Skip to content
Website
🧱 CFC 238Construction site coordination and safety for telematics techniciansChapter 2 of 10 in the section

Cabling in existing builds: fish tapes, occupied conduits, and chases as a last resort

In renovation work, every metre of cut plaster generates costly paint repairs that often exceed the budget for the network package. This chapter details the strict hierarchy of interventions required to run a data cable without damaging finishes: non-invasive location, mechanical fish tape techniques, routing through building voids, and the formal framing of a negotiated chase.

Key takeaways

  • Probe existing conduits with a tracer fish tape to identify the route before attempting any pulling operations.
  • Systematically lubricate the bundle to prevent any permanent jamming or frictional heating within the conduit.
  • Bypass masonry obstacles by using hollow skirting boards, demountable suspended ceilings, and accessible service shafts.
  • Require a written addendum pricing the plaster repairs before cutting into the masonry for a chase.

From conduit tracing to lubricated fish taping: using the existing build without opening walls

In an existing building, opening a wall represents the most destructive and expensive solution. The network electrician always begins by identifying usable embedded conduits between the communication board or floor distributor and the location of the future RJ45 socket. This tracing process requires methodically opening intermediate junction boxes, disused telephone sockets, and switch faceplates. A cable locator coupled with a transmitting probe or an endoscopic inspection camera allows tradespeople to confirm the actual run of the conduits and detect frequent crushing within slabs or sharp bends.

The presence of an existing conductor requires calculating the available space. The outer diameter of a shielded Category 6A twisted-pair cable ranges between seven and eight millimetres. Introducing such a cross-section into a 16 mm diameter corrugated conduit already occupied by a coaxial cable or an old telecommunication pair exposes the installation to irreversible jamming. Fish tape routing is always carried out using a draw wire matched to the diameter and curvature of the run.

  1. Mechanical probing and installing the draw wirePush a fibreglass fish tape with a flexible leader or guiding eyelet from the terminal box back to the starting point. If the conduit is congested, a twisted polyester fish tape offers better buckling resistance in bends.
  2. Replacement or joint pullingIf the conduit contains a redundant conductor, this conductor serves directly as a draw wire. Securely anchor the new cable and a pilot wire in a spliced loop beneath tapered adhesive tape to prevent any catch points on the internal corrugations of the conduit.
  3. Continuous bundle lubricationGenerously coat the network cable sheath with a non-greasy, water-soluble synthetic polymer lubricant gel. Never use household detergent or fatty substances, which degrade the outer sheath of data cables over time.
  4. Synchronised and steady pullingOne person pushes the cable at the feed point to introduce it straight along the conduit axis while a second worker pulls the fish tape at a constant speed, without jerking, adhering strictly to the maximum tensile load specified by the cable manufacturer.

Alternative pathways and the ultimate chase: protecting finishes and formalising extra costs

When embedded conduits are crushed, non-existent, or full, the network must use the hollow technical voids of the structure before any cutting of the substrate is considered. The technical objective consists in minimising heavy finishing work by exploiting existing building cavities.

Bypass options without damaging wall surfaces
PathwayImplementationKey point of attention
Suspended ceiling or roof spaceRouting via wire mesh cable tray or clipped rigid conduitMaintaining bending radii during wall drop
Multi-compartment skirting trunkingFixing at base of partition with segregation of power and data circuitsMechanical continuity at doorways and corner junctions
Crawl spaces and basementDistribution from below with targeted vertical drilling behind the socketAirtightness and firestop sealing at slab penetrations
Door frames and wall liningsRouting through the metal framework of lightweight stud partitionsMechanical protection against accidental drilling and drywall screws

Cutting a chase into masonry is done exclusively when all alternative routes have been exhausted. This act constitutes a physical modification of the substrate that goes beyond standard communication installation services. Under art. 365 CO, if any circumstance arises which compromises the proper or timely execution of the work, the contractor must inform the client. The inability to run the network without opening the wall represents precisely this unforeseen situation.

Mechanical cutting is carried out using a twin-blade diamond wall chaser connected to an industrial vacuum cleaner featuring automatic filter cleaning to safeguard ambient air quality and limit the spread of fine dust. The depth must solely accommodate the conduit without weakening the load-bearing structure. Once the conduit is laid and secured with clips or fast-setting plaster, the telematics installer documents the installation with photographic records before final closure by the painter and plasterer.

Routing in existing structures: conduit network diagnosis and hidden pathways

In residential or commercial refurbishment, pulling a Cat. 6A data cable or a KNX bus without altering wall finishes is the primary objective of the network installer. The work must begin with a thorough survey of junction boxes and the tracing of embedded corrugated conduits. To determine the actual route of a KR or KIR conduit hidden behind plaster, the team uses a tracer fish tape fitted with a radio-frequency transmitter or a passive electromagnetic locator. Before attempting any cable insertion, visual inspection of intermediate boxes helps determine conduit capacity: usable diameter, presence of dilapidated telephone conductors, or redundant coaxial links.

Routing a fish tape through an already occupied conduit requires absolute mechanical care. Entry is performed using a fibreglass fish tape with a flexible leader and swivel eyelet, allowing it to negotiate tight bends without aggressively rubbing against existing insulation. Using a suitable pulling lubricant formulated from synthetic polymer liquid gel is essential. Workshop grease or washing-up liquid is strictly prohibited: as they dry, they form sticky residues that polymerise with dust and permanently jam any future withdrawal, alongside posing a risk of chemical degradation to the low-smoke zero-halogen (LSZH) outer sheath.

Order of bypass solutions without paint repairs
PathwayTechnical meansTelematics inspection pointsImpact on finishes
Occupied existing conduitSynthetic polymer lubricant, nylon draw wire or 3 mm fibreglass rodVerification of bending radius (min. 4x outer diameter) and absence of jammingZero: work confined to existing flush-mounting boxes
Hollow or demountable skirting boardInstallation behind skirting with clip-fixing or rear rebate routingMaintaining physical separation from power cabling via internal dividerInvisible: careful removal and reinstatement of timber or PVC profile
Suspended ceiling or roof spaceContainment in rigid conduit or lightweight cable trayTargeted vertical penetration aligned precisely with terminal boxZero: removal of demountable ceiling tiles or access via inspection hatch
Crawl space or cellarThrough-floor drop flush with wall and upward stub under final boxSealing floor penetrations and mechanical protection using metallic conduitZero in finished areas: invisible drill holes executed behind skirting

When the existing conduit is saturated, a common technique consists in withdrawing a redundant conductor and using it as a draw wire. The head of the metal fish tape, or the pulling bundle itself, is firmly anchored to the old wire using a braided steel pulling grip and tapered, moisture-tight taping. If passage via conduit proves unfeasible due to crushing in the slab, the installer redirects the route toward concealed structural voids. Timber skirting on battens permits discreet perimeter distribution. The network cable then runs horizontally along the perimeter of the room, requiring only a blind drill hole behind the skirting to reach the vertical axis of the flush-mounting box.

Mechanical jamming, deciding on a chase, and contractual management of remedial costs

If the embedded conduit exhibits an impassable constriction and no ceiling void or subfloor cavity allows a bypass, non-destructive routing reaches its technical limit. At this point, cutting a wall chase must never be a spontaneous decision by the installer on the construction site. Opening a wall entails irreversible damage to the surface layer. In high-standard renovation work, a ten-centimetre slot in smooth plaster or wallpaper cannot be invisibly repaired locally: the repair compels the painting and plastering contractor to redo the entire wall section from corner to corner, incurring costs disproportionate to the installation of the cable itself.

