The canton of Neuchâtel regulates energy through its cantonal energy act (LCEn) and its implementing regulation. According to the official fact sheet of the energy and environment office (SENE), outdoor air/water heat pumps, and ground/water or water/water units installed wholly or partly outdoors, fall under the simplified building permit procedure (Article 4e, paragraph 2, letter j of the implementing regulation of the building act). The required annexes are submitted with the application, depending on the type of unit. The SENE points out that an air/water heat pump generates noise in operation and publishes a fact sheet on this subject.
Art Construction's heat pump, noise and solar studio contains a reference station in Neuchâtel. It sizes the unit according to SIA 384/201, from consumption or from floor area and building condition, calculates noise with the method of Cercle Bruit implementation guide 6.21 and estimates photovoltaic yield and self-consumption. It has no Neuchâtel subsidy scale: the canton's subsidy programme publishes its measures each year, and you enter the official amount.
Worked example: a 1990s house in a mixed zone in Neuchâtel
A house in Neuchâtel with 160 m² of energy reference area, built in the 1990s with replaced windows, four occupants, radiators. Studio reference station for the canton: 430 m, design temperature −8 °C, irradiation 1,180 kWh/m² per year. The unit is placed in a corner, 8 m from the neighbouring window, in a mixed zone with sensitivity level III (example value).
| Step | Input | Calculation | Result |
|---|---|---|---|
| Heat demand | 160 m², 55 W/m² at −8 °C, 4 occupants | 160 × 55 ÷ 1,000 + 4 × 0.2 | 9.60 kW |
| Unit selected | outdoor air/water, radiators 55 °C | the 10 kW model is not enough | 13 kW model (11.5 kW at 55 °C) |
| Night-time noise | LWA 53 dB(A), corner, 8 m | 53 − 11 + 9 − 18.1 + 10 + 2 | Lr = 44.9 dB(A) |
| OPB comparison | DS III, night | planning value 50 dB(A) | margin of 5.1 dB |
| Solar | 9 kWp, east-west 15° | 9 × 1,180 × 0.96 × 0.84 | 8,564 kWh per year |
The floor-area method starts from 55 W/m² at −8 °C for a house from 1980 to 2000 with replaced windows. As the station is precisely at −8 °C, no temperature correction is needed: 160 × 55 ÷ 1,000 = 8.8 kW, plus 0.8 kW for hot water for four occupants, i.e. 9.60 kW. With radiators at 55 °C, the 10 kW model only delivers 8.8 kW: the studio selects the 13 kW model (11.5 kW), whose night-time sound power is 53 dB(A).
In a corner, at 8 m: 53 − 11 + 9 − 20 × log(8) + 10 + 2 = 44.9 dB(A). For level III, the margin of 5.1 dB gives green status; for level II, the same location would be just below 45 dB(A) and in orange status. Nine kWp east-west at 15° produce about 8,564 kWh per year. Lowering the flow temperature, for example by replacing a few radiators, would allow a smaller, quieter unit.
The house needs 9.6 kW; with radiators at 55 °C, the 13 kW model is required, which stays at 44.9 dB(A) at night in a corner 8 m away.
3 common mistakes for a heat pump and solar in Neuchâtel
Keeping a high flow temperature without checking it
At 55 °C, the unit delivers less output than at 35 °C: a larger, noisier model with a lower SCOP is needed. Check whether a few enlarged radiators would allow the flow temperature to be lowered.
Forgetting the annexes of the simplified procedure
The SENE fact sheet lists the annexes required according to the type of unit. An incomplete file delays approval: prepare the data sheet, the site plan and the noise calculation before submission.
Copying last year's subsidy amount
The Neuchâtel subsidy programme publishes its measures each year. Read the version in force and submit the application before work starts, according to the programme's conditions.
Using the studio in 3 steps: heat pump, noise and solar in Neuchâtel
- Start from floor area and envelope
Choose the Neuchâtel station, enter the energy reference area, the envelope condition and the number of occupants. Compare with fuel consumption if you know it. - Compare 35 °C and 55 °C
Change the emitters to see the effect of the flow temperature on the model and the noise. Place the unit and the neighbouring window, then read the night-time Lr. - Add solar and prepare the application
Enter the panels and the household consumption. Print the sheet and plan, and enclose them with the annexes of the simplified permit application.
What the free version does not do for a project in Neuchâtel
The studio submits no permit application, notification or subsidy application. It replaces neither the official noise assessment nor the installer's calculation, and it does not know the sensitivity level of the plot, set by the zoning plan. It has no Neuchâtel subsidy scale and gives no official amount.
Soumissions takes the unit, the radiators and the panels into a quotation with the price database; the ERP tracks the job and invoicing; Portail chantier files the annexes and the noise assessment. The related pages also point to the Geo-Scanner page for the canton of Neuchâtel.
Frequently asked questions
What procedure applies to an outdoor heat pump in the canton of Neuchâtel?
According to the SENE's official fact sheet, the simplified building permit procedure, with annexes that depend on the type of unit. The municipality and the SENE provide the up-to-date list.
Is heat pump noise checked?
Yes: the federal Noise Abatement Ordinance applies, and the SENE publishes a fact sheet on heat pump noise. The studio calculates the night-time Lr with the Cercle Bruit method.
Is a permit needed for rooftop solar panels?
An installation sufficiently adapted to the roof is in principle subject to notification under Article 18a LAT. Cultural heritage and protected sites still require a permit: check the procedure with the municipality.
Where can up-to-date subsidies be found?
In the subsidy programme published each year by the canton. The studio sets no cantonal amount: you enter the one from the programme in force, and the application is submitted before work starts.