The 3 Major Site Risks
- Financial / Margin: gross margin erosion of around 8% to 15% of the awarded contract sum due to missing supplies and unbudgeted daywork, caused by failing to transfer the full quote details to the installation crew under Code of Obligations (CO) rules.
- Legal / Joint body / SUVA: work stoppage ordered by the labour inspectorate or SUVA for failure to plan preventive measures and lack of formal risk identification before starting work under the Construction Works Ordinance (OTConst).
- Administrative / Handover: advance payment applications blocked by site management and disputes during inspection of the work under standard SIA 118, caused by missing written signed commitments and unapproved technical submittals.
This internal handover file structures the operational transition between commercial award and the opening of the construction site for French-speaking Swiss construction SMEs. Designed for company directors, site managers, and crew leaders, this free PDF document formalises sold quantities, critical procurements, and logistical constraints. Its rigorous application prevents disorganized starts, eliminates early productivity losses, and cuts out recurrent friction with site management from the very first week on site.
The checklist is structured around four operational sections: an exact inventory of sold works, the material prerequisites to get started, safety coordination according to directive CFST 6508, and the formal clearance of blockers. Filled out during a thirty-minute joint review between the estimator and the site manager, this tool ensures every stakeholder understands the boundaries of their scope, avoiding execution cost overruns and securing the firm's margin.
Downloadable document — PDF (9 ko)
Handover from quote to execution — launch checklist
Receive this document by email
Enter your email address: the document will be sent to you immediately. Your data will not be shared with third parties.
Operational layout of the PDF handover file
The internal handover file comes as a standardized four-page PDF document. It is completed jointly by the project manager and the site manager during the handover meeting, specifically between signing the work contract and dispatching crews into the field. The crew leader receives the approved document during the initial technical briefing. This form prevents loss of critical information and aligns commercial expectations with actual site conditions.
How to use the four execution sections
The document is structured around four mandatory sections designed to secure the site launch:
- 1. What was sold: This section records the total contract value awarded in CHF, the detailed scope included, and the explicit list of exclusions from the accepted offer. The execution assumptions made at tender stage are transferred here. Detailed quantities and unit prices analysis belong in the Soumissions section; this document covers only the approved budget envelopes.
- 2. What is needed to start: This part covers municipal access permits, the status of temporary site water and electricity supplies, and order confirmations for long-lead materials. Here, the site manager checks that storage areas are genuinely clear and that the execution drawings issued by site management are compliant.
- 3. Construction site safety: The project manager and site manager lay out preventive measures compliant with the Construction Works Ordinance (OTConst) and directive CFST 6508. The section records the formal appointment of the safety officer, the identification of fall hazards, prior testing for potential pollutants, and the collective protective equipment required before any work begins.
- 4. Blockers and commitments: This section inventories critical interfaces with other trades, contractual milestone dates, and technical reservations made upon award. Each item is tied to a dated commitment with one single person designated to resolve it.
Comparison table of handover practices
| Risky wording / frequent mistake | Compliant formulation or practice | Why |
|---|---|---|
| "See signed quote for details of work" | "Scope as per approved description of 14.10, excluding waterproofing repairs" | Prevents disputes over works not priced during execution. |
| "Start as soon as possible, weather permitting" | "Start scheduled for 12 May, subject to municipal road access" | Sets a legally defensible baseline date for contractual time limits. |
| "Standard site safety provided by structural work contractor" | "Façade scaffolding formally inspected by us prior to installation" | Complies with the Construction Works Ordinance (OTConst) without relying on assumptions about third parties. |
| "Material orders handled by crew leader" | "Supplier purchase order no. 4812 confirmed for delivery on 15 May" | Eliminates stock shortages and urgent procurement surcharges. |
| "Coordination on site with other trades" | "Screed-plumbing interface recorded in site meeting of 3 May" | Prevents trade clashes that generate non-productive downtime. |
| "Drawing available on site notice board" | "Execution drawing Rev. C signed for approval on 28 April" | Prevents building from obsolete revisions. |
Critical errors locked down by the document
Lacking a structured handover leads to recurrent cost and schedule overruns on Swiss construction sites. Sending a crew to an unprepared site causes unplanned downtime. For a team of three installers stuck for half a day due to missing municipal access or an unavailable crane, the direct loss runs around 1 200,00 CHF to 1 800,00 CHF in unproductive labour. Likewise, ordering a bespoke component late results in express freight costs or work stoppages, with total damages typically between 3 500,00 CHF and 7 000,00 CHF. Finally, poor tracking of scope boundaries leaves the contractor carrying unbillable preparatory works, cutting into the job's net margin. For collective agreement wage scales or hiring issues, refer to the Jobs section.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios below are illustrative examples designed for operational learning.
Typical scenario: Commercial building renovation (Canton of Vaud)
A plastering and painting SME of 18 employees works on an administrative building in Lausanne. Crew assigned: 1 crew leader and 3 skilled workers.
While completing the handover PDF, the site manager and project manager discover that site management requires a start on Monday morning, but the public highway permit for the skip has not yet been issued by the local building authority. Thanks to section "4. Blockers and commitments", the actual start is formally placed on hold until the official document arrives. This step prevents idle staff time representing roughly 2 450,00 CHF in non-productive wages. Meanwhile, the safety section confirms that floor openings have been covered and secured in line with occupational safety rules before painters access the area.
Frequently asked questions
Who must sign the checklist during the internal handover meeting?
The project manager and site manager sign the document to formalise the handover. Under the Construction Works Ordinance (OTConst), this step validates the allocated resources and prevents operating losses of around 4 500.00 CHF.
How should work excluded from the firm's initial quote be recorded?
The opening section lists all excluded works to prevent unbilled scope creep. Strict application of the Code of Obligations (CO) protects operating margins against unpriced site requests, avoiding an illustrative shortfall of 3 200.00 CHF.
Which safety document must be formally approved before work begins?
The employer must check the health and safety plan required under the Construction Works Ordinance (OTConst). Operating without adequate preventive measures exposes the firm to work stoppages ordered by SUVA.
What happens if an administrative blocker remains on the handover date?
A No-Go status applies as long as the municipal building permit or truck access is missing. This operational discipline avoids wasting unproductive payroll estimated at 1 850.00 CHF per day for an idle crew.
Where are detailed quantities and unit prices handled during the handover?
Detailed take-offs and tender pricing are managed directly in the Soumissions platform. The operational handover focuses strictly on technical feasibility, safety under directive CFST 6508, and the works schedule.
An internal handover structures the transition from commercial bidding to field execution, ensuring compliance with safety directives and the profitability of every project. To refine your management procedures and coordinate operations, explore our dedicated resources: