Air-to-water heat pump and solar in the canton of Ticino: building licence, OPB noise, Len and RUEn

South of the Alps, the mild climate reduces the heat pump output, but the municipal procedure and the noise at the neighbour’s still need careful preparation.

Open the free studio →

Free, no account: your data stays in your browser. Indicative results, to be confirmed by the installer and the cantonal office.

The canton of Ticino applies the cantonal energy act of 8 February 1994 (Legge cantonale sull’energia, Len) and the regulation on energy use (Regolamento sull’utilizzazione dell’energia, RUEn) of 15 March 2023, in force since 1 January 2024, which governs in particular the installation and modification of heating and hot-water systems. For a heat pump, information published by municipalities and by the cantonal energy sector indicates that a building licence is required: the application is submitted to the Municipio with the official form. A simplified check of noise emissions according to Cercle Bruit generally accompanies the file, and the cantonal authority may require a full acoustic report drawn up by a specialist. Practice can vary from one municipality to another: check with the municipal technical office.

For photovoltaics, the cantonal procedure published under the cantonal energy plan provides for a prior notification before work begins, with notification to the municipality under Article 18a LAT, followed by a commissioning notification; in historic centres and on protected buildings, a licence and the opinion of the cultural heritage office may be needed. The Art Construction heat pump, noise and solar studio prepares the figures for this file: the studio’s Ticino station (270 m, θe = −4 °C, irradiation of 1,380 kWh/m²) gives a lower output than north of the Alps, the noise radar compares Lr with the planning value, and the solar tab estimates yield, self-consumption and the Pronovo one-off payment. The studio has no Ticino cantonal scale: enter the verified subsidy amount yourself.

Worked example: replacing an oil boiler with an air-to-water heat pump in Ticino

A detached house at 270 m (the studio’s Ticino station, θe = −4 °C), non-condensing oil boiler, hot water included. Unit in night-time silent mode, mounted on the façade, neighbour’s window at 10 m, sensitivity level II. Example values.

Output, night noise and solar calculated with the studio’s formulas (example values)
ItemValueCalculation
Current useful heat15,300 kWh/year1,800 l × 10 kWh/l × 0.85
Heat pump output6.65 kW15,300 ÷ 2,300 h
Output brought back to −7 °C7.48 kW6.65 × 27 ÷ 24
Night Lr at 10 m, on the façade39.0 dB(A)52 − 11 + 6 − 20 + 10 + 2
Night planning value, level II45 dB(A)OPB, Annex 6
Solar yield, 8 kWp south 30°10,386 kWh/year8 × 1,380 × 1.12 × 0.84

The useful heat comes from the average oil consumption: 1,800 litres × 10 kWh per litre × 0.85 default efficiency, giving 15,300 kWh per year. With 2,300 full-load hours (heating and hot water, below 800 m), the output is 6.65 kW. Unit data sheets give their output at −7 °C, so the studio brings the demand back to that point: 6.65 × 27 ÷ (20 + 4) = 7.48 kW. Ticino’s mild climate pushes this value up compared with the demand at −4 °C, which avoids undersizing the unit.

In silent mode, the unit has a night LWA of 52 dB(A). Mounted on the façade (+6 dB) 10 m from the neighbour’s window (20 × log 10 = 20 dB), it gives Leq = 27.0 dB(A) and Lr = 27.0 + 10 + 2 = 39.0 dB(A), 6 dB below the level II night-time planning value. On the roof, 8 kWp facing due south at 30° produce 10,386 kWh per year thanks to Ticino’s irradiation; the studio derives the self-consumption with the heat pump from it.

A 7.5 kW air-to-water heat pump at the −7 °C point, in night-time silent mode, stays 6 dB below the planning value at the neighbour’s; 8 kWp of solar produce about 10,400 kWh per year.

3 common mistakes with a heat pump or solar in Ticino

Installing the unit without a municipal licence

The available information indicates that a heat pump requires a building licence in Ticino. Submit the application to the Municipio with the noise check before ordering the unit, and check your municipality’s practice.

Using the temperature of a northern station

A Plateau station gives −8 or −9 °C instead of −4 °C: the unit would come out oversized, with short cycles. Choose the Ticino station or enter the real altitude for a colder valley.

Starting the photovoltaics before the prior notification

The published cantonal procedure provides for a prior notification before work begins, then a commissioning notification. Cantonal incentives and the Pronovo payment depend on these steps: check the conditions of the year with the canton.

How to use it in 3 steps for a project in Ticino

  1. Choose the Ticino station and enter the demand
    Open the studio, choose the Ticino station or your postcode, then enter the oil, gas or electricity consumption, or the energy reference area and the condition of the envelope.
  2. Check the noise at the neighbours’
    Place the unit and each window of the neighbours’ noise-sensitive rooms, enter the municipal sensitivity level, the night LWA from the data sheet and the measures (silent mode, enclosure, screen). Aim for a 3 dB margin.
  3. Add the solar system and print the sheet
    Add the photovoltaic array and the electricity demand, read the yield and the self-consumption, enter the verified cantonal subsidy amount, then print the sheet for the licence application and the installer.

Open the free studio →

What the free studio does not do for a project in Ticino

The studio submits neither the licence application, nor the solar notification, nor the incentive application, and it does not replace the signed noise check or an acoustic report required by the canton. It has no Ticino scale and does not know the sensitivity level of the plot; subsidies are as a rule requested before work begins, to be checked with the canton.

With Soumissions, the unit, the acoustic measures and the solar array become bid items with the price database. The ERP tracks the installation, the hours and the invoicing, and Portail chantier files the application, notifications and photos by site.

Frequently asked questions

Is a building licence needed for an air-to-water heat pump in Ticino?

Information published by municipalities and by the cantonal energy sector indicates that a licence is required, with a noise check. Practice can vary: check with the municipality’s technical office.

Which Ticino laws apply to energy?

The cantonal energy act of 8 February 1994 (Len) and the regulation on energy use (RUEn) of 15 March 2023, in force since 1 January 2024. Check the version in force in the cantonal statute book.

How is a photovoltaic installation notified in Ticino?

The procedure published under the cantonal energy plan provides for a prior notification before work begins, notification to the municipality under Article 18a LAT and a commissioning notification. A protected building may require a licence.

Does the studio calculate Ticino subsidies?

No: it has no scale for Ticino. It calculates the Pronovo one-off payment and adds the cantonal amount you enter after checking it.