Skip to content
Website
🧱 CFC 238Certification, measurement and acceptance dossierChapter 5 of 10 in the section

The handover file: drawings, test results, nomenclature, and reservations

Upon handover of universal cabling or a fieldbus, an incomplete file guarantees costly disputes at the first outage. This chapter details the mandatory documentary contents of an as-built documentation file, durable computer storage formats, and the rigorous procedure for handling reservations to definitively conclude the installer's liability.

Key takeaways

  • The as-built documentation establishes the actual status of copper, fibre-optic, and bus links.
  • Exported test results must strictly retain both the certifier's native format and PDF.
  • The nomenclature for outlets and patch panels must match the as-built drawing exactly.
  • Joint clearance of reservations is a prerequisite for the formal start of the warranty period.

Minimum contents of the technical file and durable data formats

Handing over a communications infrastructure without a complete operation file exposes the telematics technician to years of unpaid call-outs. In the event of a subsequent malfunction or floor refit, the operator systematically turns back to the installer if the actual label markings appear nowhere. The final documentation is not a mere administrative formality, but the contractual deliverable that validates the conformity of the installed IT and building automation links.

  • As-built drawings in vector format and PDF with exact locations of communication outlets, pull boxes, and enclosures.
  • Single-line diagrams of patch racks, reflecting strip numbering, panel layout, and U allocation.
  • Vertical distribution schematics detailing the installation of multi-pair copper backbones and fibre-optic cables.
  • Electronic certification reports for 100% of tested permanent links, both copper and fibre-optic.
  • Programming project for the KNX home automation installation exported in native format, including physical addresses and group addresses.
  • Technical data sheets of installed components, declarations of performance regarding reaction to fire, and environmental data sheets.
Documentary requirements and IT formats for network acceptance
Technical deliverableRequired computer formatCritical content verified at handover
As-built drawingsVector DWG and PDF/AActual routing, bending radii observed, labelling identical to faceplate tags
Copper certification (Cat. 6A)Native test file and PDFNEXT margin, Return Loss, actual measured length, loop resistance, and pin-to-pin wire map
Fibre-optic certificationNative OTDR file and CSVOverall attenuation in dB, loss budget for splices, connectors, and test wavelength
Home automation bus backupSoftware project archive fileComplete topology, line couplers, device parameters, and function allocation

The nomenclature applied on drawings must comply strictly with that affixed to outlet faceplates and patch panels. Any discrepancy between physical labelling on the construction site and numbering shown on the layout drawing renders the documentation unusable. The operator is then no longer able to diagnose an incident or patch a workstation without dispatching two technicians with a tone generator.

Handling reservations and contractual close-out according to standard SIA 118

The acceptance of a telecommunications installation seals the transfer of risks and marks the starting point of warranty periods. Where the parties refer to standard SIA 118, this step is formalised through a joint on-site inspection, recorded in an official formal record. Under art. 367 CO, the client must inspect the condition of the work as soon as feasible after handover and give notice of defects to the contractor.

  1. Joint inspection and identification of non-conformitiesThe installer and the site management inspect the general condition of the racks, the cleanliness of the patch drawers, the absence of plaster dust in RJ45 connectors, and overall labelling. Every non-conformity identified is entered in the formal record with its precise description.
  2. Defect categorisation and reservation classificationThe parties distinguish minor defects that do not hinder the use of the network from critical defects. A permanent link that fails to comply with normative requirements or a fibre patch cord bent beyond tolerance must be classified immediately to define the rectification protocol.
  3. Setting a formal rectification scheduleA reasonable deadline is agreed jointly for each point of non-conformity. This deadline must account for specific procurement times, for instance for replacing a modular panel or a damaged optical cassette.
  4. Re-testing and written clearance record of reservationsFollowing remediation of the affected link, a new test cycle is run on the certification tester. The new timestamped test report is appended to the reservation clearance form, signed jointly by the site foreman and the client's representative.

Once all reservations have been cleared and signed off, the final file must be submitted in two separate digital sets: physical durable media stored directly in the main distribution frame rack, and an archive copy handed over to the project management. This dual archiving protects the contractor against common document loss during building ownership transfers.

Integration of as-built drawings and durability of test data

An execution drawing marked up by hand on the edge of a workbench does not constitute an as-built drawing. For enterprise communication networks (CFC 238), technical as-built documentation records the precise reality of cable routes after closure of suspended ceilings, risers, and raised floors. Any route modification required by spatial coordination with HVAC or pipework must be plotted accurately on the vector drawing files. The location of recessed junction boxes, consolidation points, and fibre or copper cable reserve loops determines whether the installation can be maintained operationally without destructive exploratory work.

The validity of acceptance hinges on the durability of the test result format. Submitting solely printed summaries or non-editable PDF files represents a major risk for both the operator and the installer. The file must strictly include the raw databases exported directly from cable certifiers of the required accuracy class. These proprietary or interoperable files retain all spectral curves: return loss, near-end crosstalk (NEXT), propagation delay skew, and physical length calculated from the measured refractive index.

