Tool and user guide

Calculator for Site Working Capital Requirement and Security Reserve in CHF

Calculate the working capital requirement for your sites and your cash reserve in CHF according to standard SIA 118 practices and Swiss law.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Cash shortfall caused by a mismatch between 60-day client collections and 30-day supplier disbursements, tying up around 5% of the contract sum as retention money under standard SIA 118, creating a temporary cash deficit that can reach tens of thousands of francs.
  2. Legal / Joint Body / SUVA: Inability to pay contractual monthly wages or mandatory social contributions on time, exposing the company to strict joint committee audits for non-compliance with remuneration provisions under the Code of Obligations (CO).
  3. Administrative / Handover: Blocked release of retention money or delays in issuing advance payments due to lack of rigorous tracking of progress billings, triggering the 5% per annum default interest set out in art. 104 CO in the event of late settlement of accounts.

In the Swiss construction sector, a full order book does not ensure a firm's financial viability unless backed by rigorous cash management. The structural mismatch between paying fixed overheads, buying materials from suppliers, and actually collecting advance payments from the client constantly drains capital. Without an exact appraisal of the working capital requirement specific to each job, contractors risk having to fund work progress out of equity long before issuing their first progress statement checked by site management.

This calculator determines the exact cash reserve in Swiss francs to hold in your bank accounts to absorb contractual payment terms and build a security reserve proportional to your monthly overheads. Estimating unit prices and detailed quantity surveying are handled on the Soumissions platform, while formal tracking of joint inspection of the works takes place via the site portal. Factoring in standard SIA 118 retention money secures your operating cash flow without compromising your commitments to your fiduciary.

Operating cash requirement calculation mechanics

Financial management of a general contractor or trade specialist relies on accurately anticipating time gaps between incurred expenses and received payments. The calculator's algorithm models this operating cycle from billing flows under standard SIA 118, without transmitting any data to an external server.

To draw up price breakdowns by element or prepare a detailed quote, contractors rely on the platform's Soumissions module. Team wages comply with the minimum wages of the applicable collective agreement, which are monitored via the dedicated personnel module.

Formulas and mathematical breakdown

The calculation is structured around four fundamental financial relationships:

  • Daily operating cost: direct expenses incurred divided by the scheduled duration of operations in calendar days.
  • Payment gap working capital: positive difference between the payment term granted to the client and the credit term granted by suppliers, multiplied by the daily cost. If the supplier term exceeds the client collection term, this gap is set to zero as a matter of accounting prudence.
  • Retention money: fraction temporarily withheld on monthly progress statements, calculated as a percentage of the total contract according to contract terms.
  • Resilience reserve: allocation intended to cover structural overheads, determined by multiplying the target number of weeks by weekly fixed costs (monthly overheads × 12 ÷ 52).

The cumulative funding requirement is obtained by adding the gap-related working capital, the retention money, and the structural reserve. The net operating balance is calculated by deducting this requirement from available cash.

Benchmark parameters for construction SMEs

Operating indicatorObserved rangeTypical calculation basisImpact on liquidityControl method
Client collection period30 to 90 days60 daysLinear rise in outstanding billingTracking payment statements
Supplier payment30 to 60 days30 daysPressure on monthly bank outflowsNegotiating purchasing terms
SIA 118 retention money0% to 10%5 %Gross margin tied up until the final accountReplacement with a joint and several guarantee
Operating reserve4 to 12 weeks8 weeksSafety lockup for wages and rentAdjustment based on seasonality
Monthly fixed costs15 000 to 120 000 CHF45 000 CHFIncompressible disbursements regardless of site contingenciesAdministrative cost control

Full worked example in Swiss currency

Consider a finishing work order of 300 000,00 CHF excluding VAT, with estimated direct costs of 240 000,00 CHF excluding VAT over an execution period of 120 days. The client collection period is 60 days, compared with 30 days granted by creditors. The retention rate is 5,0%. Company overheads are 45 000,00 CHF per month, with a target reserve set at 8 weeks and an existing bank balance of 150 000,00 CHF.