The site foreman logs the obstacle in the construction site daily report and notifies site management of the issue. In accordance with art. 365 para. 3 CO, if any circumstance arises which compromises the proper or timely execution of the work, the contractor must immediately inform the client. The installer submits a sketch of the proposed direct route, includes a metric estimate with the notice, and suspends work on the link until the change order is approved.

The chase is then addressed through a formalised addendum. This document details precisely the chased route, the installation of the flexible KR conduit, the basic patching with bonding mortar by the telematics installer, and the explicit appointment of the trade responsible for finishes. Expenses associated with fine skimming, applying fibreglass fleece, and fully repainting the wall section concerned are in the region of several hundred francs per room; they must be settled by an accepted supplementary quote before any tool impacts the masonry.

Blocked conduit, snapped fish tape, or refusal to open: escalation protocol

When the fish tape hits a crushed conduit or a bend choked with cement slurry, persistence only destroys existing infrastructure. Forcing with a manual winch or yanking the fibreglass rod risks severing existing conductors or blocking the passage permanently. The site foreman stops pulling, measures the exact distance penetrated on the graduated rod to locate the obstruction, and inspects the immediate surroundings before taking any destructive measures.

  1. 1. Exhaust all concealed pathwaysThe network seeks an alternative route through construction voids: top framework of built-in cupboards, behind thermal linings, space under demountable timber skirting, or vertical service risers alongside soil and vent stacks.
  2. 2. Dismantle without altering finishesCarefully remove demountable architraves, access technical suspended ceilings through existing equipment cut-outs, or bypass the masonry partition by penetrating the floor down to an unfinished basement to re-emerge directly behind the socket.
  3. 3. Issue notification of technical impossibilityIf the route remains entirely sealed, the telematics installer reports the conduit defect to site management. Under art. 365 para. 3 CO, if any circumstance arises which compromises the proper execution of the work, the contractor must inform the client.
  4. 4. Draw up an addendum before cuttingChasing is the final technical resort. No diamond blade touches the masonry without a written agreement specifying the run, mineral dust extraction methods, and financial responsibility for plastering and painting remedial works.

Frequently asked questions

How can a crushed conduit be located precisely within a solid wall?

Push a metal draw wire or rigid fish tape until it hits the obstruction, then mark the rod flush with the conduit entry. Next, transfer that exact extracted length onto the wall surface starting from the junction box. Using a miniature radio-frequency transmitter probe attached to the tip of the fish tape enables electromagnetic tracing down to the centimetre through 20 cm of brick or concrete before considering any local wall opening.

What approach should be taken if the property owner refuses both wall openings and surface-mounted trunking?

When the client rejects masonry chasing and the installation of decorative trunking above skirting boards, the installer diverts the run through secondary rooms. The network link can run below the structural slab through an uninhabited basement, transit via a plant room, or route through roof spaces, enabling vertical drilling directly below the furniture or device without damaging the wall finish of the living room.

Can an old coaxial cable be replaced with a network cable to avoid chasing?

This direct exchange procedure is common practice in telecoms renovation. The installer detaches the end terminations, splices the new data cable securely to the shielding of the old coaxial cable using a slim heat-shrink sleeve, applies pulling lubricant generously, and pulls with steady, non-jerking tension. If the old conductor snaps under tension, the conduit becomes unusable immediately: moderate manual pulling force remains essential.

Who is financially responsible for plaster and paint repairs after a chase is cut?

If the original drawing indicated a clear conduit that turns out to have been crushed during construction, cutting chases and remedial work represent unforeseen additional works. The telematics installer submits a supplementary quote including chasing, firestop filling if required, and the engagement of plasterers and painters. Work begins only after this addendum is formally approved by site management.

Texts and standards cited

  • CO art. 365materials and site: the contractor is liable for the good quality of the materials supplied; if the materials supplied by the client or the site designated by the client are found to be defective, or if any other circumstance arises which compromises the proper or timely execution of the work, the contractor must immediately inform the client, failing which the contractor will bear the consequences (para. 3)

In the same section