The 3 Major Site Risks
- Financial / Margin: Hidden drift in hours and budget overruns not arbitrated in time, causing an estimated ongoing margin loss of around 4% to 8% of annual turnover under the duty of care rules of art. 398 CO.
- Legal / Joint Body / SUVA: Failure to monitor safety alerts and prevention measures required by CFST directive 6508, exposing site management and the company to stop-work orders issued by the labour inspectorate.
- Administrative / Acceptance: Leaving interim claims unresolved during project execution, holding up monthly payment claims and delaying the joint inspection prescribed by standard SIA 118.
This operational PDF template structures the weekly management routine for heads of French-speaking Swiss construction SMEs employing 5 to 50 staff, their site managers, and their administrative executives. Used every Monday morning or Friday afternoon for precisely forty-five minutes, this tool prevents getting bogged down in execution details by focusing the session on the week's critical decisions. It eliminates scattered priorities thanks to a timed agenda, a review of key indicators, and a tamper-proof register of named commitments.
By recording governance decisions, this tool prevents the management paralysis that occurs when the business owner centralises every technical or administrative decision. The document formalises the immediate clearing of operational bottlenecks, 13-week cash flow monitoring, and safety coordination without encroaching on quantity surveying or preparing quotes, which belong to pricing. It establishes team discipline where each manager is accountable for deliverables with a firm deadline, securing the overall profitability of operations.
Downloadable document — PDF (9 ko)
45-minute management meeting — agenda and register
Receive this document by email
Enter your email address: the document will be sent to you immediately. Your data will not be shared with third parties.
Operational structure and instructions for the PDF template
The document comes as a two-page A4 dynamic PDF form, designed for handwritten input on a tablet or direct office software entry. Intended for the SME owner, assisted by site managers and the finance and administration manager, it takes place every week at a set time. Its structure enforces strict discipline divided into the four sections of the standard template.
1. Timed agenda (strictly 45 minutes)
This section sets the pace of the meeting with no overruns permitted: 5 minutes for check-in and review of prior commitments, 10 minutes for reviewing the week's indicators, 20 minutes for addressing critical bottlenecks, then 10 minutes for arbitration and closing the register of commitments. The facilitator records the start and end times. Any topic exceeding its allocated time is moved to an ad hoc technical meeting outside overall governance.
2. Indicators of the week
This section gathers the factual summary of operations without debating micro-details: recorded site production hours versus hours sold, interim invoicing issued, short-term available cash position, and tracking of safety-related incidents. In accordance with the general prevention requirements of art. 82 LAA, management checks here that appropriate protective measures have been implemented on current construction sites and that equipment alerts are addressed without delay.
3. Problems to solve (rank, then address the top 3)
The table records operational friction reported from the field. Participants rank issues by impact level (margin, safety, schedule) and select exclusively the three priority items for the session. Secondary matters remain on the waiting list for the following week. Each selected item is subject to root-cause analysis rather than simply observing symptoms.
4. Register of commitments
As a true record of decisions, this section formalises every resolution with a single action, a named owner (assigning a general team is prohibited), and a specific deadline down to the exact day. The previous week's register serves as the entry point for the current session, with each commitment validated as completed or deferred with a recorded reason.
Governance practices: comparison of wording
| Risky wording / frequent mistake | Compliant formulation or practice | Why |
|---|---|---|
| "Look into the supply issue on the Lausanne construction site." | "Marc finalises delivery of the precast units before Thursday 16:00." | Vague wording dilutes accountability. Naming an owner with a set deadline locks in responsibility. |
| "Analyse the hours overrun on the masonry work." | "David delivers the variance between budget hours and booked hours by Tuesday morning." | An analysis task without a specific deliverable never leads to an executive decision. |
| "The team must order the required safety protections." | "Jean inspects and orders the missing edge protections before Wednesday noon." | Collective responsibility leads to inertia. A single person must be accountable for the commitment. |
| Debating for twenty minutes over the brand of a workshop compressor. | Moving the tool selection to a bilateral site manager-storekeeper discussion outside the routine. | The management routine arbitrates financial and organisational flows, never workshop trivia. |
| Listing ten disputes simultaneously without formal prioritisation. | Rank the list and address exclusively the 3 major points of friction for the cycle. | Trying to resolve everything in forty-five minutes guarantees the failure of every action plan. |
| "Continue debt collection steps for overdue invoices." | "Sophie sends out formal notices of default by Friday 11:00." | Informal follow-up does not constitute an enforceable milestone for cash flow management. |
Fatal mistakes eliminated by the template
Omitting a weekly register leads to organisational amnesia. The build-up of unrecorded decisions leads to unbilled work representing 15 000,00 CHF to 45 000,00 CHF in margin erosion per year. Likewise, the lack of a formal review of safety alerts exposes the company to avoidable work stoppages with an average operational cost of around 4 500,00 CHF per day of construction site shutdown.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and situations described below are illustrative examples designed for managerial training. A finishing work general contractor in the canton of Vaud, employing twenty-eight staff on the major refurbishment of an office complex, observed recurring schedule slippage. During the weekly routine guided by the PDF template, the "Indicators of the week" section revealed sixty-eight unplanned hours spent on technical coordination. Under "Problems to solve", the site manager and technical director isolated the primary bottleneck: the lack of sign-off on plumbing and drainage penetrations by subcontractors. The resolution recorded in the "Register of commitments" set a coordinated formal notice within forty-eight hours managed by the lead site manager, heading off a potential delay estimated at over 25 000,00 CHF in contractual penalties.
Frequently asked questions
Who must attend this weekly meeting?
The meeting brings together the business owner, the technical manager, and the operations manager. A site manager attends only if a decision on a specific construction site exceeds an illustrative threshold of 5 000,00 CHF according to internal rules.
How should disagreements over safety instructions be handled?
The business owner decides pursuant to CFST directive 6508 and the accident prevention ordinance. The operational decision is logged in the register as a corrective action, with a single owner and a specific deadline within seventy-two hours.
What if reviewing the three problems takes longer than twenty minutes?
The facilitator suspends unresolved debates. The topic moves to a dedicated bilateral technical meeting. Exceeding forty-five minutes in total damages the autonomy of the structure and ties up managerial hourly wages estimated at over 120,00 CHF.
Can acceptance disputes be recorded in this register?
No. The management register arbitrates the internal organisation of the SME. Acceptance inspections and snagging items fall exclusively under the formalised tracking of site management according to standard SIA 118, accessible in our dedicated section.
How does this routine tie in with cash flow tracking at the fiduciary?
Management signs off on blocked invoices and expected cash collections over thirteen weeks. The fiduciary then applies the accounting entries under the Code of Obligations (CO), avoiding damaging payment delays with suppliers and cantonal social insurance funds.
This PDF template guarantees structured governance without overloading management's diary. To apply these routines, digitalise your agendas, or train your managers, consult the following resources: