Earthworks, excavations and temporary retaining structures: the execution standard
Intended for team leaders and foremen in French-speaking Switzerland, this section covers critical decisions from opening an excavation and shoring down to the formation level. It gathers the execution rules for stabilising slopes, managing water ingress, sorting excavated soils and validating the bearing capacity of backfill. An operational guide compliant with the requirements of standard SIA 267 and federal ordinances applicable to construction sites.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
1 m 50
Maximum depth of an un-shored vertical-sided trench
50 cm
Minimum clearance width to maintain along a shored excavation
1 m 00
Minimum clearance width to maintain along a battered slope
4 m 00
Slope height requiring design justification by a specialist engineer
Technical scope of earthworks and site responsibilities
Opening an excavation directly engages the responsibility of site management from the very first bucket stroke. This section focuses purely on the constructive and geotechnical aspects of earthworks, temporary shoring and laying buried utilities. It guides the contractor in reading the ground, dimensioning standard retaining structures, the methodical compaction of backfill and the environmental traceability of excavated materials.
The site foreman must distinguish between geological hazards and defects in execution. When ground displays unforeseen instability or hidden contamination, the prompt notification procedures set out in the Code of Obligations (CO) allow facts to be recorded without prematurely committing company costs. In earthworks, trench wall stability cannot be improvised: it relies on measurable geotechnical verifications and rigorous acceptance records.
Excavations, shafts and earthworks must be constructed in such a way that the fall or collapse of materials does not endanger any worker (para. 1). Those deeper than 1 m 50 that are not propped or shored must be battered back or secured by other adequate measures (para. 2).
OTConst art. 68
Compliance with excavation regulations protects teams at the bottom of the excavation and safeguards adjacent properties. Operating loads along the edge of the excavation, dumper movements and spoil heaps demand daily vigilance regarding setback berms and shoring systems.
Execution process: from setting out to platform acceptance
Opening an excavation follows a strict technical sequence. To ensure the profitability of earthworks and the conformity of the works, mastering the ten chapters of this section must follow the natural chronological sequence of the construction site, thereby preventing underpinning works and measurement disputes.
- Preparation, survey and initial calculationsBefore mechanical operations begin, set up batter boards outside the collapse zone. Assess the actual volume using bulking factors and characterise contaminated strata to direct lorries to compliant disposal sites.
- Excavation, stability and water managementImmediately adapt slope angles to the nature of the exposed ground. If space is restricted, select the appropriate shoring or supervise the construction of Berlin-type soldier pile walls, while applying for the necessary permits as soon as groundwater appears.
- Utility laying, backfilling and final checksAdhere to trench geometry for pipework, place surround materials in successive layers and validate platform compaction with properly recorded plate load tests.
| Construction site phase | Operational check | Validation deliverable |
|---|---|---|
| Initial pegging out | Profile board setback and centreline levels | Setting-out report |
| Bulk earthworks | Face and slope stability | Geotechnical monitoring sheet |
| Excavation support | Installation of struts and trench boxes | Shoring compliance sheet |
| Formation level | Deformation measurement under load | ME plate load test report |
Strutting and shoring must resist foreseeable loads and forces, be executed according to good engineering practice, and be dimensioned taking additional loads (vehicles, machinery, spoil heaps) into account.
OTConst
For managing unforeseen site conditions, earthwork delays due to bad weather or volume disputes, the contractual provisions of standard SIA 118 define the mandatory notification formalities to assert the contractor's rights.
⛏️ Chapters in this section 10
Plate bearing test on excavation base: ME target values and recording procedure
Secure acceptance of the excavation bottom by achieving the contractual deformation moduli.
Earthworks, excavations and temporary shoringTalutage d'une fouille : les angles de pente admissibles selon le terrain rencontré
Determine compliant slope angles to prevent cave-ins without excavating surplus volume.
Earthworks, excavations and temporary shoringChoisir un blindage de fouille : palplanches, caissons ou blindage coulissant
Select trench boxes, sliding-rail systems or sheet piles according to site constraints and earth pressure.
Earthworks, excavations and temporary shoringBulking factor: calculating the volume of soil actually to be removed
Adjust your lorry cycles and quantity surveys by mastering bulking factors according to the ground.
Earthworks, excavations and temporary shoringExcavation dewatering: lowering, discharge and cantonal permit
Master pumping systems and administrative procedures for discharging dewatering effluent.
Earthworks, excavations and temporary shoringContaminated soil on a Swiss construction site: material classification and landfill disposal route
Identify signs of contamination on the construction site to direct materials to the compliant disposal facility.
Earthworks, excavations and temporary shoringSoldier pile wall and soil nailed wall: execution and monitoring
Supervise section drilling, concreted infill and excavation passes for a soil-nailed retaining wall.
Earthworks, excavations and temporary shoringTrench excavation for pipework: minimum width, pipe bedding and surround
Ensure the proper bedding of pipes and prevent settlement through correct trench opening widths.
Earthworks, excavations and temporary shoringBackfill compaction: layer thickness and bearing capacity control
Coordinate roller passes and verify the bearing capacity of materials reused as backfill.
Earthworks, excavations and temporary shoringExcavation setting out: batter boards, transfer of dimensions, and checks before the first bucket
Check alignments and reference levels before deploying the mechanical excavator for bulk excavation.