Drywall partitions: framing, linings and performance: the execution reference

Building a drywall partition requires reconciling mechanical strength, sound insulation and fire safety. Aimed at team leaders and site supervisors, this section brings together the rules of the trade for CFC 271 to design and install metal-stud partitions compliant with SIA 242 and SIA 181. From sizing the studs to connecting to the structural work and the screed, each step secures technical acceptance without unpleasant surprises.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

norme SIA 242

600 mm

Standard maximum spacing of metal studs in a partition wall

norme SIA 242

50 mm

Minimum longitudinal offset between board joints in a multi-layer lining

norme SIA 242

15 m

Maximum continuous straight length before a movement joint must be created

norme SIA 242

5 mm

Minimum residual gap below the ceiling to absorb the foreseeable deflection of the slab

Technical scope of CFC 271 and limits of the works

Dry construction under CFC 271 covers all non-load-bearing lightweight partitions built on a metal framing, their plasterboard or cement-board linings, the integrated thermal and acoustic insulation and the treatment of joints. The final performance depends on a complete and inseparable system: galvanised steel sheet profiles, elastomer decoupling strips, mineral wool batts and screwed linings. The dry-lining plasterer delivers a flat, stable surface ready to receive the finishes, at the quality level agreed with the site management.

  • Included in the trade: marking out on the floor and ceiling, installation of perimeter profiles and vertical studs, acoustic and thermal insulation in the cavity, internal reinforcements for suspended loads, installation of boards and jointing in accordance with SIA 242.
  • Excluded - Structural work (CFC 201 and 211.1): masonry, concrete walls and slabs, structural sealing of structural-work joints.
  • Excluded - Interior joinery (CFC 273): supply and fitting of door sets and frames in timber or metal, the plasterer being limited to reinforced head profiles and edge studs.
  • Excluded - Screed and floor coverings (CFC 281): execution of the liquid or traditional screed and perimeter floor strips.
  • Excluded - Building services (CFC 232, 241, 250): pulling of cables, ventilation ducts and sanitary pipes, the drywaller carrying out only the drilling of the framing and the precise cut-outs for boxes.

Site progression method and use of the data sheets

Building a network of drywall partitions leaves no room for improvisation. To prevent acoustic or mechanical non-conformities, the team leader plans the work in a strict sequence. Each project stage refers to the chapters of this section, designed as practical execution guides for the field.

  1. 1. Sizing and setting outValidate the ceiling heights, the framing width and the stud spacing (N1-01) to ensure stability under wind and pressure. Analyse the levelling and out-of-plumb constraints on the structural work (N1-04), always interposing the resilient strip.
  2. 2. Technical coordination and provisions for openingsDetermine whether the partition stops on a raw slab or on a floating floor in order to satisfy SIA 181 (N1-09). Incorporate the fixing cross-members suited to heavy loads (N1-02), frame the door frames with reinforced studs (N1-05) and manage the passage of service ducts without ruining the sound insulation (N1-06).
  3. 3. Choice of linings and special roomsDistinguish dry rooms from rooms subject to water splashing by selecting impregnated plasterboard or cement-based boards (N1-03) according to the degree of exposure to moisture.
  4. 4. Fixing, movement joints and finishingFit the screws at a regular spacing without piercing the paper face. Provide movement joints on long corridor runs (N1-08) and carry out the jointing with paper tape in three successive passes (N1-07).
  5. 5. Waste management and end of construction siteIn the case of refurbishment or later dismantling, organise strict selective sorting between steel profiles, mineral wool and plasterboard in accordance with art. 17 OLED to feed the closed recovery channels (N1-10).

📘 Chapters in this section 10

Drywall partitions: framing, linings and performance

Choosing the framing: stud spacing, limiting height and profile width

Determine the exact profile and spacing according to the height to guarantee rigidity under service loads.

Drywall partitions: framing, linings and performance

Hanging items on a dry partition: reinforcement, timber crosspiece and actual load

Plan the position of the cross-members in advance to hang heavy furniture and washbasins without tearing out the lining.

Drywall partitions: framing, linings and performance

Wet room: moisture-resistant board, cement board and the limits of each

Select the appropriate board for private wet rooms and communal showers to stop moisture.

Drywall partitions: framing, linings and performance

Connecting to the existing structure: left wall, fitting clearance and levelling strip

Neutralise acoustic bridges and compensate for out-of-plumb structural work during perimeter fixing.

Drywall partitions: framing, linings and performance

Preparing a door: opening, reinforcement of the door frame and a partition that no longer moves

Tie the door frames in securely to withstand repeated slamming without cracking the adjacent plaster.

Drywall partitions: framing, linings and performance

Letting services through: stud perforations, back boxes and making good the lining

Coordinate the drilling of studs and flush-mounted boxes in order to preserve the acoustic and fire insulation.

Drywall partitions: framing, linings and performance

Treating joints: paper tape, three-coat filler and internal corners

Master the bedding of the paper tape and the three coats of jointing compound for a perfect result.

Drywall partitions: framing, linings and performance

Long runs: control joint, building movement and anticipated cracking

Position the strategic movement joints to avoid defects caused by building shrinkage.

Drywall partitions: framing, linings and performance

Partition and floating screed: which comes first, and why it matters

Install your partition on a slab or on a floating screed while controlling the critical acoustic decoupling.

Drywall partitions: framing, linings and performance

Dismantling cleanly: selective removal, recyclable plasterboard and mineral wool

Organise selective removal to recycle the plaster in a closed-loop channel in line with environmental requirements.