Earthworks, excavations and temporary retaining structures: the execution standard

Intended for team leaders and foremen in French-speaking Switzerland, this section covers critical decisions from opening an excavation and shoring down to the formation level. It gathers the execution rules for stabilising slopes, managing water ingress, sorting excavated soils and validating the bearing capacity of backfill. An operational guide compliant with the requirements of standard SIA 267 and federal ordinances applicable to construction sites.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

OTConst art. 68

1 m 50

Maximum depth of an un-shored vertical-sided trench

OTConst art. 71

50 cm

Minimum clearance width to maintain along a shored excavation

OTConst art. 71

1 m 00

Minimum clearance width to maintain along a battered slope

OTConst

4 m 00

Slope height requiring design justification by a specialist engineer

Technical scope of earthworks and site responsibilities

Opening an excavation directly engages the responsibility of site management from the very first bucket stroke. This section focuses purely on the constructive and geotechnical aspects of earthworks, temporary shoring and laying buried utilities. It guides the contractor in reading the ground, dimensioning standard retaining structures, the methodical compaction of backfill and the environmental traceability of excavated materials.

The site foreman must distinguish between geological hazards and defects in execution. When ground displays unforeseen instability or hidden contamination, the prompt notification procedures set out in the Code of Obligations (CO) allow facts to be recorded without prematurely committing company costs. In earthworks, trench wall stability cannot be improvised: it relies on measurable geotechnical verifications and rigorous acceptance records.

Excavations, shafts and earthworks must be constructed in such a way that the fall or collapse of materials does not endanger any worker (para. 1). Those deeper than 1 m 50 that are not propped or shored must be battered back or secured by other adequate measures (para. 2).

OTConst art. 68

Compliance with excavation regulations protects teams at the bottom of the excavation and safeguards adjacent properties. Operating loads along the edge of the excavation, dumper movements and spoil heaps demand daily vigilance regarding setback berms and shoring systems.

Execution process: from setting out to platform acceptance

Opening an excavation follows a strict technical sequence. To ensure the profitability of earthworks and the conformity of the works, mastering the ten chapters of this section must follow the natural chronological sequence of the construction site, thereby preventing underpinning works and measurement disputes.

  1. Preparation, survey and initial calculationsBefore mechanical operations begin, set up batter boards outside the collapse zone. Assess the actual volume using bulking factors and characterise contaminated strata to direct lorries to compliant disposal sites.
  2. Excavation, stability and water managementImmediately adapt slope angles to the nature of the exposed ground. If space is restricted, select the appropriate shoring or supervise the construction of Berlin-type soldier pile walls, while applying for the necessary permits as soon as groundwater appears.
  3. Utility laying, backfilling and final checksAdhere to trench geometry for pipework, place surround materials in successive layers and validate platform compaction with properly recorded plate load tests.
Earthwork phases and associated control documents
Construction site phaseOperational checkValidation deliverable
Initial pegging outProfile board setback and centreline levelsSetting-out report
Bulk earthworksFace and slope stabilityGeotechnical monitoring sheet
Excavation supportInstallation of struts and trench boxesShoring compliance sheet
Formation levelDeformation measurement under loadME plate load test report

Strutting and shoring must resist foreseeable loads and forces, be executed according to good engineering practice, and be dimensioned taking additional loads (vehicles, machinery, spoil heaps) into account.

OTConst

For managing unforeseen site conditions, earthwork delays due to bad weather or volume disputes, the contractual provisions of standard SIA 118 define the mandatory notification formalities to assert the contractor's rights.

⛏️ Chapters in this section 10

Earthworks, excavations and temporary shoring

Plate bearing test on excavation base: ME target values and recording procedure

Secure acceptance of the excavation bottom by achieving the contractual deformation moduli.

Earthworks, excavations and temporary shoring

Talutage d'une fouille : les angles de pente admissibles selon le terrain rencontré

Determine compliant slope angles to prevent cave-ins without excavating surplus volume.

Earthworks, excavations and temporary shoring

Choisir un blindage de fouille : palplanches, caissons ou blindage coulissant

Select trench boxes, sliding-rail systems or sheet piles according to site constraints and earth pressure.

Earthworks, excavations and temporary shoring

Bulking factor: calculating the volume of soil actually to be removed

Adjust your lorry cycles and quantity surveys by mastering bulking factors according to the ground.

Earthworks, excavations and temporary shoring

Excavation dewatering: lowering, discharge and cantonal permit

Master pumping systems and administrative procedures for discharging dewatering effluent.

Earthworks, excavations and temporary shoring

Contaminated soil on a Swiss construction site: material classification and landfill disposal route

Identify signs of contamination on the construction site to direct materials to the compliant disposal facility.

Earthworks, excavations and temporary shoring

Soldier pile wall and soil nailed wall: execution and monitoring

Supervise section drilling, concreted infill and excavation passes for a soil-nailed retaining wall.

Earthworks, excavations and temporary shoring

Trench excavation for pipework: minimum width, pipe bedding and surround

Ensure the proper bedding of pipes and prevent settlement through correct trench opening widths.

Earthworks, excavations and temporary shoring

Backfill compaction: layer thickness and bearing capacity control

Coordinate roller passes and verify the bearing capacity of materials reused as backfill.

Earthworks, excavations and temporary shoring

Excavation setting out: batter boards, transfer of dimensions, and checks before the first bucket

Check alignments and reference levels before deploying the mechanical excavator for bulk excavation.