Costing specifics for CFC 201: Earthworks & excavation
CFC 201 covers bulk excavation, trench digging, temporary earth support, as well as backfilling, levelling and the removal of soil and excavated material. Reference collective agreement in the Studio: CN (National Collective Agreement, main construction trades). The Studio’s default measurement unit is m³; the figures below are those of the Studio’s latest update, with Vaud as the starting canton.
The bulked or in-place volume per cubic metre (m³) is the usual unit for earthworks according to the standard item catalogues. Topsoil stripping and slope trimming are commonly expressed per square metre (m²), whereas narrow trenches or pipe runs use the linear metre (lm). Complex trench shoring or the crossing of obstacles is often dealt with as a lump sum or per piece. To prevent disputes with site management at the final account, define explicitly whether the volumes are based on the theoretical profile of the construction drawings or on jointly agreed topographical surveys.
| Item | Value in the Studio |
|---|---|
| CFC code | 201 |
| Title | Earthworks & excavation |
| Reference collective agreement | CN (National Collective Agreement, main construction trades) |
| Default measurement unit | m³ |
| VAT applied | 8.1% |
Items often forgotten in a quote for earthworks
- Cantonal landfill charges and environmental analyses of polluted soils
- Pumping out surface water inflows or groundwater
- Reinstating the access roads and cleaning the site tracks
- Additional excavation depth made necessary by unexpectedly poor bearing capacity of the ground.
- Bringing in, taking away and assembling the trench shoring or heavy excavators
Neighbouring trades
A building site involves several trades in succession, and each line of a quote carries its own CFC code: you can therefore combine several trades in a single document. Here are the other Studio codes attached to the same cost profile, with their default unit.
| CFC | Title | Default unit | Page |
|---|---|---|---|
| 112 | Demolition & deconstruction | m³ | Quote CFC 112 |
| 211 | Masonry & structural work | m² | Quote CFC 211 |
SIA 118 clauses, retention and SUVA safety
SIA standard 118 governs the arrangements for jointly agreed measurement that are essential for earthworks, while structuring the formal acceptance of the work and the notification of defects as soon as the excavation is completed. It also sets the principle of a two-year defects notification period for reporting any defective work. This standard protects the contractor against late claims concerning the geometry of the slopes, but it only applies if the contract for work and services expressly declares it applicable between the parties.
SIA 118 as contractual basis
Tick box (unticked by default).
SIA standard 118 “General Conditions for Construction Work” forms part of the contract, in addition to the Swiss Code of Obligations.
Asbestos and pollutants
Ticked by default.
Reservation in the event of asbestos or other pollutants not detected before the work (OTConst).
Rise in material prices
Ticked by default.
Reservation for increases in material prices according to the KBOB indices in force.
Pricing method
Your choice, when printing.
Unit prices, settlement according to actual measurement (Art. 374 CO) — or fixed lump-sum price (Art. 373 CO).
Retention
On monthly interim payments and on the final account, the client often applies a retention. In our tool, this amount can be set from 0 to 10% of the value of the services excluding VAT. Depending on the clauses of the contract, this deduction may be released on the agreed date or replaced as soon as the work is finished by a bank guarantee certificate or a performance insurance bond. In the Studio’s copilot, the retention (SIA 118) can be set to 0, 5 or 10% of the total incl. VAT, with 10% as the default; cash discount and retention reduce what you actually collect, whereas the discount and the pro-rata account reduce the quote itself.
Safety: what SUVA accident insurance costs
Occupational accident insurance (SUVA) is paid entirely by the employer: 6.2% of gross pay for the Main construction trades CN profile in the Studio. For an employee earning CHF 6'350 a month, that is CHF 393.70 a month at your expense, before a single hour has been worked. This premium is part of the 34% of charges that the Studio builds into your daywork rate.
Daywork and profitability: the real cost of one hour of earthworks
The most common trap: invoicing on the basis of the hourly wage. An employee with the “Experienced qualified bricklayer (class Q)” profile earns CHF 6'350 a month, i.e. CHF 36.08 over 176 paid hours. Once charges of 34.8% (Vaud) and CHF 616 of monthly expenses (meals, travel, equipment) are added, and the result is divided by the 135 genuinely productive hours, one hour costs CHF 67.97, before overheads and margin. You pay for every hour, but you invoice only part of them.
| Step | Hours |
|---|---|
| Paid hours (176 h × 12 months) | 2'112 |
| Holidays (25 days) | −212 |
| Public holidays (9 days) | −76 |
| Sickness / accident absences (average) | −68 |
| Depot preparation, loading, travel and bad weather | −136 |
| Productive hours used by the Studio | 1'620 |
How to read this table. Start from the 2'112 paid hours and take away holidays, public holidays, absences and time spent at the depot, loading and travelling: 1'620 billable hours remain, i.e. 77% of paid time.
When to invoice on a daywork basis
Daywork applies to technical contingencies, such as encountering buried boulders, discovering unrecorded pipes or the manual clearing of water infiltration. The work must be recorded on daily daywork sheets, checked and signed by site management. In addition to the machine-operating hours under the National Collective Agreement, the quote will state how site plant, fuel and the associated travel are invoiced.
| Profile | Average gross monthly pay | Daywork rate |
|---|---|---|
| Foreman / site supervisor (class V) | 7'250 CHF | 122.00 |
| Experienced qualified bricklayer (class Q) | 6'350 CHF | 108.00 |
| Qualified bricklayer / recent graduate (class A) | 6'000 CHF | 102.00 |
| Skilled worker / federal certificate holder (class B) | 5'650 CHF | 96.00 |
| Labourer / site assistant (class C) | 5'100 CHF | 88.00 |
How to read this table. Vaud is the reference canton (coefficient 0%). Gross monthly pay is the average wage for the profile; the daywork rate is the hourly rate to invoice, excluding VAT. In another canton, the daywork rate is multiplied by the regional coefficient: the “Experienced qualified bricklayer (class Q)” profile goes from CHF 108.00/h in Vaud to CHF 120.95/h in Geneva (+12%). See the page for the canton of Geneva.
Frequently asked questions about quotes for earthworks (CFC 201)
How do you secure the volume calculation for earthworks & excavation with site management?
The most rigorous method is to have a survey of the natural ground validated by a surveyor before any work. The final volumes must be calculated from the theoretical profiles of the project or by comparing digital terrain models. In this way you avoid any dispute over natural settlement or intermediate earth movements when the account is drawn up.
Who bears the extra cost linked to the presence of water in the excavation?
If the geotechnical report did not announce groundwater or any particular water inflow, these constraints may constitute varied or unforeseen work according to the contract and the applicable rules. Dewatering, the installation of pumps and the treatment of sludge must be covered by a written variation or charged as daywork with the prior agreement of site management.
What precautions should be taken for sending excavated material to landfill?
It is useful to request soil analyses beforehand in order to determine the hazard class of the materials. Without an environmental report provided by the client, make an explicit reservation in your offer by basing your prices on unpolluted soil. Any discovery of pollutants leads to specific disposal routes and much higher landfill charges, which must be passed on.
How do you price the need for temporary shoring of the excavation walls?
According to the contract and the safety rules in force under the OTConst, excavations may require battering or shoring beyond a certain depth. If the layout of the site does not allow free slopes, the earth-support system must be priced separately per square metre or as a lump sum, including installation, maintenance during the works and extraction.
From quote to site
Studio Devis Suisse is free and is enough for a one-off quote. When your quotes multiply, two tools take over where the Studio stops: the full price list to cost faster, then site tracking to check the real margin, hour after hour.
The same trade in the 26 cantons
The regional coefficient, the charges and the family allowances change from one canton to another: open the page for the canton of your site to see the daywork rate and the charges that apply there.
- Vaud (VD)
- Geneva (GE)
- Valais (VS)
- Fribourg (FR)
- Neuchâtel (NE)
- Jura (JU)
- Bern (BE)
- Zurich (ZH)
- Zug (ZG)
- Basel-Stadt (BS)
- Basel-Landschaft (BL)
- Aargau (AG)
- Solothurn (SO)
- Lucerne (LU)
- Schwyz (SZ)
- Nidwalden (NW)
- Obwalden (OW)
- Uri (UR)
- St. Gallen (SG)
- Thurgau (TG)
- Schaffhausen (SH)
- Appenzell Ausserrhoden (AR)
- Appenzell Innerrhoden (AI)
- Glarus (GL)
- Graubünden (GR)
- Ticino (TI)