Air-to-water heat pump and solar in Thurgau: OPB noise, permit and notification

In Thurgau, the air-to-water heat pump is handled with the permit application to the municipality, and rooftop solar is notified 20 days before work begins.

Open the free studio →

Free, no account: your data stays in your browser. Indicative results, to be confirmed by the installer and the cantonal office.

The canton of Thurgau regulates energy through the energy use act (Energienutzungsgesetz, ENG, RB 731.1), in force since 2005; a revision was proposed in a dispatch of 1 April 2025, and its outcome is to be checked in the cantonal statute book. According to the cantonal fact sheet on using ambient heat, an air-to-water heat pump is subject to authorisation by the municipality and is generally handled with the building permit application; the noise certificate is part of it. Replacing a heat generator is documented with the cantonal energy compliance form.

For solar, the canton has anchored the notification under Article 18a LAT in § 52b of its planning and building act: the form of the spatial development office is submitted to the authority that grants permits, 20 days before work begins. The Art Construction heat pump, noise and solar studio prepares both parts, with the nearest reference station (410 m, θe,norm −9 °C) or a free entry.

Worked example: a large oil-heated house in a mixed zone

A house heated with oil through a condensing boiler, with radiators, in a mixed zone with noise sensitivity level III, the unit against a façade 9 m from the neighbour’s window. The studio’s nearest station: 410 m, −9 °C, 1,150 kWh/m². Example values.

Heat pump and solar for a house in Thurgau (example values)
ItemInputCalculationResult
Oil consumed (condensing)2,800 l per year2,800 × 10 × 0.92 ÷ 2,300 h11.2 kW
Output to guarantee at −7 °C (radiators 55 °C)θe −9 °C11.2 × 27 ÷ 2910.43 kW
Template selected by the studiooutdoor air-to-water11.5 kW at 55 °Cnight LWA 53 dB(A)
Night-time rating level, window at 9 magainst a façade53 − 11 + 6 − 19.08 + 12Lr 40.9 dB(A) for VP 50
Photovoltaics south 30°30 modules, 13.5 kWp13.5 × 1,150 × 1.12 × 0.8414,606 kWh per year

With a condensing boiler, the studio uses an efficiency of 0.92: 2,800 litres × 10 kWh × 0.92 = 25,760 kWh, divided by 2,300 full-load hours: 11.2 kW. Under test conditions: 11.2 × 27 ÷ 29 = 10.43 kW. With radiators at 55 °C, the 11.5 kW template is suitable, for a night sound power of 53 dB(A). Noise: 53 − 11 + 6 − 20 × log(9) = 28.9 dB(A), then 12 dB of night corrections: Lr = 40.9 dB(A).

In level III, the night-time planning value is 50 dB(A): a 9.1 dB margin, green status. If the neighbour were in a residential zone (level II, 45 dB(A)), the margin would be 4.1 dB, still green but close to the precautionary threshold. The solar system produces 13.5 × 1,150 × 1.12 × 0.84 = 14,606 kWh per year. Lowering the flow temperatures, for example after replacing a few radiators, would reduce the output needed from the unit.

An 11.5 kW unit stays 9 dB below the planning value in a mixed zone; the application is submitted to the municipality with the noise certificate.

3 common mistakes before installing a heat pump in Thurgau

Believing an air-to-water heat pump is simply notified

According to the cantonal fact sheet, it is subject to authorisation by the municipality, generally with the permit application. Prepare the noise certificate and the data sheet before ordering.

Notifying the solar system the day before the work

The notification form is submitted 20 days before work begins to the authority that grants permits. Attach a description of the type of installation and how it fits into the roof.

Submitting the subsidy application after work has begun

Thurgau support applications are submitted online on the cantonal portal, before construction starts. Check the conditions of the programme in force.

How to use it in 3 steps for a house in Thurgau

  1. Enter the oil and the boiler
    Enter the average oil consumption over three years and tick the condensing boiler if applicable; choose the type of heat emitters (35 °C or 55 °C).
  2. Assess the noise according to the zone
    Place the unit and each neighbouring window with its sensitivity level (II in a residential zone, III in a mixed zone, to be checked). Read the night Lr and the margin.
  3. Prepare the solar notification and the sheet
    Enter the modules and the orientation, note the output and the yield for the notification form, then print the studio sheet for your file.

Open the free studio →

What the free studio does not do in Thurgau

The studio submits no permit application, no solar notification and no subsidy application, does not replace the official noise certificate and does not know the sensitivity level of the plot. It includes no Thurgau scale: enter the amount from the programme in force. The Geo-Scanner page for Thurgau helps you read the plot’s zone.

Portail chantier files the application, the notification and the sheets by site. Soumissions takes the output and the quantities into your bid; the Art Construction ERP tracks the installation, the hours and the invoicing.

Frequently asked questions

Is a permit needed for an air-to-water heat pump in Thurgau?

According to the cantonal fact sheet, yes: it is subject to authorisation by the municipality and is generally handled with the permit application, noise certificate included.

Which energy act applies?

The energy use act (ENG, RB 731.1). A revision was proposed in 2025: check the version in force in the cantonal statute book.

When should rooftop solar panels be notified?

At least 20 days before work begins, with the cantonal form, to the authority that grants permits (§ 52b of the cantonal act, Article 18a LAT).

Does the studio know the Thurgau subsidies?

No: it estimates the federal Pronovo one-off payment but not the cantonal subsidy. Enter the published amount and submit the application online before work begins.