The canton of Zurich applies its energy act (Energiegesetz, EnerG), amended on 19 April 2021 to regulate the replacement of heat generators: when a boiler is replaced, the renewable solution becomes the rule, subject to the exceptions provided by the act. Since 1 January 2023, many heat pumps have been installed under the notification procedure (Meldeverfahren): indoor units and outdoor air-to-water heat pumps with a volume of no more than 2 m³, according to cantonal information. Whatever the procedure, a noise certificate (Lärmschutznachweis) must be submitted for an air-to-water heat pump; it follows Cercle Bruit implementation guide 6.21, and enforcement lies with the municipalities and private inspection. Solar installations sufficiently adapted to the roof also go through notification to the municipality; a geothermal-probe heat pump additionally requires a water protection authorisation.
The Art Construction heat pump, noise and solar studio follows these steps in the browser. The Zurich reference station provides the altitude (410 m), the design temperature (−9 °C) and the irradiation; tab 1 sizes the heat pump according to SIA 384/201, tab 2 calculates the rating level Lr at each neighbour with the Cercle Bruit method, including for several cascaded units, and tab 3 estimates photovoltaic yield, self-consumption and the Pronovo one-off payment. For Zurich, the studio contains a cantonal scale taken from its specification: starting values, to be checked on the official page of the support programme.
Worked example: two cascaded air-to-water heat pumps for a renovated house in Zurich
A large renovated house with 220 m² of energy reference area, five occupants, at 410 m (the studio’s station, θe = −9 °C). Two identical cascaded units mounted against the façade, neighbour’s window at 9 m, sensitivity level II. Example unit values.
| Item | Value | Calculation |
|---|---|---|
| Output from the area | 10.11 kW | 220 × 40 ÷ 1,000 × 29 ÷ 28 + 5 × 0.20 |
| Output brought back to −7 °C | 9.42 kW | 10.11 × 27 ÷ 29 |
| Increase for two units | +3.0 dB | 10 × log(2) |
| Night Lr at 9 m, on the façade | 44.9 dB(A) | 54 + 3.0 − 11 + 6 − 19.1 + 12 |
| Night planning value, level II | 45 dB(A) | OPB, Annex 6 |
| Solar yield, 9 kWp east-west | 8,346 kWh/year | 9 × 1,150 × 0.96 × 0.84 |
Without reliable bills, the output is based on the area: 220 m² × 40 W/m² (the default load of a renovated envelope, at −8 °C) gives 8.8 kW, corrected for the temperature difference (20 + 9 = 29 K instead of 28 K) and then increased by 0.20 kW per occupant for hot water: 10.11 kW. Brought back to the −7 °C point of unit data sheets, the required output is 9.42 kW. The studio finds no single template and proposes two cascaded units, which adds 10 × log(2) = 3.0 dB to the sound power level.
With a night LWA of 54 dB(A) per unit, façade mounting (+6 dB) and 9 m to the neighbour’s window (20 × log 9 = 19.1 dB), Leq = 32.9 dB(A) and Lr = 32.9 + 10 + 2 = 44.9 dB(A): the 45 dB(A) planning value is met by only 0.1 dB. The status is amber: under the precautionary principle, the authority may require an additional, economically reasonable measure (silent mode, enclosure, another position). On the roof, 9 kWp facing east-west produce 8,346 kWh per year, the basis of the self-consumption calculation.
The two units stay below the night-time planning value, but with a 0.1 dB margin: plan a noise reduction measure before completing the Zurich noise certificate.
3 common mistakes with a heat pump or solar in Zurich
Believing notification exempts you from the noise certificate
The notification procedure simplifies the authorisation, not the acoustics: for an air-to-water heat pump, the Cercle Bruit noise certificate is required in every case. Prepare it before notifying, with the manufacturer’s data sheet and the real distances.
Forgetting the increase for a cascade
Two identical units add 3 dB, four units 6 dB. A house that stays below the limit with one unit can come close to it with two: the studio applies this increase when you enter the number of units.
Ordering the unit before the support application
The Zurich support programme requires the application to be submitted before work begins, with the installation of an air-to-water heat pump counting as the start of work according to the cantonal conditions. Check the conditions of the year on the canton’s website: the amounts change.
How to use it in 3 steps for a project in Zurich
- Calculate the output
Choose the Zurich station or your postcode, then enter the current consumption or the energy reference area and the condition of the envelope. Let the studio propose the unit or use the manufacturer’s data sheet; if it proposes a cascade, check the alternative of a larger unit. - Prepare the noise certificate
Place the unit and the neighbours’ windows on the plan, enter the municipal sensitivity level and the night LWA, then test silent mode, an enclosure or another position until you reach a margin of at least 3 dB. - Add the solar system and print
Add the photovoltaic array and the electricity demand, read the self-consumption, then print the sheet with the formulas: it serves as the basis for the certificate and the notification you will submit to the municipality.
What the free studio does not do for a project in Zurich
The studio submits no notification and no support application and does not replace the signed noise certificate or the private inspection required by the municipality. It does not know the sensitivity level of the plot; its Zurich scales are starting values from its specification, to be checked. A probe heat pump additionally requires the water protection authorisation, which the studio does not handle.
With Soumissions, the unit, the enclosure and the solar array become bid items with the price database. The ERP tracks the installation, the hours and the invoicing, and Portail chantier files the certificate, the notification and the photos by site for the client.
Frequently asked questions
Can an outdoor air-to-water heat pump be notified in Zurich?
Yes, if its volume does not exceed 2 m³ according to cantonal information; indoor units also go through notification. Beyond that, an authorisation procedure applies. Check with the municipality.
Is the noise certificate required with the notification?
Yes. For an air-to-water heat pump, the canton requires a noise certificate under Cercle Bruit implementation guide 6.21, whatever the procedure. The municipality and the private inspection review it.
What does the EnerG say when a boiler is replaced?
Since its 2021 amendment, the Zurich energy act makes renewables the rule when a heat generator is replaced, with exceptions provided by the act. A heat pump meets this requirement; check the details with the cantonal department.
Does the studio know the Zurich amounts?
It contains a starting scale taken from its specification, to be checked. The amounts change from year to year; submit the application on the cantonal platform before work begins.