Site coordination and telematics safety: execution baseline
Aimed at site managers, foremen and telecom network installers, this guide brings together Swiss execution practices for smoothly integrating extra-low voltage into structural work and finishing work. Between pouring schedules, mineral dust and risks of falling beneath slabs, you will find concrete benchmarks to preserve the integrity of your physical links, work in compliance with SUVA directives and protect your teams daily.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
2 m
Fall height above which a guard rail or equivalent device is required
100 cm
Minimum height of the upper edge of a top rail on perimeter guard rails
15 cm
Minimum height of the retaining toeboard at the base of a protective guard rail
19 to 21 %
Normal volume range of oxygen required in ambient air at workstations
Scope of work of the telematics technician and interface boundaries
The field of the telematics technician CFC 238 focuses on extra-low voltage, data connectivity, copper or optical infrastructure and building automation buses such as KNX. This specialisation requires constant vigilance during interactions with other trades on Swiss construction sites, from the raw concreting phase through to handover of the finished premises.
- Included in this guide: scheduling cable pulling in relation to screed layers and plasterers, routing cables in renovations, safety during core drilling and disc cutting, preventing falls from height beneath slabs and in raised floors, shared management of cable trays, working in live server rooms, traceability of delegated tasks, secure storage of racks and active components, safe collection of specific waste and the methodical handling of crushing beneath screed.
- Excluded from this guide: all mains power distribution (main electrical distribution boards, conductor cross-section calculation, circuit breakers, earthing system, inspections within the meaning of the ordinance on low-voltage electrical installations), which falls within the remit of the electrician CFC 232.
- Excluded from this guide: thermodynamic parameter setting of heat generators (CFC 241) and air-handling adjustments of air handling units (CFC 244). The telematics technician pulls, terminates and tests the KNX or BACnet bus up to the gateway, but does not adjust the thermal production equipment.
- Excluded from this guide: fire alarm systems subject to acceptance by certified companies in accordance with VKF/AEAI requirements, heavy core drilling of structural elements reserved for masons CFC 211.1, as well as the erection or acceptance of façade scaffolding, which is the responsibility of scaffolders CFC 212.
The telematics technician never operates in isolation. Their conduits share space on slabs cluttered with rebar, their cable trays intersect plumbing and ventilation ductwork, whilst their optical connectors require clean ambient air for splicing. Knowing how to establish clear technical boundaries right from the weekly site meeting is the first safeguard against costly disputes and remedial structural work.
Methodical progression: from raw slab to acceptance of links
The ten chapters of this section form an operational curriculum designed to track the physical progression of a project, from the raw slab through to final operational handover of the network links.
- Phase 1: Chronology and wall constraints (I6-01 to I6-03)Schedule management begins with the rigorous alignment of operations between structural work and finishes. We look at routing prior to screed laying to protect conduits, pulling tricks in occupied conduits of older buildings, and collecting fine quartz dust using industrial extraction during drilling.
- Phase 2: Overhead work and technical coexistence (I6-04 to I6-06)The focus then shifts to physical safety at height, precluding the use of ladders as prolonged workstations in accordance with the construction work ordinance. This is followed by geometric allocation of cable trays and the shutdown protocol when working on servers in service.
- Phase 3: Liability, material management and damage incidents (I6-07 to I6-10)The final section covers managing external labour, anti-theft protection of PoE switches before lockup, sorting optical glass offcuts, and measures to take when fresh screed severs a bundle of data cables.
Following this path enables the site manager to anticipate friction between trades, reduce the stepladder accident rate to zero and ensure unreserved acceptance of the passive infrastructure.
📘 Chapters in this section 10
Passing through at the right time: before the screed, after the plasterer, before painting
Coordinate conduit installation between concrete pouring, plaster spraying and painters' work.
Construction site coordination and safety for telematics techniciansCabling in existing builds: fish tapes, occupied conduits, and chases as a last resort
Pull cables through congested existing conduits without damage using suitable lubricants and draw tapes.
Construction site coordination and safety for telematics techniciansCoring safely: source extraction, masks, and noise
Eliminate silica dust during core drilling with a certified dust extractor to protect your lungs.
Construction site coordination and safety for telematics techniciansWorking below ceilings: platform, ladder ban and falling objects
Make your ceiling operations safe by replacing unstable ladders with a suitable podium step.
Construction site coordination and safety for telematics techniciansSharing a cable tray: reservation, installation order, space
Reserve your usable space on shared cable trays alongside electricians and ventilation fitters.
Construction site coordination and safety for telematics techniciansWorking on a live production site: window, notice and rollback
Work in live server rooms without unintended outages by using a fallback plan.
Construction site coordination and safety for telematics techniciansSubcontracting installation: supervision, inspection, and final liability
Supervise subcontracted cable pulling to ensure end-to-end link compliance.
Construction site coordination and safety for telematics techniciansSafeguarding equipment: storage, switch theft and delivery timing
Protect your valuable distribution frames and switches from moisture, dust and theft on the construction site.
Construction site coordination and safety for telematics techniciansClean disposal: copper offcuts, fibre offcuts, and packaging
Dispose of copper offcuts and secure fibre debris to avoid skin punctures.
Construction site coordination and safety for telematics techniciansFifteen dead links under the screed: findings, liability and directed remediation
Document severing under screed to demand immediate repair coverage by the liable contractor.