raumentwicklungs- und Baugesetz (RBG) of 2 May 2010, completed by each municipality’s building regulations. The text in force is consulted in the canton’s official collection of laws.
Does the canton of Glarus use the Ausnützungsziffer (AZ)?
It depends on the municipality: one set of municipal regulations keeps the Ausnützungsziffer, another has replaced it with other volume rules. Check the regulations of the municipality where the plot lies.
Where can I find the Glarus ÖREB cadastre?
The ÖREB cadastre is published by the canton on its geoportal geo.gl.ch. The Geo-Scanner shows its status and offers the link to the plot’s extract when it is available.
Is the Geo-Scanner avalanche layer enough for a permit?
No. The SilvaProtect indications are national and indicative. The canton’s hazard map and a specialist’s opinion determine whether protection measures are required.