Safeguarding equipment: storage, switch theft and delivery timing

After this chapter, you will know how to time the delivery of your switches, routers and KNX gateways to the latest useful date in the master schedule. You will master the on-site reception procedure, the recording of serial numbers, the physical locking of the distribution room, and the contractual clarification of insurance responsibilities in the event of theft or a claim on the construction site.

Key takeaways

  • Active equipment is delivered solely to a ventilated, dry and lockable room.
  • Systematic recording of serial numbers and MAC addresses validates reception on the construction site.
  • A room secured by a dedicated lock cylinder prevents direct access by other trades.
  • Verification of the construction works insurance ensures compensation for components prior to acceptance.

Coordinate delivery to the latest useful date and inventory active components

Unloading enterprise network switches, KNX/IP gateways or PoE injectors prematurely on a construction site exposes this active equipment to major hazards. Delivered two or three months prior to the completion of finishing work, an unprotected rack quickly becomes a target for opportunistic theft or suffers irremediable damage caused by abrasive sanding dust and wet plaster splatter.

To eliminate these perils, the telematics technician applies the principle of delivery at the latest useful date. This coordination demands rigorous tracking of the master schedule alongside site management. Sensitive active equipment only leaves the installer's workshop or warehouse once distribution rooms are fully enclosed, cleaned and temperature-stabilised. As long as doors do not lock and floors continue to emit cement dust, the equipment remains held at the supplier's warehouse or at the contractor's premises.

  1. Inspection of seals and parcelsInspect every carton immediately upon unloading to identify any sign of tampering or crushing before signing the carrier's consignment note.
  2. Recording serial numbers and MAC addressesSystematically scan the barcode of each active unit to log its individual serial number and physical address onto a dedicated tracking sheet.
  3. Preparation of the joint acceptance sheetHave the intake inventory countersigned by the site logistics manager or site supervisor to confirm the physical presence of the equipment.
  4. Placement under waterproof protectionPlace inventoried cartons inside enclosures or onto pallets isolated from ground moisture, sealed under plastic sheeting, until final installation.

Locking the plant room and defining insurance liabilities

As soon as switches and gateways arrive, the physical safeguarding of the storage area becomes paramount. Pursuant to art. 364 CO, the contractor is liable for the work carried out and the means employed. This liability mandates unceasing vigilance over stored components. Plant rooms and floor distribution rooms must under no circumstances serve as thoroughfares or changing rooms for other trades. The site foreman insists on the installation of a solid-core door fitted with an operational lock. If the building's final master key system is not yet deployed, the installer fits a temporary construction cylinder, retaining the keys jointly with the site supervisor.

Required protection levels according to plant room progress
Distribution room stagePredominant risksRequired measures for active equipment
Structural work and wet finishing workResidual moisture, cement dust, impact damageImperative retention of active equipment off-site in the contractor's workshop
Room secured by a temporary door without a keyOpportunistic theft, unauthorised borrowing and damageFitting a lockout padlock or temporary cylinder managed by the telematics technician
Completed, clean and climate-controlled plant roomUncontrolled access during commissioning phasesMaintenance of a key sign-out log and commencement of network configuration

Insurance coverage for burglary, theft and damage must be locked down contractually before equipment is routed to the site. Art. 97 CO stipulates that the debtor must make amends for damage resulting from non-performance of an obligation unless they prove that no fault is attributable to them. Until the acceptance of the work under standard SIA 118, the risks of loss or damage to non-accepted materials generally rest with the installer, unless agreed otherwise with the client. The telematics technician must verify the scope of the construction works insurance policy taken out by the client, particularly the coverage caps applying to IT equipment held in storage. If this policy excludes active equipment not yet bolted into racks, the contractor must extend its own site property insurance policy.

Logging identifiers and admitting active equipment

Premature introduction of network components onto a construction site exposes the contractor to heavy material losses. Managed switches, KNX IP gateways, wireless access points and PoE injectors are prime targets owing to their compact size and high resale value. The latest useful delivery date method requires synchronising the delivery of cartons with the actual completion of the distribution room: painted masonry, dust-sealed floors, fire-rated door hung and operational lock in place. Delivering this equipment three months prior to final cabling turns the plant room into a vulnerable depot, exposed to mechanical damage from other trades and illicit removal.

  1. Verification of original sealsInspect the integrity of tamper-evident tape on each packaging carton immediately upon receipt in front of the dedicated room. Any opened or repackaged carton must be subject to written reservations noted on the carrier's consignment note.
  2. Digitisation of identifiersScan serial numbers, manufacturing part numbers and MAC addresses from the manufacturer labels on the chassis using an optical reader. This record is incorporated into the as-built documentation schedule and checked against the original purchase order.
  3. Drafting the intake inventoryDraft a joint inventory record countersigned by the site manager and site management, confirming physical custody of the modules inside the locked enclosure.

