Table of contents
The 3 Major Site Risks
- Financial / Margin: A final non-payment often represents around 15 to 30 % of the contract amount, absorbing the SME's net profit and causing severe liquidity strains under Code of Obligations (CO) rules on due dates.
- Legal / Joint Body / SUVA: The legal obligation to continue paying minimum wages and social security contributions to the compensation funds, even when progress billings remain unpaid by the project client.
- Administrative / Acceptance: Contractual advance payments blocked during work inspection under SIA 118 norms due to one-sided financial clauses or insufficient payment guarantees agreed when setting up the contract.
In the French-speaking Swiss building sector, rigorous claims management starts well before teams step onto the jobsite. Assessing a client's financial stability in advance is the key commercial step to safeguard company cash flow. By routinely cross-checking commercial register data via Zefix against an extract from the debt enforcement office, site management and business owners identify clear warning signs of default, such as recent payment orders, pending debt enforcement proceedings, or frequent changes of company name.
This decision-support calculator turns your factual checks into a weighted risk score to set an appropriate advance payments schedule—specifying, for example, an initial payment of 10 % to 50 % of the contract value depending on verified reliability. Calculations run locally in your browser, ensuring compliance with the Federal Act on Data Protection with no sensitive data sent to external servers. For detailed project estimates or tender bill of quantities, visit our dedicated section; this tool focuses exclusively on securing your firm's incoming payments under contract.
How the scoring algorithm and calculation logic work
The tool applies strict weighting to the legal and financial indicators spotted by business owners during their preliminary checks. In line with essential precautionary principles in both finishing work and structural work, the model leaves no room for commercial complacency. The analysis centres on checking the debt enforcement office extract, company history on Zefix, and the client's legal form.
Each factual finding is assigned a specific number of risk points. The standardised assessment formula runs as follows:
Overall score = 100 × (Total points recorded ÷ Total possible maximum points)
The result places the client into one of three risk tiers:
- Low risk (score below 30): Long-standing client or established company with no recent debt enforcement, standard 10 % advance payment on signing.
- Medium risk (score 30 to 59): Recently formed entity, isolated or disputed debt enforcement, safety advance payment set at 30 % before any procurement.
- High risk (score 60 or above): Multiple payment orders, certificates of loss, frequent management changes on Zefix, mandatory 50 % advance payment or a bank guarantee required.
The financial amount required on signing is calculated directly by applying the selected percentage to the contract amount before tax:
Protective advance payment (CHF excl. VAT) = Contract amount excl. VAT × Risk tier percentage
Weighting matrix for administrative findings
The table below sets out the points scale based on findings gathered from official Swiss registers:
| Source checked | Finding regarding the client | Points assigned | Alert level | Contractual impact |
|---|---|---|---|---|
| Debt enforcement office | Clean extract over the last three full calendar years | 0 | None | Standard terms apply |
| Debt enforcement office | Single debt enforcement under 3 000,00 CHF currently under objection | 10 | Moderate | Review the grounds of the dispute |
| Debt enforcement office | Multiple uncancelled debt enforcement claims totalling over 10 000,00 CHF | 35 | Critical | Refusal to advance materials |
| Zefix register | Company active for over 10 years without corporate changes | 0 | None | Recognised stable structure |
| Zefix register | Formed within the last 12 months or minimum paid-up capital | 15 | Caution | Tighter billing schedule required |
| Zefix register | Registered office or director changes within the last 6 months | 25 | High | Suspected opaque restructuring |
| Law of obligations | Formal refusal to issue a guarantee under the Code of Obligations (CO) | 40 | Deal-breaker | Halt commercial negotiations |
Complete worked example with Swiss VAT
Assume a tender for a building envelope renovation valued at 120 000,00 CHF excluding tax. The credit check shows a company recently entered in the commercial register (15 points) that had a payment order of 4 500,00 CHF settled late (10 points), giving a total of 25 points out of a theoretical maximum of 70 points for this profile.
The score is calculated as follows: 100 × (25 ÷ 70) = 35,71. The file falls into the medium-risk tier. The recommended advance payment rate is set at 30 % of the order.
- Total contract amount: 120 000,00 CHF excl. VAT
- Calculated 30 % advance payment: 36 000,00 CHF excl. VAT
- Value-added tax (8,1 % VAT): 2 916,00 CHF
- Total amount due before work begins: 38 916,00 CHF incl. VAT
- Remaining balance subject to monthly progress billings: 84 000,00 CHF excl. VAT (90 804,00 CHF incl. VAT)
Illustrative practical cases (typical scenarios on Swiss construction sites)
The following cases are illustrative examples developed to show how this method works in daily trade business operations.
Scenario 1: Roof renovation in the Canton of Vaud
A Vaud Sheet-metal Work firm with 8 workers is asked by a limited liability company to convert a farmhouse into rental flats. The quote comes to 85 000,00 CHF excl. VAT. A Zefix search reveals a registered office relocation from the canton of Geneva three months earlier, alongside a complete change of managing directors. The debt enforcement register extract shows two pending, unlifted proceedings totalling 7 200,00 CHF.
The checker calculates a risk score of 64, placing it in the high-risk band. The business owner contractually insists on a 50 % advance payment, or 42 500,00 CHF excl. VAT (45 942,50 CHF incl. VAT at 8,1 % VAT), payable before ordering copper coils and profiled metal sheeting, combined with strict bi-monthly progress billings. When the client refuses, the contractor applies the no-go protocol, avoiding a direct out-of-pocket loss on materials.
Scenario 2: Liquid screed installation in Valais
A Valais plastering company with 14 employees acts as a subcontractor for a local property developer on a small multi-unit chalet project. The contract is worth 48 000,00 CHF excl. VAT. The commercial register confirms the firm has been trading for 12 years with fully paid-up share capital. The debt enforcement extract shows no asset seizures or payment orders.
The calculated score is 0, placing the job in the low-risk tier. The business owner applies the standard 10 % advance payment, or 4 800,00 CHF excl. VAT (5 188,80 CHF incl. VAT), covering batching plant setup and raw material booking, before committing labour under a protected cash-flow schedule.
Frequently asked questions
How do you obtain a client's debt enforcement register extract?
Request the extract from the debt enforcement office where the client is domiciled, enclosing your signed quote to prove your legitimate interest under the Federal Act on Debt Enforcement and Bankruptcy.
What advance payment should you require for a 120 000 CHF excl. VAT job at medium risk?
Specify a 30 % advance payment in the contract, around 36 000,00 CHF excl. VAT, payable before any site work begins under standard Code of Obligations (CO) provisions governing mutual agreements.
What should you check first on a prospective corporate client's Zefix extract?
Check the registration date, paid-up capital, statutory registered office, recent director changes, and whether contract signatories hold individual or joint signing authority according to the commercial register.
When should you ask for a bank guarantee or a joint and several guarantee?
Demand a guarantee under art. 492 CO as soon as the risk score enters the high tier, or whenever a contract exceeds 100 000,00 CHF excl. VAT with an unfamiliar client.
How should prospect financial data be handled under Swiss law?
In accordance with the lawfulness and proportionality principles of the Federal Act on Data Protection, process these records solely for credit-checking purposes, with no third-party disclosure and no retention beyond what is needed.
Can you stop work if the initial advance payment is not received?
Yes, provided your works contract explicitly makes site start conditional on receipt of the initial advance payment. Without verified payment, your site management should not sign off on the site opening order.
To structure your site openings, apply client qualification criteria, and download our contract templates, explore our dedicated resources: