Practical guide

Eliminating Unbilled Supplier Runs

Stop unbilled supplier runs in Swiss construction SMEs: supply-chain methods, CHF cost control, and CFST 6508 occupational health and safety compliance.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Recurring deadweight loss of around 120,00 CHF to 280,00 CHF per unscheduled trip in a commercial vehicle (unproductive hourly wage under art. 319 CO, fuel, and vehicle wear), eroding the job's net profit margin with no possibility of recharging as daywork to the client under standard SIA 118 without prior approval.
  2. Legal / Joint Body / SUVA: Increased driver fatigue during rushed, improvised errands under time pressure; disrupted work stations that expose crews to breaches of occupational safety guidelines defined by the MSST system under directive CFST 6508.
  3. Administrative / Acceptance: Lack of coordination between trades caused by the team leader's temporary absence on supply runs, delaying interim milestones and complicating joint inspection procedures during the acceptance of the work under standard SIA 118.

In French-speaking Swiss construction SMEs, unplanned trips to building materials trade counters represent an invisible yet continuous drain on profitability. When an installer or a bricklayer leaves their workstation at 10 h to pick up fittings, sealant cartridges or missing fasteners, the business absorbs the entire labour cost with no billable counterpart in the final account. These hours spent on the road form part of the agreed wage owed by the employer under the individual employment contract pursuant to the Code of Obligations (CO), but generate no physical progress on the executed work.

This logistical breakdown stems from a lack of upfront standardisation, often aggravated by superficial job preparation during internal handover. For company owners, site managers, and team leaders, the challenge is to replace panic reactions with a rigorous workflow built around predefined mobile inventory kits and scheduled site deliveries. This approach restores operational cash flow, protects site productivity, and ensures compliance with the organisational rules prescribed by directive CFST 6508 on every work location.

Anatomy of a logistical breakdown: why the job site stops at the trade counter

A crew member's impromptu departure to a builder's merchant is never an isolated event. It points to a breakdown in the internal planning of construction sites. In the day-to-day management of a trade firm with 10 to 30 workers, these errands are often seen as normal adjustments to job-site contingencies. Yet every van run incurs a three-fold penalty: tying up a service vehicle, halting work on the construction site, and buying supplies at retail counter prices with no pre-negotiated discount.

Under Swiss contract law, the hours spent on these trips cannot be included on daywork sheets submitted to the site management under standard SIA 118, because procuring everyday tools and consumables forms part of the contractor's overheads. For detailed pricing of bill items or the analysis of unit times by CFC, firms should consult dedicated tender estimation tools rather than adding gross price sheets to workshop protocols.

The distinction between technical contingencies and poor layout planning

There is frequent confusion between a change order requested by the client and a shortage of supplies arising during a task. When the site management requests a rerouting or a different material, the addendum procedure applies. Conversely, running out of wall plugs suited to the substrate, lacking specific adhesive, or forgetting a connector sleeve is entirely the organisational responsibility of the executing contractor. This downtime harms overall output and disrupts the schedule of finishing work trades.

A 4-step operational protocol to lock down supply chains

To eliminate these unproductive round trips once and for all, the BOSS method structures field operations around four standardised milestones, applied from the yard right up to the installation face.

1. The staging area at D-2 in the yard

Forty-eight hours before working on site, the team leader gathers all the materials specified in the execution drawings into bins labelled by work zone. Routine consumables (fasteners, sealing tapes, cartridges, abrasives) are packed according to a verified packing list. No morning departure takes place without a physical check of this kit by the yard manager.

2. Van buffer stock and visual replenishment systems

Every commercial vehicle carries a standardised minimum inventory of everyday small parts and fasteners. Access to these storage bins follows the two-bin Kanban principle: each box contains a reorder level tag. As soon as the critical threshold is reached, the tag is dropped at the logistics office that evening for restocking overnight, preventing work stoppages the next morning.

3. Exclusive reliance on scheduled on-site deliveries

Partnerships with Swiss material suppliers must include direct early-morning site deliveries, dropped off before 07:30. The negotiated cost of a distributor delivery is consistently lower than the cost of taking a skilled tradesperson and their van off the job and into city traffic. Urgent top-up orders are centralised by the site manager and delivered by the supplier at a set time.

4. Collaborative weekly scheduling

Anticipating requirements relies on close, short-term task coordination. By identifying space constraints and trade interfaces several days ahead of time, the technical team can order bespoke items with sufficient lead time, removing the emergency that usually drives an installer to the nearest trade counter.

Comparison table of logistics management methods

The table below compares common rule-of-thumb practices with standardised logistics workflows aligned with industry standards.

Operational parameterUncontrolled rule-of-thumb practiceStandardised, secured workflowDirect impact on the business
Material preparationSame-morning counter purchases based on immediate requests from workers.Complete staging in the workshop at D-2 with verification against a standardised checklist.Elimination of morning job-site startup delays.
Consumables managementAd-hoc emergency purchases in small quantities at full price with no volume control.Standardised van inventory with reorder tags and scheduled restocking at the yard.Lower procurement costs and an end to stockouts.
Handling missing parts on siteAn installer immediately heads to the nearest distributor as soon as an item is missing.Requests centralised at midday; bundled site delivery by the supplier the next day.Teams remain productive on their installation work.
Purchasing authorityLeft to individual installers holding open trade accounts with several merchants.Orders strictly approved by the site manager or the dedicated logistics manager.Strict expense control and an end to duplicate purchases.
Labour time billingAttempted daywork billing disputed by the site management at final account.Hours included in workshop preparation according to accepted trade practice under the contract.Zero disputes when verifying quantities and daily reports.

Common organisational mistakes and recurring financial impacts

Analyzing breakdowns on trade construction sites highlights four recurring mistakes that generate direct profit margin losses.

Open trade accounts without spending limits or oversight

Leaving open collection accounts with multiple trade counters without prior sign-off lets every team leader pick up convenience items or quick workarounds. Beyond missing out on volume discounts, this practice prevents cost accounting from allocating supplies accurately to the correct job account. In uncontrolled businesses, this average financial leakage represents an illustrative waste of roughly 15 000,00 CHF to 35 000,00 CHF per year in scattered purchases.

Downgrading productive labour

Sending a qualified installer holding a Federal VET Diploma (CFC) to drive a van just to pick up three fittings is a misuse of skills. During that drive, their technical expertise produces zero added value on the project. Furthermore, workforce management, collective labour agreement scales, and employment contracts belong on dedicated recruitment platforms and must not interfere with daily task scheduling.

Overlooking road safety under time pressure

Rushing out to pick up a missing part causes stress and increases the risk of road accidents during intermediate journeys. In accordance with directive CFST 6508 and occupational accident prevention rules under the accident insurance law, employers are required to organise work rationally to safeguard employee physical health by eliminating unplanned emergency trips.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following scenarios are illustrative case studies designed to quantify the impact of logistics protocols, and do not depict any specific job site.

Scenario A: Office building renovation in the Canton of Vaud

On a commercial MEP renovation project involving a crew of six electricians, the initial setup averaged seven trips per week to the local wholesaler to pick up basic installation supplies (conduits, flush-mounting boxes, and cable clips). Each round trip meant an average absence of 90 minutes for one installer and a van.

Setting up a secure on-site storage container, restocked every Monday morning via a consolidated order approved the previous Thursday, eliminated these unscheduled runs. The direct gain in productive labour was roughly 10,5 hours per week reallocated to actual installation, enabling the contractor to meet the project milestone set in the master schedule without requesting contractual extensions of time.

Scenario B: Multi-family housing construction in the Canton of Fribourg

A Plumbing & Sanitary Installations contractor working on 16 residential units faced recurring downtime at the installation face due to stockouts of specific drainage fittings. Two workers regularly left the construction site in the middle of the day to collect parts from a warehouse 25 kilometres away.

Management introduced a strict preparation protocol on an apartment-by-apartment basis: all stack pipes, brackets, and sleeves required for a vertical service duct are now packed in sealed crates at the central yard before dispatch. If a snag or a defective part occurs, the team leader immediately switches the crew to the duct on the floor above, which is already kitted out, while the missing piece is ordered for the supplier's next morning delivery run. This discipline brought the logistical downtime rate to zero across the entire execution phase of the finishing work.

Frequently asked questions

How should unplanned trips to suppliers be recorded?

The time spent represents an internal operating loss that cannot be billed to the client. These hours are charged to an overheads account to track the financial cost, estimated as an example at 145,00 CHF per round trip.

Can the client refuse to pay for these travel hours?

Yes. Under standard SIA 118, ordinary supplies and small accessories needed for installation are deemed included in the agreed contract prices. No extra charge is admissible without a daywork sheet approved in advance by the site management.

What is the travel-time status under the LTr?

Under the labour law, travel between the construction site and the yard or supplier during the working day counts as actual working time. Employers must therefore pay for it in accordance with the relevant collective labour agreements.

What is the optimal buffer stock for a light utility vehicle?

A standardised stock of small ironmongery, fixings, and consumables represents an indicative value of around 1 200,00 CHF. This mobile buffer avoids daily runs whose logistics costs quickly exceed the value of the items retrieved.

How can site supervisors be held accountable for top-up orders?

Establishing a daily logistics routine helps anticipate material requirements 48 hours ahead. Any unscheduled trip to the wholesaler is reviewed at a weekly debriefing to adjust standard picking lists without disrupting site execution.

What safety obligations apply to shuttling materials?

Employers must apply art. 82 LAA to prevent accidents during repeated handling operations and transport. Loads in commercial vehicles must be securely fastened to protect workers' physical safety on the road.

Eliminating unscheduled trips to wholesalers hinges on meticulous scheduling before ground is even broken. By stabilising supplies and tool allocations, companies safeguard their profit margins and streamline daily site coordination for installation teams.