Rigorous logging of serial numbers upon receipt provides the only technical and administrative safeguard against subsequent disputes. If a 48-port switch disappears or sustains mechanical damage during finishing work, the intake register proves that the delivered hardware corresponded precisely to the technical submittals approved at the time of ordering. This inventory document also guarantees traceability for software licences, certificates of authenticity and manufacturer warranties, which are essential during the final commissioning of the building automation or IT installation.

Transfer of risk, insurance guarantees and claims management

Legal custody of active devices remains under the exclusive responsibility of the installer until acceptance of the work. Pursuant to art. 97 CO, the debtor is bound to compensate for the damage resulting from the non-performance of their obligation, unless they prove that no fault is attributable to them. If stored switches disappear without the contractor being able to prove that appropriate protective measures were implemented, the cost of re-purchasing the equipment and the resulting delays remain their liability. Standard SIA 118 provides that the contractor is answerable for deterioration and loss of materials and appliances supplied by them as long as formal handover of the installation has not been executed.

Claims settlement regimes for telecom active equipment
Type of coverInsured eventRequired contractual conditionsFinancial settlement
Contractors' All Risks Insurance (CAR)Theft involving proven burglary into the buildingLocked room, police report accompanied by list of serial numbersReplacement value as new, subject to deduction of the client's general policy excess
Contractor's property insuranceMisappropriation or destruction during on-site storageExclusive custody proven, evidence of forced entry into private plant roomContractual indemnity under insurance policy, excess borne by installer
Absence of forced entry (simple theft)Unexplained disappearance, shared room accessNo physical evidence of forced entry on the locked room access pointsSystematic refusal of indemnity, full cost absorbed by the installer

To pursue recourse with insurance companies following a break-in, the team leader must file a detailed report with the cantonal police as soon as the offence is discovered. This formal inspection report must incorporate the comprehensive list of serial numbers prepared during the intake inventory. Without these unique identifiers, the insurance company may challenge the physical presence of the devices on site at the time of the loss. Furthermore, an official complaint blocks resale of the hardware on the grey market by enabling manufacturers to log stolen chassis onto their international service registries.

Intervention protocol in the event of disappearance or damage in the plant room

Discovering a forced cabinet or ripped-open cartons demands an immediate halt to all handling in the area. The lead installer freezes the scene without moving residual packaging or touching vandalised racks. Pursuant to CO, the contractor notifies the client of any circumstance that compromises the regular or timely execution of the work. This written notice is dispatched to site management that very day.

  1. Scene preservation and visual inspectionTake comprehensive and detailed photographs of forced access points, broken locks and stripped rack rails before carrying out any room clean-up.
  2. Filing a complaint and claims reportingFile a formal complaint with the cantonal police station, supplying an exact inventory of stolen KNX modules and switches along with their MAC addresses.
  3. Formal notification to insurersForward the police report and delivery notes to the contractor's property insurance carrier and to the administrator of the contractors' all risks policy.

Cross-referencing the intake inventory list immediately against remaining equipment identifies the missing components. Serial numbers recorded during unloading eliminate any dispute regarding the actual presence of the devices on site. This documented reconciliation provides the evidentiary basis for insurance loss adjusters to calculate indemnification.

Site management must approve the revised installation schedule. The telematics technician enters the delay caused by the lead time for replacement active components into the site daily log.

Frequently asked questions

Who is financially liable if an unmounted switch disappears from the network room?

Until acceptance of the work has taken place pursuant to standard SIA 118, the contractor retains custody of its supplies. If the room was not formally locked and taken over under key under the exclusive responsibility of site management, the telematics technician bears the cost of the theft. The contractor's commercial property insurance or the client's contractors' all risks policy responds only upon presentation of proof of forced entry and a full intake inventory.

Can one refuse to store active equipment on the construction site if the room is not secure?

Yes, the telematics technician may legitimately refuse to have switches or home automation gateways delivered to a room that lacks a lockable door or functional lock. The active equipment then remains stored in the contractor's warehouse until a clean, dry room fitted with a controlled site cylinder is made available. Written confirmation of this delivery deferral is dispatched promptly to site management to justify project progress.

Why systematically record MAC addresses and serial numbers during unloading?

This systematic record constitutes formal proof of the presence of the specific equipment on the construction site upon delivery. In the event of a burglary, this list provided to police services enables the hardware to be flagged with manufacturers and on second-hand marketplaces. For insurers, these unique identifiers prove that the components claimed for indemnification correspond precisely to the project's purchase invoices and do not reflect theoretical stock.

Does the contractors' all risks policy cover active equipment that is not yet connected?

The contractors' all risks policy covers materials and equipment incorporated into or intended to be incorporated into the work, against theft with forced entry and accidental physical damage. However, it imposes strict storage conditions, specifically storage within an enclosed and roofed building equipped with compliant security locks. Components merely placed in open cartons in a corridor or an area accessible to all trades are routinely excluded from compensation.

Texts and standards cited

  • CO art. 97non-performance of obligation: the debtor is bound to compensate for the damage, unless they prove that no fault is attributable to them.
  • COmaterials and site conditions: the contractor immediately notifies the client of any circumstance compromising the work, under penalty of bearing the consequences.
  • norme SIA 118General conditions for construction work.