Key takeaways
- Any penetration through compartmentation requires a firestop system holding an AEAI technical certificate.
- The filling ratio of conduits must leave the space required for the intumescent product to expand.
- Integrating re-enterable modules guarantees the subsequent addition of cables without compromising the initial compartmentation.
- The identification plate installed on site and timestamped photographs constitute the legal proof of execution.
Restoring fire compartmentation: approved systems, expansion, and provisions
As soon as a bundle of data cables crosses a concrete slab or a lightweight partition delineating a fire compartment, the integrity of the fire separation is compromised. Resealing permits no makeshift solutions with ordinary plaster or standard polyurethane foam. The installer must install a complete system tested and approved by an application certificate from the Association of Cantonal Fire Insurers (AEAI). These devices rely on intumescent components that swell under the effect of heat to carbonise and hermetically seal the penetration, thereby blocking hot gases, toxic fumes, and flames for the designated period (typically EI 30, EI 60, or EI 90).
| Sealing technology | Recommended configuration | Advantage for low current | Installation constraint |
|---|---|---|---|
| Intumescent mastic and coating with mineral wool | Large openings, mixed cable trays | Conforms perfectly to the complex geometries of substrates | Long drying time and difficult to rework when adding cables |
| Elastomeric foam bricks and plugs | Rectangular provisions or regular core-drilled holes | Easy cutting with a knife and clean, dust-free fitting | Requires mechanical compression in accordance with the data sheet |
| Preformed penetrating sleeves with caps | Single penetrations or small-diameter copper bundles | Instant mechanical reopening for network expansions | Location and diameter fixed from the structural work stage |
The classic mistake on construction sites is overfilling the conduit or core-drilled hole. For an intumescent product to work during a fire, it imperatively needs free volume to expand. If UTP or shielded cables are crammed together without clearance, heat travels directly through the copper and the plastic insulation melts, creating channels into which toxic gases rush before the firestop can expand. The actual filling ratio of openings must never exceed the maximum value specified by the manufacturer's approval, which is generally between 40% and 60% of the total cross-section of the opening.
Ensuring long-term compliance: installing the plate and compiling the evidence file
Cabling a penetration takes only a few dozen seconds, but the installation must prove its resistance for decades, particularly to cantonal fire inspectors or insurers in the event of a fire. Pursuant to art. 364 CO, the contractor is liable for the proper and faithful performance of their work. Upon completion of the firestop, the installer must secure a tamper-proof and non-removable identification plate directly adjacent to the penetration, on the accessible face of the wall or slab.
- The AEAI approval or technical certificate number of the complete installed system.
- The fire resistance class achieved by the sealed element (for example, EI 60 depending on the occupancy of the room).
- The exact designation of the firestop product used and its installation date.
- The company name of the installation company and the name of the qualified installer who carried out the seal.
- The warning notice stating the obligation to reseal the penetration immediately in the event of any subsequent work.
In commercial or administrative buildings, fire penetrations are almost systematically located above suspended ceilings or in service shafts enclosed by access panels. Once the false ceilings are fitted, visual inspection becomes complex, costly, or even impossible without destructive dismantling. The network electrician must therefore imperatively record proof of their work before the rooms are closed up.
- Cleaning and visual inspection of the sealRemove dust from the opening, check that no through voids appear around the cables, and ensure that the thickness of the intumescent material complies with the minimum value indicated in the technical certificate.
- Mechanical fastening of the mandatory plateFill out the label using an industrial permanent marker, then rivet or screw it onto the concrete or masonry substrate, directly above or to the side of the firestop.
- Wide-angle contextual photographPhotograph the partition as a whole with visible reference points (corridor axis, door number, suspended ceiling grid) to locate the penetration within the building without ambiguity.
- Timestamped close-up photographTake a sharp, close-up photograph showing the perfectly smoothed finish joint, the well-spaced cable arrangement, and the clearly legible identification plate.
- Inclusion in the as-built documentationFile the photographs in the technical handover documentation submitted to site management, alongside the layout drawings and product data sheets.
Penetration layout: filling ratio and managing future reserves
Pulling a Category 6A twisted-pair cable or a KNX bus through a fire compartment takes barely a minute on the construction site. Conversely, sealing the penetration affects the safety of the building throughout its service life. Any penetration through a wall rated EI 30, EI 60, or EI 90 compromises smoke and flame tightness until a firestop system approved by the Association of Cantonal Fire Insurers has restored the integrity of the wall.
The classic mistake of the network installer is to overfill a KRFWG conduit or a core-drilled hole in masonry with U/FTP or S/FTP IT cables. If cables occupy all available volume, the intumescent material no longer has the space required to expand under heat and crush the combustible plastic sheaths. The free annular space around each conductor and between cables must remain sufficient to accommodate the depth of mastic or elastomeric pillow specified in the approval.
| Firestop system | Maximum filling ratio | Provision for future cables | Method for subsequent rework |
|---|---|---|---|
| Intumescent acrylic or silicone mastic over backer rod | 60% of internal diameter | Difficult without piercing the hardened bead | Targeted core-drilling or complete re-extrusion after addition |
| Intumescent elastomeric bricks or plugs | 40% to 50% of penetration opening | Excellent, integrated via pre-cut modules | Manual removal of a block, cable routing, and reinsertion |
| Metallic penetrating sleeve with intumescent inserts | 100% of the internal calibrated opening | Optimum via flexible foam caps | Punctured with a draw wire without heavy tools |
| Woven firestop pillows | Variable depending on mechanical wedging | Good for temporary vertical openings | Mechanical removal of pillows and re-wedging after pulling |
For technical rooms and floor distribution frames subject to frequent additions of data backbones, choosing cylindrical mechanical sleeves with flexible caps prevents destructive damage. The telecommunications technician preserves a spare capacity of 30% to 40% during initial installation, which enables a patch cord or fibre optic cable to be pulled without compromising the existing firestop assembly.
Installing the seal, standard markings, and as-built records
Installation begins with careful cleaning of the substrate: drilling dust and brick residues impair the adhesion of intumescent resins and foams. In a masonry penetration, inserting a non-combustible rock mineral wool backer (melting point above 1000 °C) provides thermal backing and defines the minimum application depth for the sealing product. Art. 364 CO states that the contractor is liable for the proper and faithful execution of their work; this rule applies to the fire performance of building services installations.
- Cleaning and preparing the penetrationVacuum concrete dust from the interior of the core hole or conduit. Separate the data cables using temporary combs to maintain a minimum clearance of 5 mm between each sheath.
- Installing the backing insulationPack high-density mineral wool into the centre of the wall to leave the required depth on each side according to the manufacturer's approval data sheet.
- Injecting the sealing productExtrude the mastic or insert the two-component firestop foam evenly. Check that there are no air pockets around the sheaths and smooth the edges flush with the surface.
- Riveting the identification plateMechanically fasten the rigid, tamper-proof identification plate immediately adjacent to the penetration, on the side visible from the corridor or technical room.
The identification plate forms the link between the construction site and the building's fire safety officer. Filled out with an indelible marker or engraved, it states the exact designation of the sealing system, the AEAI approval number, the fire resistance rating achieved (EI 30, EI 60, or EI 90), the date of installation, and the name of the installation firm along with the qualified technician's signature.
A company's liability is more reliably discharged when the as-built documentation contains the complete sealing protocol. Under CO, acceptance of the work releases the contractor for discernible defects. By including the dimensioned penetration drawings, the product data sheet, and high-resolution photographs of each resealed penetration in the as-built file, the telecommunications technician prevents any dispute during periodic insurance audits.
Dispute management, firestop remediation, and thirty-year traceability
On the construction site, the temptation to rush a penetration through a fire-rated wall remains high: running a bundle of U/FTP network cables takes only a few seconds, but concealing a breach behind a false ceiling engages the installer's liability for several decades. Finding standard yellow polyurethane foam, a mineral wool plug without intumescent mastic, or an overfilled conduit leads to outright rejection of the work by the fire quality assurance manager or the fire protection authority.
- Stripping and securing the areaHalt all additional cable pulling in the disputed area. Remove non-compliant firestops without damaging the outer sheath of the telecommunications cables. Clean the reveals of the opening and vacuum dust from the surfaces.
- Reorganising the bundle and sparesSeparate the conductors to maintain the spacing required by the system manufacturer. If the maximum allowable filling ratio is exceeded, install a dedicated re-enterable modular sleeve for future extensions.
- Applying the certified systemInstall the intumescent foam blocks, elastomeric bricks, or certified mastic, observing the thickness and installation depth specified in the AEAI-approved data sheet.
- Marking and evidentiary archivingRivet or adhere the durable identification plate beside the penetration. Take sharp photographs of the firestop, the legible label, and the overall surroundings prior to the final closing of technical service shafts.
Under CO, acceptance of the work releases the contractor, except for defects that could not be detected during normal inspection or that the contractor intentionally concealed. A concealed firestop seal without a label or photographic records falls squarely into this second category in the event of an incident.
Frequently asked questions
What should be done if an existing penetration was never resealed by the preceding trade?
The telecommunications technician must never pull data cables through an unsealed opening without reporting the defect. They must record the condition of the penetration in writing to site management and refuse to add connections until the compartmentation principle is resolved. If they perform the complete sealing themselves, it must be covered by a technical addendum including the supply of the certified system and its identification plate.
Why is standard commercial expanding polyurethane foam prohibited?
Standard expanding foam is a combustible plastic derivative that ignites quickly and releases lethal toxic gases. Only intumescent firestop systems tested in accordance with AEAI fire protection regulations are permitted. These specialised products expand under heat to form an insulating carbonised crust capable of blocking flames, smoke, and hot gases for the required duration (for example EI 60 or EI 90).
How can provision be made for future copper links without breaking the firestop seal?
Inserting a re-enterable sleeve made of preformed intumescent foam or mechanical firestop cartridges is the compliant solution. This arrangement allows an additional cable to be pulled during subsequent IT network changes without destroying the fire barrier. Once the cable has been pulled, the sleeve is resealed by simply twisting it or replacing the approved plug, maintaining the integrity of the wall without applying new mastic.
What mandatory information must appear on the penetration identification plate?
The rigid label fixed near the penetration indicates the name of the product used, the fire resistance rating achieved (EI 30 to EI 120), the AEAI approval or certificate number, the name of the approved installation company, the precise installation date, and the signature of the responsible installer. This data enables fire safety officers to audit the installation throughout the lifetime of the building.
Texts and standards cited
- COacceptance of the work: the contractor is released from liability, except for defects that could not be detected during normal inspection or that were intentionally concealed