The canton of St. Gallen regulates energy through its energy act (Energiegesetz, sGS 741.1). For an air-to-water heat pump, the canton applies the Cercle Bruit noise certificate used throughout Switzerland, and cantonal case law treats it as a document of the building permit application. The cantonal parliament has asked for simpler procedures, but as a general rule these units remain subject to a permit: the municipality confirms the procedure. The canton’s energy agency has published explanations on declaring heat pumps, valid from 2025, which recall the amendment of the Noise Abatement Ordinance that came into force on 1 November 2024. For rooftop solar, the canton provides a notification form and explanations.
The Art Construction heat pump, noise and solar studio prepares these items in your browser. It sizes the unit from the heated area or the consumption, calculates the night-time Lr at the neighbour’s window using the Cercle Bruit method, compares it with the planning value and estimates photovoltaic yield. It offers a St. Gallen reference station (670 m, θe,norm −10 °C).
Worked example: a St. Gallen house in a mixed zone with underfloor heating
A 1990s house with 160 m² of energy reference area, replaced windows, underfloor heating, 4 occupants, in a mixed zone with noise sensitivity level III. The studio’s reference station for the canton: 670 m, −10 °C, 1,150 kWh/m² per year. Example values.
| Item | Input | Calculation | Result |
|---|---|---|---|
| Demand from the area (55 W/m² at −8 °C) | 160 m², θe −10 °C | 160 × 55 ÷ 1,000 × 30 ÷ 28 | 9.43 kW |
| Hot water, 4 occupants | 0.2 kW per person | 4 × 0.2 | 0.8 kW, total 10.23 kW |
| Output to guarantee at −7 °C (floor 35 °C) | 10.23 kW | 10.23 × 27 ÷ 30 | 9.21 kW |
| Template selected by the studio | outdoor air-to-water | 9.7 kW at 35 °C | night LWA 51 dB(A) |
| Night-time rating level, window at 6 m | against a façade | 51 − 11 + 6 − 15.56 + 12 | Lr 42.4 dB(A) for VP 50 |
| East-west photovoltaics 15° | 24 modules, 10.8 kWp | 10.8 × 1,150 × 0.96 × 0.84 | 10,015 kWh per year |
The default specific load for a building from 1980 to 2000 (55 W/m² at −8 °C) is brought back to the local temperature: 160 × 55 ÷ 1,000 × (20 + 10) ÷ 28 = 9.43 kW, plus 0.8 kW for hot water, giving 10.23 kW. Under test conditions (−7 °C), the unit must deliver 10.23 × 27 ÷ 30 = 9.21 kW: the 9.7 kW template at 35 °C is suitable. Night noise: 51 − 11 + 6 (against a façade) − 20 × log(6) = 30.4 dB(A), plus 10 dB (night K1) and 2 dB (K2): Lr = 42.4 dB(A).
In sensitivity level III, the night-time planning value is 50 dB(A): a 7.6 dB margin, green status. If the neighbour lives in a residential zone (level II, 45 dB(A)), the margin falls to 2.6 dB: amber status, and the precautionary principle calls for moving the unit or planning silent mode. The east-west panels produce 10.8 × 1,150 × 0.96 × 0.84 = 10,015 kWh per year.
The 9.7 kW unit meets the planning value in a mixed zone, but the margin would be small in a residential zone: check the neighbour’s sensitivity level.
3 common mistakes before installing a heat pump in St. Gallen
Submitting the permit application without a noise certificate
The Cercle Bruit certificate is part of the file: without it, the municipality cannot decide. Attach the form with the site plan, the unit’s data sheet and the neighbouring windows taken into account.
Ignoring the sensitivity level of the neighbouring plot
The planning value depends on the neighbour’s sensitivity level, not yours. Between a residential zone and a mixed zone, the difference is 5 dB: read the municipal zoning plan before placing the unit.
Forgetting cascaded units
Two identical units add 3 dB to the sound power level. The cantonal explanations cover this case: enter the number of units in the studio to see the effect on Lr.
How to use it in 3 steps for a house in St. Gallen
- Choose the station and enter the demand
Use the St. Gallen reference station or a free entry for a house at a higher altitude. Enter the area and the condition of the building, or the current consumption, and the number of occupants. - Assess the noise at each neighbour
Place the unit and each neighbouring window with its sensitivity level. Compare the night Lr with the planning value and test another position or silent mode. - Add the solar system and print
Enter the modules and the orientation, read the yield and the self-consumption, enter the published cantonal subsidy amount, then print the sheet to attach to your working file.
What the free studio does not do in St. Gallen
The studio does not complete the official noise certificate form and submits no permit, no solar notification and no subsidy application. It does not know the sensitivity level of the plot and includes no St. Gallen subsidy scale: enter the amount published by the canton. The Geo-Scanner page for St. Gallen helps you read the plot’s zone.
Portail chantier files the certificate, plans and sheets by site and shares them with the client. Soumissions takes the output and the quantities into your bid; the Art Construction ERP tracks the installation, the hours and the invoicing.
Frequently asked questions
Does an air-to-water heat pump need a permit in St. Gallen?
As a general rule, yes: the canton has not made notification the standard for these units, and the noise certificate is part of the application. The municipality confirms the procedure for your project.
Which noise certificate does the canton use?
The Cercle Bruit noise certificate, used throughout Switzerland. The explanations of the cantonal energy agency cover apartment buildings, noise-sensitive rooms and cascaded units.
How are rooftop solar panels notified?
An installation sufficiently adapted to the roof in a building or agricultural zone falls under notification (Article 18a LAT). The canton publishes a notification form and explanations; cultural monuments remain subject to a permit.
When should the subsidy application be submitted?
As a general rule before work begins, on the canton’s support portal. The studio shows no amount for St. Gallen: enter the one from the programme in force.