Minimum alignment nomenclature between site, drawing, and certification report
Physical componentAs-built drawing identifierFaceplate / panel tagAssociated entry in raw export
Horizontal copper linkL-03-B2-RJ45-104R3 / P02 / Port 14Identical channel name + timestamp
Consolidation point (CP)CP-03-North-ZoneCP-NZ-Enclosure 2Cumulative interconnection attenuation
Optical backboneFO-SM-BLD-A-B-12R0 / Optical Drawer 01 / Cores 1-12Bidirectional OTDR
Floor bus lineBUS-KNX-FL02-L1LV-Switchboard-ELV / Terminal block X3Record of ETS physical addresses

Technical management of reservations and securing the warranty

Rigorous management of reservations during acceptance of the work determines the commencement of the warranty periods provided for by standard SIA 118 and the application of the Code of Obligations (CO). Where a copper link exhibits an impedance fault or an optical core shows a break located by optical time-domain reflectometry, the technical reservation is logged in the formal record with explicit identification of the room, panel, and affected connector. The installer then has a contractually defined period to rectify the issue, failing which the client may resort to substitute performance.

  1. Classification of defects during the joint inspectionFormally differentiate blocking reservations (inoperative link, optical attenuation exceeding the contractual link budget) from minor documentary reservations (incomplete labelling on a patch panel, misaligned faceplate).
  2. Technical rectification on the installationReplacing the defective RJ45 module, completely re-splicing via core-alignment fusion, or pulling a new conductor if the permissible bending radius was exceeded in the slab.
  3. Re-testing and systematic re-exportAny physical intervention invalidates the original test. A new certification run must be logged in the tester with explicit indication of the rectification date, without improperly overwriting fault histories.
  4. Joint signature of the clearance slipPreparation of the close-out document incorporating the new test sheets. Joint signature certifies the discharge of the reservation and finalises the definitive as-built documentation.

Under CO, the client's claims for defects in immovable structures are barred by the limitation period of five years. A dispute regarding packet drops or service outages occurring after two years of operation is resolved by consulting the records handed over at acceptance of the work. If the initial file proves that connectors were delivered free of scratches on video inspection and compliant with normative limits, the presumption of user-caused degradation prevails. Without these timestamped, sealed records, the contractor is compelled to cover complex troubleshooting and the remediation of links damaged by third parties at its own expense.

Acceptance dispute management and late claims

The dreaded scenario arises frequently: two years after commissioning, an IT fault or a KNX infrastructure modification leads the operator to commission an expert evaluation. If the as-built documentation cannot be found, is incomplete, or was provided in an unreadable proprietary format, the contractor is left defenceless against the claims of the client.

Under art. 367 CO, following handover, the client must inspect the condition of the work as soon as feasible and give notice of defects to the contractor. Under standard SIA 118, a two-year warranty period begins upon formal acceptance of the work. During this period, the burden of proof is reversed against the installer: the telematics technician must prove that the network complied with tolerances when the keys were handed over.

  1. Comparing against original dataAs soon as a notice of defects is served, retrieve the native Fluke LinkWare or equivalent file archived during acceptance of the work. This report certifies the crosstalk margins, actual lengths, and optical attenuation measured before the premises were occupied.
  2. Inspection of physical as-built integrityConduct a joint inspection record on site with the representative of the client. Check whether the cables have been subjected to subsequent mechanical stress or whether patch racks have been modified by a third party without respecting bending radii.
  3. Formal close-out of reservation clearanceDemand the signing of the definitive clearance record as soon as initial rectifications are complete. A defect logged as an outstanding reservation prevents the release of financial guarantees and leaves the construction site contractually open.

Art. 371 CO sets the limitation period for the client's rights arising from defects at five years for immovable structures. In view of this duration, only the rigorous retention of a full digital duplicate of the handover file — drawings in open format, raw test databases, and KNX programming — protects the contractor against unwarranted remediation work caused by improper subsequent operation.

Frequently asked questions

What should be done if the client refuses to sign the formal acceptance record for a defective copper link?

Isolate the disputed link immediately within the reservations list with a precise intervention deadline. Replace the modular connector or pull a new replacement cable, then run a complete certified re-test. Submit the updated test report together with the reservation clearance slip signed by your site foreman to secure formal signature of the record by the site management.

How can it be proved that optical fibre degradation occurred after acceptance of the work?

Comparison between the original reflectometry file included in the as-built documentation and a new OTDR measurement provides definitive proof. If the initial trace shows a compliant splice below the contractual threshold and a break or stress now appears midway along the run, you formally demonstrate that the damage stems from third-party intervention after handover of the work.

The client demands the unlocked ETS project: are we obliged to provide it?

Yes, the as-built documentation must include the complete KNX home automation project archive exported without password protection. The operator must be able to maintain, reconfigure, or expand its building management system fully autonomously. Withholding the programming database constitutes a contractual breach that prevents the release of retention money and approval of acceptance of the work.

Which file formats guarantee the readability of layout drawings ten years later?

Systematically provide diagrams and as-built drawings in two complementary formats: vector DWG for future revisions by an engineering consultancy, and standardised PDF/A for long-term document consultation. Prohibit proprietary files from non-interoperable CAD software that lack a certified free viewer for long-term archiving.

Texts and standards cited

  • norme SIA 118General conditions for construction works, governing acceptance of the work, the two-year defect notification period, and warranty for hidden defects.
  • CO art. 367Inspection of the work and notification of defects by the client to the contractor following handover.
  • COLimitation period for the client's rights in respect of defects in the work, set at five years for immovable structures.

In the same section