Costing specifics for CFC 112: Demolition & deconstruction
CFC 112 covers careful dismantling, selective deconstruction, the demolition of load-bearing or secondary structures, as well as on-site sorting, packaging and removal of waste to authorised disposal routes. Reference collective agreement in the Studio: CN (National Collective Agreement, main construction trades). The Studio’s default measurement unit is m³; the figures below are those of the Studio’s latest update, with Vaud as the starting canton.
Bulk demolition is usually quantified per m³ of structure in place, whereas sawing, core drilling and cutting are assessed per linear metre or per m² depending on the thickness. The selective removal of equipment or individual elements is often priced per piece or as a lump sum. Transport and landfill are generally measured per tonne or per m³ of bulked material. It is useful to state in your offer whether the volumes shown correspond to the theoretical dimensions before demolition or to the bulked volume transported, in order to limit disagreements at the final account.
| Item | Value in the Studio |
|---|---|
| CFC code | 112 |
| Title | Demolition & deconstruction |
| Reference collective agreement | CN (National Collective Agreement, main construction trades) |
| Default measurement unit | m³ |
| VAT applied | 8.1% |
Items often forgotten in a quote for demolition work
- Dust-protection installations and the airtight containment of adjoining occupied areas
- Thorough selective sorting on site and landfill charges for each specific disposal route
- The temporary safety shoring that is essential before deconstruction operations begin
- The extra cost of manual removal caused by narrow access or the lack of a site hoist.
- Regular cleaning of the external access routes and keeping the surroundings clean
Neighbouring trades
A building site involves several trades in succession, and each line of a quote carries its own CFC code: you can therefore combine several trades in a single document. Here are the other Studio codes attached to the same cost profile, with their default unit.
| CFC | Title | Default unit | Page |
|---|---|---|---|
| 201 | Earthworks & excavation | m³ | Quote CFC 201 |
| 211 | Masonry & structural work | m² | Quote CFC 211 |
SIA 118 clauses, retention and SUVA safety
SIA standard 118 formally governs the contractual relationship, providing clear rules for settlement according to actual measurement as well as a rigorous procedure for acceptance of the work. It defines how defects are to be notified and establishes a two-year defects notification period for reporting anomalies after completion of the services. This protective set of rules only takes effect, however, if your contract or the specification expressly declares it applicable between the client and your company.
SIA 118 as contractual basis
Tick box (unticked by default).
SIA standard 118 “General Conditions for Construction Work” forms part of the contract, in addition to the Swiss Code of Obligations.
Asbestos and pollutants
Ticked by default.
Reservation in the event of asbestos or other pollutants not detected before the work (OTConst).
Rise in material prices
Ticked by default.
Reservation for increases in material prices according to the KBOB indices in force.
Pricing method
Your choice, when printing.
Unit prices, settlement according to actual measurement (Art. 374 CO) — or fixed lump-sum price (Art. 373 CO).
Retention
On deconstruction sites, the client may frequently ask for financial security. Our tool lets you set a retention of 0 to 10% directly on each monthly interim payment and on the final account. Depending on the special clauses of the contract, this retention may be released on acceptance or replaced by a bank or insurance guarantee of an equivalent amount provided by the contractor. In the Studio’s copilot, the retention (SIA 118) can be set to 0, 5 or 10% of the total incl. VAT, with 10% as the default; cash discount and retention reduce what you actually collect, whereas the discount and the pro-rata account reduce the quote itself.
Safety: what SUVA accident insurance costs
Occupational accident insurance (SUVA) is paid entirely by the employer: 6.2% of gross pay for the Main construction trades CN profile in the Studio. For an employee earning CHF 6'350 a month, that is CHF 393.70 a month at your expense, before a single hour has been worked. This premium is part of the 34% of charges that the Studio builds into your daywork rate.