The daily cost excluding VAT comes out to 2 000,00 CHF (240 000,00 ÷ 120). The payment gap is 30 days (60 − 30), generating a direct requirement of 60 000,00 CHF excluding VAT. Retention money represents 15 000,00 CHF excluding VAT (300 000,00 × 5%). Total site working capital reaches 75 000,00 CHF excluding VAT. Weekly fixed costs stand at 10 384,60 CHF (45 000,00 × 12 ÷ 52), giving an 8-week reserve of 83 076,80 CHF excluding VAT. The total cumulative requirement is 158 076,80 CHF excluding VAT.

The overall breakdown subject to 8,1% Swiss VAT is detailed as follows:

  • Total requirement net of tax: 158 076,80 CHF
  • Value-added tax (8,1%): 12 804,20 CHF
  • Total requirement including tax: 170 881,00 CHF
  • Available operating cash (incl. tax): 150 000,00 CHF
  • Required funding balance: −20 881,00 CHF

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures presented in the two scenarios below are illustrative examples to help guide your cash-flow choices.

Scenario 1: Major renovation in an urban area (Canton of Geneva)

A firm with 18 employees is carrying out the conversion of an office building. The job involves workshop costs on the order of 400 000 CHF to 500 000 CHF. The approval period for progress statements by the client's representative reaches 75 days, while profile merchants demand net settlement within 30 days. Contractual retention money is set at 10%.

The simulation shows a temporary requirement exceeding 165 000,00 CHF, creating critical pressure when social contributions fall due. The contractor chooses to replace the retention deduction with a joint and several guarantee issued by their bank, under the provisions of the Code of Obligations (CO). This measure releases 45 000,00 CHF in immediate cash and brings net exposure back below the warning threshold without hurting profitability.

Scenario 2: Multi-family housing construction (Canton of Fribourg)

A masonry contractor employing 12 workers carries out a structural work lot over 90 days. Payments from site management arrive at 45 days, and concrete suppliers are paid at 45 days. The payment gap is zero, limiting operating working capital solely to the 5% guarantee retained on advance payments.

With fixed costs of 32 000,00 CHF per month, management decides to maintain a strict 6-week reserve, or about 44 300,00 CHF. The tool confirms that available cash fully covers the total requirement. The company avoids drawing on a bank credit line, thus protecting its gross margin from debtor interest.

00:00 - 00:15 AI Avatar: A full order book can hide a cash-flow crunch. Master the gap between team payroll expenses and your advance payment receipts.

00:15 - 01:10 Screen and Diagrams: View the gap in days, the impact of a 5% retention under standard SIA 118, and the eight-week safety cushion on your firm's fixed overheads.

01:10 - 01:30 AI Avatar: Assess your available balance using our secure client tool and synchronise your operating financial management.

Frequently asked questions

How do you factor the client collection period into working capital?

Calculate the actual gap between client receipts and payments to subcontractors. Under the Code of Obligations (CO), unless agreed otherwise, due dates depend on contract terms; allow 60 days, for example, to anticipate potential delays.

How much should you allocate to the monthly security reserve?

Set aside eight weeks of fixed operating costs, roughly 90 000 CHF for a typical firm. This amount protects your cash position against billing surprises without unnecessarily locking up your funds.

How should client retention money be treated in cash planning?

Standard SIA 118 governs retention money. Deduct 5% of the total contract value up front, for instance 15 000 CHF on 300 000 CHF, until the funds are released.

Why neutralise a positive supplier payment gap?

As a matter of prudence under the BOSS method, paying suppliers after collecting from clients must not mask an underlying deficit. The gap is therefore set to zero in the working capital formula.

Where can a bank guarantee be used to replace retention money?

Under art. 492 CO, a guarantee secures the agreed obligation. This bank guarantee avoids the direct 5% deduction on progress billings and immediately releases operating cash in your current account.

How does this calculation link to the 13-week forecast?

The total identified requirement feeds weekly disbursements in your spreadsheet. You can then compare the theoretical balance with actual cash flows verified monthly with your fiduciary in French-speaking Switzerland.

To strengthen the financial structure of your Swiss construction SME and secure every operational phase, apply our practical methods and templates: