🧱 CFC 238Structured copper cabling: classes, installation and linksChapter 9 of 10 in the section

Keeping space: spare conduits, ports and rack height capacity

At the end of this chapter, the telematics technician will know how to size and obtain contractual sign-off for the three critical spare capacities of a structured cabling infrastructure: empty conduits, patch panels and vertical space in the server rack. You will possess the technical arguments and engineering ratios essential for integrating future expansion without heavy masonry remedial work or service outages.

Key takeaways

  • Systematic empty conduit provision guarantees subsequent pulling without diamond drilling or destructive chasing into the structural work.
  • Retaining twenty to thirty per cent available ports on patch panels ensures the long-term viability of horizontal distribution.
  • Providing one third free rack units in the cabinet avoids the costly addition of secondary cabinets.
  • Costing the extension right from the project phase prevents disputed addenda as the building evolves.

Empty conduits and containment runs: ensuring the route before concrete pouring

On Swiss construction sites, the durability of a multimedia network depends on anticipating volumes below the slab. Installing a conduit without room for manoeuvre condemns the future operation of the building to destructive work as soon as the first workstation or Wi-Fi access point is added. Right from the structural work phase, the telematics site foreman negotiates the routing of empty conduits dedicated to extensions along risers and in raised floors. Early installation of this spare capacity avoids subsequent diamond core drilling into reinforced concrete, trenching into floating screeds and operational disruptions for users.

For the terminal connection to floor boxes or dado trunking, the network electrician prefers M25 flexible conduits over M20. Two shielded Cat. 6A twisted-pair cables occupy a significant cross-section and demand bending radii that respect high-frequency signals. In vertical technical service ducts, installing bundles of M32 or M40 conduits with continuous nylon pull cords enables anticipation of routing additional optical fibres or copper pairs. Plugging conduits before concreting prevents cement ingress and guarantees that the pull wire remains fully usable during subsequent cable-pulling operations.

Coordination with the bricklayer and the steel fixer is decisive. The telematics craftsman checks for the absence of sharp bends: two consecutive 90-degree bends without an intermediate pull box permanently jam the draw wire when pulling rigid-sheathed cables.

Pulling capability and spare capacity according to nominal conduit diameter
KRFW conduitUsable diameterCat. 6A cables installedAvailable spare capacity
M2014 mm1 cable of 8 mm0% (conduit saturated)
M2519 mm2 cables of 8 mm30% (compliant spare capacity)
M3225 mm3 cables of 8 mm45% (easy extension)
M4032 mm6 cables of 8 mm40% (backbone link)

Patch panels and rack height: sizing capacities and costing upgradability

Fitting out the network rack in the technical room requires rigorous projection of hardware requirements. Too many 19-inch cabinets end up saturated as soon as acceptance of the work takes place due to a lack of overall vision. The telematics technician must lock down the spare capacity for patch ports and the vertical volume in rack units (U) to accommodate future network switches, additional patch panels, power distribution units and shelves for floor servers. Each modular copper patch panel must be selected to allow the addition of Keystone connectors without dismantling the supporting frame.

Rack unit (U)
Standardised height of 44.45 mm (i.e. 1.75 inches) governing the vertical stacking of active and passive equipment in 19-inch distribution racks and cabinets.
  1. Calculating the spare capacity of patch portsDedicate twenty to thirty per cent free slots on distribution panels. Using straight or angled 24-port modular panels fitted with shielded RJ45 modules allows future connectors to be inserted individually without disrupting operational links.
  2. Allocating rack units in the cabinetSize the cabinet to retain at least one third free U units. Systematically insert a 1U horizontal cable tidy between each patch panel and each switch to ensure patch cord management without sharp bends.
  3. Formalising extension costingDetail the cost of extension options in the initial tender: supply of complementary modules, pulling an additional link and integrating patch cords. This pre-agreed rate schedule protects the parties against unforeseen financial addenda.

Financially, integrating technical spare capacity right from the start is far more cost-effective for the client. Specifying a 42U cabinet rather than a 24U model, doubling risers with M32 conduits and installing pre-equipped patch panels only leads to a marginal increase in material costs, in the region of 10 to 15% on the cabling package, whereas replacing a full cabinet or embedding containment during the operational phase multiplies the final bill by five. For the detailed costing of associated supplies and services, the quote is structured according to standardised items.

Initial trade-off: establishing the three-reserve ratio at the preliminary design stage

When managing a major commercial or residential construction site, the structured copper network faces constant pressure towards densification. From the very first technical coordination meetings, the telematics technician faces tight spatial trade-offs: technical service ducts and suspended ceilings shrink beneath the stacking of the building's mono-service utilities. To guarantee the durability of the communication infrastructure without generating premature operational extra costs, negotiations must jointly address three distinct reserves: empty conduits in risers and slabs, patch ports in faceplates or panels, and free height in the IT rack. Accepting handover without extension margin condemns the operator to destructive works as soon as workstations, wireless access points or CCTV cameras are added.

Spare conduit capacity is anticipated right from the marking out of penetrations and slab crossings. In risers, systematically installing one empty conduit for every three occupied conduits guarantees the future routing of a horizontal link or fibre backbone without diamond drilling in an occupied environment. Each spare conduit is fitted with a rot-proof draw line and watertight plugs at the ends to prevent laitance ingress. For patching, spare capacity is established on distribution frames: using unloaded modular patch panels in Keystone format allows connector-by-connector upgrades without replacing the entire panel. Finally, spare height units (U) in the rack ensure subsequent integration of PoE switches and fibre patch panels, while preserving the volume essential for patch lead routing and thermal dissipation of active equipment.

Integration specifications for cabling and housing spare capacities
Type of spare capacityRecommended sizingPractical implementationConsequence of undersizing
Conduits and ducts25 to 30% free cross-sectionKRF/KRG conduits with nylon draw wire and watertight couplingsSub-structure core drilling and removal of stud partition walls
Patch ports20 to 25% free slots24-port 1U modular panels fitted with blanking platesPatch frame saturation and untagged trailing patch leads
Rack height (U)30 to 40% available volume42U rack instead of 24U with 1U cable management barsComplete replacement of the cabinet and service outage

Differential costing and defending spare capacity to the client

The client or architect often perceives the request for residual space as superfluous expenditure that impinges on usable floor space. To convince the site management, the team leader or project manager must present a rigorous comparative costing: counterbalancing the marginal cost of an additional conduit installed during the structural work phase against the expenditure caused by post-handover work. Installing an empty conduit before concrete pouring or selecting a rack frame one size larger only generates a minimal material surcharge, without slowing down installation rates. Conversely, pulling a data run in a completed building requires dismantling suspended ceilings, remedial drilling, paintwork repairs and meticulous restoration of firestop barriers.

To anchor these provisions contractually, each reserved pathway and each free technical volume must be recorded on the working drawings issued to the engineering consultancy. If the initial quote imposes profile reductions, the telematics technician records in writing the resulting technical limitations on the future operation of the building. When handing over the as-built drawings, spare conduits and vacant faceplate positions are meticulously inventoried with their routing and labelling. This documentary rigour prevents other finishing work trades from appropriating conduits left empty to run unforeseen cabling before acceptance of the work.

Managing unfavourable trade-offs and unforeseen saturation on site

On the construction site, the elimination of expansion margins often results from immediate financial pressure from the client or a lack of spatial coordination between consultants. When the site management refuses the initial oversizing of ducts or the choice of a larger rack, the telematics technician CFC 238 must record the technical impact of this decision. An IT or home automation network without residual capacity precludes any subsequent addition of wireless access points, control gateways or workstations without destructive masonry work.

If the construction site requires cost cutting, the contractor gives priority to preserving heavy physical pathways over active or modular components. It is technically preferable to install patch panels partially loaded with RJ45 connectors rather than reducing the diameter or number of embedded conduits.

  • Systematic verification of conduit routes under slabs using a draw wire before pouring concrete to detect crushing.
  • Recording on as-built drawings reserved empty conduits, identified with nylon pull cords and sealing plugs.
  • Prioritised installation of unloaded Keystone faceplates on panels to defer the purchase of shielded connectors without blocking the chassis.
  • Reservation of at least 20% vertical space in the 19-inch enclosure for future addition of patch cord organisers or uninterruptible power supplies.

In the event of proven obstruction of an embedded conduit unrecoverable with a steel fish tape, a joint inspection record must be drawn up with the structural work site manager. The cost of an emergency pathway in a suspended ceiling or under surface trunking then becomes a charge allocated to the party liable for the damage, thereby preventing handover hold-ups when commissioning the copper links.

Frequently asked questions

What should be done if a reserved M25 conduit emerges crushed after slab formwork stripping?

The telematics technician carries out a joint draw wire test in the presence of the site management. If the pull wire fails to pass, a technical inspection report is drafted. Rectification requires locating the pinch point using metric markings on the draw tape, followed by localised diamond coring of the concrete or negotiating an exposed bypass route in technical rooms in accordance with standard SIA 118 rules.

What minimum spare capacity of patch ports should be provided on an RJ45 panel?

Good professional practice recommends an available spare capacity of between 20% and 30% on floor distribution frames. In commercial installations, using 24-port modular panels in Keystone format allows only the connectors ordered in the base quote to be fitted, while reserving empty slots to insert future modules without having to add a complete panel or redress the rear harness cabling.

How can the additional cost of a 42-unit rack compared to a 24-unit cabinet be justified?

The argument is based on the whole-life operating cost of the building. Replacing a saturated 19-inch enclosure after a few years requires full network disconnection, IT service disruption and complete re-termination of copper links. The purchase price difference between a 24U rack and a 42U rack remains minimal compared to the labour cost that a live replacement would incur.

How can future extension be costed without penalising the profitability of the initial tender?

The installer prepares a separate costed variant in the tender. The base amount includes the installation of empty conduits of larger cross-section, such as M25 conduit instead of M20, and rack space reservations. Additional cables, RJ45 modules and patch leads are quantified as optional unit prices, which protects the main offer while clearly defining the future connection cost.

Texts and standards cited

  • CO art. 365Defective material and ground, or circumstances compromising regular execution
  • norme SIA 118General conditions for construction work