Daywork and profitability: the real cost of one hour of demolition work
The most common trap: invoicing on the basis of the hourly wage. An employee with the “Experienced qualified bricklayer (class Q)” profile earns CHF 6'350 a month, i.e. CHF 36.08 over 176 paid hours. Once charges of 34.8% (Vaud) and CHF 616 of monthly expenses (meals, travel, equipment) are added, and the result is divided by the 135 genuinely productive hours, one hour costs CHF 67.97, before overheads and margin. You pay for every hour, but you invoice only part of them.
| Step | Hours |
|---|---|
| Paid hours (176 h × 12 months) | 2'112 |
| Holidays (25 days) | −212 |
| Public holidays (9 days) | −76 |
| Sickness / accident absences (average) | −68 |
| Depot preparation, loading, travel and bad weather | −136 |
| Productive hours used by the Studio | 1'620 |
How to read this table. Start from the 2'112 paid hours and take away holidays, public holidays, absences and time spent at the depot, loading and travelling: 1'620 billable hours remain, i.e. 77% of paid time.
When to invoice on a daywork basis
Daywork is often suitable for unforeseen work discovered in the course of the site, such as hidden structures, delicate unplanned removals or cleaning ordered by site management. To secure your payment, have your daywork sheets countersigned every day by the client’s representative. Depending on the contractual arrangements, fuel, heavy plant, specialist tools and travel are added to the labour hours.
| Profile | Average gross monthly pay | Daywork rate |
|---|---|---|
| Foreman / site supervisor (class V) | 7'250 CHF | 122.00 |
| Experienced qualified bricklayer (class Q) | 6'350 CHF | 108.00 |
| Qualified bricklayer / recent graduate (class A) | 6'000 CHF | 102.00 |
| Skilled worker / federal certificate holder (class B) | 5'650 CHF | 96.00 |
| Labourer / site assistant (class C) | 5'100 CHF | 88.00 |
How to read this table. Vaud is the reference canton (coefficient 0%). Gross monthly pay is the average wage for the profile; the daywork rate is the hourly rate to invoice, excluding VAT. In another canton, the daywork rate is multiplied by the regional coefficient: the “Experienced qualified bricklayer (class Q)” profile goes from CHF 108.00/h in Vaud to CHF 120.95/h in Geneva (+12%). See the page for the canton of Geneva.
Frequently asked questions about quotes for demolition work (CFC 112)
How do you correctly estimate bulking in demolition & deconstruction?
The change from the compact structure in place to broken rubble considerably increases the apparent volume to be loaded. One cubic metre of demolished concrete or masonry produces a larger volume once bulked in a skip. Calculate your transport costs and your lorry trips on the basis of this real bulked volume, while checking the permissible axle load in order to avoid overloading the vehicles.
What health measures should be planned for when building pollutants are present?
Before any work, the client must provide a technical survey of pollutants such as asbestos, PCBs or lead. If hazardous substances are detected, apply the directives issued by SUVA. Asbestos removal or remediation work requires defined containment protocols, suitable protection and removal to approved disposal routes, and is best shown as specific items in the quote in accordance with the applicable rules.
How should temporary shoring be handled in the tender?
The shoring needed to keep the building stable during demolition is not generally included by implication. Describe it in a separate item, stating how long the props, shoring towers or needle beams will be made available. If the loads require validation by a civil engineer appointed by site management, it is advisable to specify the limits of your company’s involvement.
Who is responsible for managing access and permits for occupying the public highway?
Placing a skip or a rubble chute, or parking plant on municipal public land, requires prior authorisation issued by the competent local authority. State expressly in your offer whether the administrative formalities, the temporary signage plan and the payment of municipal fees are borne by the company or recharged directly to the client in the account.
From quote to site
Studio Devis Suisse is free and is enough for a one-off quote. When your quotes multiply, two tools take over where the Studio stops: the full price list to cost faster, then site tracking to check the real margin, hour after hour.
The same trade in the 26 cantons
The regional coefficient, the charges and the family allowances change from one canton to another: open the page for the canton of your site to see the daywork rate and the charges that apply there.
- Vaud (VD)
- Geneva (GE)
- Valais (VS)
- Fribourg (FR)
- Neuchâtel (NE)
- Jura (JU)
- Bern (BE)
- Zurich (ZH)
- Zug (ZG)
- Basel-Stadt (BS)
- Basel-Landschaft (BL)
- Aargau (AG)
- Solothurn (SO)
- Lucerne (LU)
- Schwyz (SZ)
- Nidwalden (NW)
- Obwalden (OW)
- Uri (UR)
- St. Gallen (SG)
- Thurgau (TG)
- Schaffhausen (SH)
- Appenzell Ausserrhoden (AR)
- Appenzell Innerrhoden (AI)
- Glarus (GL)
- Graubünden (GR)
- Ticino (TI)