Table of contents
The 3 Major Site Risks
- Financial / Margin: A gross margin drift of around 8 % to 15 % of the awarded contract sum due to quantity takeoff omissions or supplies not ordered in time, jeopardising operating results under the Code of Obligations (CO).
- Legal / Joint / SUVA: Work stopped by the labour inspectorate or SUVA if the measures specified in art. 3 OTConst and the written plan required by art. 4 OTConst are missing when opening the site.
- Administrative / Acceptance: Advance payments rejected by site management and the future acceptance of the work blocked under SIA 118 standard due to discrepancies between the technical tender and execution.
In running a French-Swiss building SME, the operational handover between cost estimating and field deployment is the most critical financial vulnerability zone. Once the contract is awarded, sloppy handover between the sales team and the site manager triggers execution misunderstandings, erroneous material orders, and logistical improvisations that destroy planned profitability. For projects requiring a complete quantity takeoff, our dedicated tenders platform details price series without interfering with this internal organisational protocol. Implementing this formalised check ensures that every assumption made in the quote is rigorously vetted against actual site constraints before committing the firm's manpower and plant.
This systematic check-up structures twelve essential technical milestones to authorise the actual start of production. The review covers municipal administrative approvals, formal approval of drawings by site management, and safety measures required by the CFST 6508 directive and the construction work ordinance. Contractual issues concerning condition reports or final handover minutes under SIA 118 standard are handled via our site portal. By establishing a minimum evaluation threshold and locking down blocking criteria, company management protects operating cash flow, safeguards fitters, and ensures seamless execution on site.
Decision algorithm and operational weighting model
The evaluation engine relies on a matrix of twelve checkpoints built around the CFST 6508 directive and the principles of the construction work ordinance. Each criterion receives a discrete score: two points for validated compliance, one point for partial status, and zero points for untreated items. A specific weighting from one to three is assigned based on direct impact on staff safety and company cash flow.
The overall score is calculated using the following mathematical formula:
Score = 100 × Σ (criterion weight × response value) ÷ Σ (criterion weight × 2)
A strict disjunction rule governs the result: four critical criteria are defined as blocking. If any of these items receives a zero, site opening authorisation is rejected ("No-Go"), regardless of the overall arithmetic score. For files with no failing blocking points, the threshold for immediate go-ahead is set at 80 out of 100 points. Below 80 points, corrective actions must be completed before deploying crews to the field.
Weighting grid and decision criteria
| Internal review criterion | Weight | Blocking status | Organisational impact | Expected deliverable |
|---|---|---|---|---|
| Approval of works contract and addenda | 3 | Yes | Legal and billing | Initialled and signed contract |
| Safety measures under CFST 6508 directive | 3 | Yes | Occupational health and SUVA | Written safety concept |
| Execution drawings stamped "Approved for construction" | 3 | Yes | Technical compliance of the works | Drawings certified by site management |
| Municipal permits and public land occupancy | 2 | Yes | Building control authority | Road occupancy or site installation permit |
| Validated material data sheets | 2 | No | Procurement and logistics | Supplier purchase orders |
| Master schedule aligned with site management | 2 | No | Inter-trade coordination | Validated critical path |
| Target labour hours communicated to team leader | 2 | No | Labour profitability | Production target sheet |
| Underground utilities and service locator check | 1 | No | Damage prevention | Utility maps and site markings |
Applying this scale eliminates interpretation uncertainties between the project estimator and site management.
Financial simulation of avoided failure costs
Lacking a structured handover leads to unproductive downtime on site arrival. The following example illustrates the average economic impact observed on a ten-day finishing work job involving four workers:
Downtime on site waiting for approved execution drawings: 16 hours at 95,00 CHF per hour, i.e. 1 520,00 CHF excl. VAT.
Non-compliant material returned to supplier with unplanned handling: flat logistics fee of 850,00 CHF excl. VAT.
Reworking wall openings not indicated on the initial quote: 12 hours at 95,00 CHF per hour, i.e. 1 140,00 CHF excl. VAT.
Subtotal of operational losses: 3 510,00 CHF excl. VAT.
Value-added tax (VAT 8,1 %): 284,30 CHF.
Total margin losses: 3 794,30 CHF incl. VAT.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The following two cases are illustrative examples developed to demonstrate the practical application of this decision tool in French-speaking Switzerland.
Scenario 1: Major urban renovation (Canton of Geneva)
A general contractor with eighteen employees is awarded the refurbishment of an office building. The crew on the construction site consists of six workers and a site foreman. During internal handover, the project scores a raw 84 out of 100 thanks to a precise quote and locked supplier material orders. However, the public land occupancy permit for placing a skip has not been formally issued by the municipal administration of Geneva, scoring zero on a blocking point.
Tool decision: Start suspended ("No-Go"). Work was postponed by forty-eight hours until the official permit was secured. This preventive delay avoided an administrative fine for unlawful road occupancy and the immediate turnback of transport vehicles.
Scenario 2: Construction of three terraced villas (Canton of Vaud)
A masonry SME with twenty-four employees is preparing to start earthworks for a residential development on the Vaud Riviera. The scheduled crew comprises four structural work operatives. The check-up analysis shows a calculated score of 71 out of 100. No blocking item is at zero, but special reinforcement data sheets are missing, the schedule lacks approval from site management, and the target labour hours have not been shared with the team leader.
Tool decision: Start suspended until complete ("Complete first"). Management mandated a two-hour coordination meeting at the office between the estimator and the site manager to finalise bending schedules and distribute working hours. The construction site started with an updated score of 88 out of 100, preventing any delivery halts during concrete pouring.
Frequently asked questions
Who signs off on the handover checklist before work begins?
The site manager and team leader countersign the evaluation. If access is blocked, the business owner arbitrates to protect an illustrative operating margin of around 4 500,00 CHF.
How do you handle an unresolved blocking point during the check-up?
The start is postponed until written clearance is obtained. Under the construction work ordinance, preventive measures must be anticipated to avoid work shutdowns or illustrative extra costs of 1 800,00 CHF.
Does a score of 85 out of 100 authorise opening the construction site?
Yes, unless a blocking criterion scores zero. The MSST system under CFST 6508 directive requires eliminating any critical organisational risk before dispatching fitters to the site.
Where should detailed quantity takeoffs from the initial tender be recorded?
Full takeoffs and unit prices are managed on the dedicated tenders platform. The handover tool extracts only the total labour hours to plan crew resources.
Is the form data stored on external servers?
No. The calculation runs entirely inside your browser in accordance with the Federal Act on Data Protection. No financial details or personal data ever leave your office desktop.
What impact does the handover protocol have on cash flow?
A structured handover prevents unbudgeted rush orders. For an illustrative 50 000,00 CHF project, this discipline secures net cash collection without disputes with site management.
This structured protocol secures the transition from cost estimating to field operations. Continue streamlining your projects using our additional resources for Swiss contractors:
