The 3 Major Site Risks
- Financial / Margin: Hidden slippage of daywork hours and unbilled site supplies, causing direct margin erosion of around 8% to 15% of annual turnover under the accountability rules of the Code of Obligations.
- Legal / Joint Body / SUVA: Unchecked exceeding of overtime caps under the Labour Act and lack of traceability for safety measures required by directive CFST 6508, exposing the company to joint body audits and SUVA orders.
- Administrative / Acceptance: Monthly payment claims blocked by site management and advance payments postponed due to the lack of agreed weekly progress records aligned with standard SIA 118 practice.
In a French-speaking Swiss construction SME employing 5 to 50 people, managing operations solely through the accounting wrap-up provided by your fiduciary is a fatal trap. Financial lag conceals productivity losses until the annual closing, depriving management of any corrective leverage. To ensure profitability and keep the business sustainable amid collective agreement requirements and directive CFST 6508, company heads must establish a tight weekly review routine. This streamlined dashboard relies on five tangible metrics, recorded every Friday in under thirty minutes.
This operational method directly connects site reality with cash flow. It tracks short-term available cash, the ratio of billable productive hours sold, hour budget slippage per job, unbilled work in progress, and the status of critical safety hold points. Unit prices fall under tender pricing, while contractual reservations are tracked on the execution monitoring portal. Wage scales, meanwhile, are governed by collective agreements.
The 5 weekly indicators of the executive dashboard
In an artisanal trade or structural work SME in Switzerland, weekly operational management relies on five physical and financial variables. These metrics are reviewed every Friday afternoon to adjust the schedule for the coming week without waiting for monthly valuations.
1. Billable productive hour rate (Labour yield)
This ratio measures the exact share of paid hours billed to tender items or approved daywork, relative to the total paid volume under art. 319 CO. The calculation excludes non-billable travel time, logistical waiting, and rework on defective elements. For a workshop or installation crew, the break-even target sits between 82% and 88%. Below 80%, each percentage point lost represents a direct, bottom-line loss to the company's gross margin.
2. Overtime volume and balance of banked hours
Accumulating excessive hours jeopardises financial balance and exposes the business to joint commission audits. Art. 73 OLT 1 mandates the precise recording of daily and weekly working time actually performed, including overtime. Logging the total volume of hours worked beyond contractual schedules every Friday helps prevent crew burnout, schedule time off in lieu before bad weather periods, and ensure compliance with maximum working hours under the Labour Act.
3. Outstanding daywork sheets pending sign-off
Works carried out outside the agreed lump sum without written confirmation are the primary cause of disputes at the final account stage. Recording the estimated CHF value of open daywork sheets each week that have not been signed by site management or the client's representative allows you to take action before memories fade. A daywork sheet older than ten days carries a risk of deductions exceeding 40% during final account negotiations.
4. Net available cash and overdue receivables
This figure consolidates the actual bank balance minus immediate liabilities (wages, AVS social security contributions, VAT at 8,1%) and includes overdue client claims. Weekly tracking pinpoints payment delays from the very first day past the agreed due date, making it possible to initiate friendly reminders before issuing formal payment notices. For detailed pricing and quantity breakdown analysis, specialised pricing databases can be accessed in the dedicated module for tenders.
5. Safety compliance rate and CFST 6508 hold points
This barometer logs the number of safety non-conformities identified across all active construction sites: missing edge protection, unsecured tools, or failure to wear personal protective equipment. It also covers administrative or technical hold points (waiting for formwork drawings, missing area handover by another trade) that could halt production in the coming week.
Comparison table of weekly management indicators
| Vital indicator | Frequency & Source | Critical alert threshold | Operational consequence | Immediate corrective action |
|---|---|---|---|---|
| Productive hours sold | Weekly (time reports) | Below 78% of paid time | Margin erosion of 4 500,00 CHF to 9 000,00 CHF per month for 10 workers | Reassign crews, eliminate unoptimised intermediate travel |
| Overtime balances | Weekly (register under art. 73 OLT 1) | Over 25 cumulative hours per employee | Risk of joint commission adjustment, increased fatigue, accidents | Mandatory scheduling of compensatory leave during the current month |
| Unsigned daywork sheets | Weekly (service reports) | Over 5 000,00 CHF pending for more than 7 days | Refusal of recognition by site management, CO dispute | Site visit by the site manager for joint validation |
| Overdue claims > 30 days | Weekly (fiduciary debtors ledger) | Exceeding 15% of average monthly turnover | Cash flow strain for paying social security contributions and suppliers | Hold non-critical deliveries, make formal phone follow-ups |
| CFST 6508 safety deviations | Weekly (site safety walk) | More than 2 major deviations unresolved after 48 hours | Work stoppage ordered by the labour inspectorate or SUVA | Immediate area lockout, remediation before resumption |
Common management pitfalls and financial impacts
The most widespread mistake is delegating productivity analysis solely to your fiduciary during quarterly or annual closing. This time lag prevents any timely response to output drops. An unnoticed slippage of 10 hours per week on a structural work crew generates an extra cost of around 3 800,00 CHF per month.
The second pitfall is accumulating variations without prior agreement. Performing technical adjustments without written confirmation exposes the contractor to outright rejection of billed amounts during final inspection of the works under standard SIA 118, whose contract management procedures are detailed in the execution portal. Staff hiring and wage classification matters fall under the dedicated recruitment section.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and parameters below are illustrative examples designed to model common site situations in French-speaking Switzerland.
Scenario 1: Major renovation of a residential building (Canton of Vaud)
A Vaud plastering and painting contractor with 14 employees is working on the conversion of a rental property in Lausanne. During the Friday check-in, the business owner notices that the billable hour rate on this job has plunged to 71%, alongside 8 400,00 CHF in variations unapproved by local site management. An analysis of daily logs reveals that plasterers are spending two hours each day shifting materials stored by other trades.
Rationale and decision: The manager suspends the removal of third-party obstructions, serves a written disruption notice to the client's representative, and submits standby sheets for signature within 48 hours. The billable hour rate recovers to 84% the following week, protecting an operating margin of 6 200,00 CHF on the partition phase.
Scenario 2: Construction of a timber-frame industrial hall (Canton of Fribourg)
A Fribourg timber construction company with 22 employees is erecting a logistics facility in Bulle. The Friday weekly report shows an accumulation of 140 overtime hours across the entire erection crew, resulting from bad weather earlier in the week, alongside three open non-conformities regarding safe roof access.
Rationale and decision: To comply with the provisions of the Labour Act and the Construction Works Ordinance, the site manager refuses Saturday working. He reschedules a mobile elevating work platform to arrive on Monday morning and plans compensatory time off towards the end of the month. This decision removes the risk of an intervention by the cantonal inspectorate while avoiding wage premiums not accounted for in the initial budget.
Frequently asked questions
How often should the 13-week cash flow forecast be updated?
Updates should be completed every Friday morning with your fiduciary. A payment delay of around 45 000.00 CHF alters cash disbursements. For precise quantity surveying or offer pricing, visit our dedicated section /soumissions/.
How should bad weather hours be logged without skewing productivity rates?
Weather-related downtime is recorded under a separate category in accordance with the Labour Act. The billable hour variance remains calculated against actual productive hours, maintaining an accurate picture of active construction site profitability.
What threshold of unbilled work should trigger an executive alert?
As soon as an approved milestone exceeds seven working days without an invoice, liquidity risks rise. An indicative sum of 25 000.00 CHF tied up affects current operational costs and requires immediate administrative invoicing.
How can safety requirements be met without hurting weekly profitability?
Directive CFST 6508 and the Construction Works Ordinance impose rigorous organisation. Integrating safety toolbox talks into weekly scheduling protects staff and prevents unexpected operating downtimes.
Why keep snagging management separate from the five-figure review?
Defect remediation belongs to contractual execution monitoring. Joint inspection reports and reservations under standard SIA 118 are managed through our dedicated tool in the /portail/ section.
What impact does tracking the five figures have on crew wages?
The weekly dashboard manages overall working hours without changing pay scales. For wage grids under the applicable collective agreement or employment contracts, consult the specialised resources in our /jobs/ section.
Managing a construction SME through weekly measurement
Methodical tracking of your five operational indicators gives you full visibility over actual margins and company solvency. By delegating regular time logging and milestone billing, management can step back from daily emergencies to safeguard ongoing operations. To explore your governance, formal delegations, and Swiss management tools further, consult our complementary guides:
- Organising Your Construction SME to Run Without the Owner: Governance, Delegation, and Executive Autonomy in Switzerland
- Opportunity Cost Calculator for the Business Owner on Site
- Escaping Permanent Operational Firefighting in a Construction SME of 5 to 50 Employees
- Civil and Criminal Liability of the Swiss Business Owner: Making Delegations of Authority Legally Valid
- Building a 1-Page Strategic Plan for a Construction Firm