The 3 Major Site Risks
- Financial / Margin: Disorganised safety roles lead to team shutdowns and operating cost overruns of around 15 000 to 45 000 CHF per construction site when a formal notice is issued by the site management, reducing gross margin under the Code of Obligations (CO).
- Legal / Joint / SUVA: Failure to take prevention measures exposes the employer to an activity shutdown ordered by labour inspectors or SUVA, incurring company liability under art. 82 LAA for breach of general prevention rules.
- Administrative / Acceptance: Lack of MSST evidence or traceability of instructions blocks the release of retainage and delays the joint inspection of the works under standard SIA 118.
CFST directive 6508 on calling in occupational physicians and other occupational safety specialists governs the methodical handling of occupational hazards in craft and building firms in Switzerland. For a French-speaking Swiss SME with between 5 and 50 employees, implementing a structured ten-point safety system is not merely an administrative formality, but an operational lever that ensures business continuity during inspections by SUVA and joint parity commissions. Applying the general prevention rules set out in the Federal Accident Insurance Act requires clearly assigning internal duties, rigorously identifying recurring hazards on site, and keeping verifiable records of the instructions given to site teams.
This self-assessment tool evaluates your organisation's progress against the ten criteria of CFST directive 6508, from the safety charter through to emergency management and employee participation. The calculation runs entirely in your browser without transmitting any data to an external server, preserving your firm's confidential data in accordance with Swiss standards. For questions regarding unit prices or tender bills of quantities, see our dedicated Soumissions module; for contractual disputes or acceptance minutes, refer to the execution portal.
Evaluation algorithm and safety system compliance formula
The checker applies an even linear weighting across the ten structural elements defined by CFST directive 6508 on calling in occupational safety specialists. Each operational section receives a closed whole-number rating: 2 points when the measure is in place and formally documented, 1 point when it is partially applied or not formalised, and 0 points if it is not applied on the ground at all.
The overall score is calculated using the following mathematical formula:
Compliance rate (%) = 100 × (Total points scored) ÷ 20
A firm's level of integration falls into three tiers of organisational maturity:
- Score of 80% or higher (16 to 20 points): robust safety system, established procedures, and clearly allocated responsibilities.
- Score between 50% and 79% (10 to 15 points): partial compliance, risks of disruption during site inspections, and documentation gaps.
- Score below 50% (fewer than 10 points): inadequate system, lack of coordination exposing the firm to operating shutdowns.
The assessment relies on tangible evidence such as workstation instruction sheets, equipment maintenance logs, and training certificates, rather than purely theoretical adherence.
Scoring grid for the 10 criteria of CFST directive 6508
| Audited criterion | Documentary evidence required | Max points | Average SME score (observed) | Observed standard deviation |
|---|---|---|---|---|
| 1. Safety policy | Charter signed by management and annual objectives | 2 | 1 | Not distributed to teams |
| 2. Safety organisation | Formal appointment of a safety officer (art. 5 OTConst) | 2 | 1 | Incomplete specifications |
| 3. Training and instruction | Records of continuing training and safety passports | 2 | 1 | No tracking for new hires |
| 4. Safety rules | Working rules displayed and handed out at workstations | 2 | 1 | Verbal rules not tracked |
| 5. Hazard identification | List of trade-specific hazards and associated measures | 2 | 0 | Inventory missing or outdated |
| 6. Action planning | Costed annual action plan with tracking schedule | 2 | 0 | Measures taken after incidents |
| 7. Emergency measures | First aid organisation and evacuation plans | 2 | 1 | Rescuers without refresher training |
| 8. Staff participation | Minutes of safety meetings and field feedback | 2 | 0 | Informal consultation |
| 9. Health protection | Ergonomics, pace management, and site hygiene | 2 | 1 | Piecemeal measures |
| 10. Monitoring and audit | Periodic inspection reports and annual reviews | 2 | 0 | No internal audit conducted |
Sample calculation of organisational upgrading costs
A French-speaking Swiss SME with 18 employees wishes to resolve its methodological gaps to raise its score from 6 out of 20 (30%) to 17 out of 20 (85%). The three-month catch-up plan draws on internal managerial resources and external documentation support. The amounts listed below are representative orders of magnitude:
- Internal safety officer training (certified course and allocated time): 3 200,00 CHF excl. VAT
- Compiling the company manual and workstation sheets (40 site manager hours): 4 600,00 CHF excl. VAT
- Internal signage equipment and standardised first aid kits: 1 450,00 CHF excl. VAT
- Subtotal of services and supplies excluding tax: 9 250,00 CHF excl. VAT
- Value-added tax (Swiss VAT at the rate of 8,1%): 749,25 CHF
- Grand total to bring the company into compliance: 9 999,25 CHF incl. VAT
This structural investment pays for itself through standardised internal workflows and eliminating wasted time during site installation.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios described below are illustrative examples designed for methodological learning by a French-speaking Swiss construction SME.
Scenario 1: General masonry contractor in the canton of Vaud
A Vaud firm with 24 workers carries out the structural work for a residential building in Morges. During the initial self-assessment, the SME scores a total of 9 out of 20 points (45%, insufficient level). The main shortcomings involve the lack of written hazard assessments and missing formal induction when temporary staff arrive. Alerted by this result, management appoints a site manager as the safety lead and standardises the ten required points. Introducing translated onboarding sheets and weekly equipment checks enables the firm to reach a score of 16 out of 20 (80%) within six weeks. During an unannounced site visit by SUVA inspectors, the company promptly presents up-to-date logs, preventing any shutdown and keeping work on schedule without delay penalties.
Scenario 2: Steel Construction SME in the canton of Fribourg
A Fribourg firm with 12 employees is erecting an industrial frame in Bulle. The initial assessment using the grid produces 12 out of 20 points (60%, partial level). The missing points stem from the absence of an emergency response plan for work at height and the lack of a periodic inspection log for harnesses and ropes. Management decides to structure its safety system: it drafts an evacuation protocol for injured workers, inspects all personal protective equipment, and institutes a monthly consultation meeting with erectors. Once these measures are implemented, the second score reaches 18 out of 20 points (90%, robust system). This administrative and operational rigour protects the firm against claims from site management and stabilises its crews on complex jobs.
Frequently asked questions
What budget should be allocated to structure the 10 MSST points?
For an artisanal SME, plan for an internal investment estimated at around 4 800,00 CHF in coordination hours, supplemented by acquiring safety binders in line with CFST directive 6508.
Who checks the implementation of our MSST system?
SUVA inspectors and cantonal authorities check the practical application of measures required by the Federal Accident Insurance Act and the construction work ordinance.
Does an industry solution eliminate the need for internal documents?
No. Affiliation provides standard manuals, but your company must prove the practical fit of the setup with tailored workstation sheets under CFST directive 6508.
How can safety instructions be logged without overburdening the field?
Use laminated onboarding sheets and pocket-sized team protocols. CFST directive 6508 requires verifiable proof of communication, without imposing unnecessary red tape.
What risks does an employer face during an inspection without an MSST manual?
The authority issues a formal warning setting a deadline for technical compliance. In serious cases, the enforcing body may order a partial shutdown of unaddressed workstations.
Where can pricing references for protective equipment be found?
Unit prices for supplying and installing safety equipment come from descriptive quotes: visit our dedicated module at /soumissions/ for detailed pricing.
Continue bringing your business into compliance
The ten-point diagnosis establishes the baseline for your preventive setup. To take your operational structure further, explore our complementary resources: