Steel: grades, sections, and execution classes: the execution standard
Designed for site managers, site foremen, and workshop managers in steel construction (CFC 215), this section details the essential technical rules for accepting, inspecting, and processing structural steel in Switzerland. From mechanical grades to the traceability of material certificates, rigorously apply SIA 263 and SN EN 1090 standards to ensure the safety of your frameworks and primary structures before any assembly or erection on the construction site.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 5
235 N/mm²
Minimum nominal yield strength of standard structural steel S235 for thicknesses up to 16 mm
355 N/mm²
Minimum nominal yield strength of high-strength steel S355 for thicknesses up to 16 mm
27 J
Minimum impact energy absorbed (Charpy-V notch) required for JR quality at 20 °C
2 mm
Standard nominal clearance for normal bolt holes of diameter M16 to M24
L / 1000
Usual straightness tolerance of a rolled section in standard functional class
Technical scope and professional demarcations
The acceptance of steel products and the verification of execution classes constitute the first critical link in a structural steelwork project. In French-speaking Switzerland, the contractor is directly responsible for the conformity of sections and plates incorporated into the works with the specifications of the contractual documents, under art. 365 CO. Practice requires systematically verifying the grade, metallurgical condition, and dimensional tolerances as soon as bundles arrive at the workshop or packages arrive at the storage area of the construction site.
| Work item | Typical grade or section | Core standard | Competent CFC |
|---|---|---|---|
| Main beams, columns, plate girders | S235JR to S355K2, MSH hollow sections | SIA 263, SN EN 1090 | CFC 215 |
| Load-bearing facade framing | Structural open or hollow sections | SIA 263, SN EN 1090 | CFC 215 |
| Guardrails, handrails, wicket gates | Flat bars, thin tubes, light metalwork | SIA 263 standard (rules of the art) | CFC 274 |
| Aluminium or glazed curtain wall | Lightweight extruded sections | Building envelope industry guidelines | CFC 221 |
| Reinforcing bars for raft foundations or slabs | B500B, welded wire mesh | SIA 262 standard | CFC 211.1 |
Compliance with metallurgical requirements also protects the safety of workers during subsequent operations. Neglecting these aspects may lead to liability under art. 229 CP in the event of structural failure resulting from failure to comply with the rules of the art.
Learning path and reading logic of the ten chapters
The methodological progression of this section faithfully follows the physical flow of the material, from the steel mill order to hand-over for lifting. Each chapter provides measurable benchmarks for inspecting components and making decisions on the marking-out table or unloading dock.
- Step 1: Define the grade and execution class (C1-01 to C1-03)Understand yield strengths and impact values between S235 and S355 to prevent any arbitrary substitution. Gauge the constraints imposed on the workshop by EXC2 or EXC3 classes, then verify traceability stamps against 3.1 inspection certificates in accordance with the SN EN 1090 standard.
- Step 2: Select products and master specific alloys (C1-04 and C1-05)Distinguish the economic scope of standard rolled sections from that of welded plate girders. Specify austenitic or duplex stainless steel grades to prevent crevice and stress corrosion cracking in aggressive atmospheres.
- Step 3: Check geometry and machining (C1-06 to C1-08)Check camber, sweep, twisting, and straightness of raw bars. Assess thermal roughness and the hardness of cut edges resulting from flame cutting, plasma, or laser cutting. Master drilling and punching holes according to bolt diameter and normative clearances.
- Step 4: Store and implement execution drawings (C1-09 and C1-10)Ensure off-ground blocking and sloping of sections in the steel storage yard to eliminate water retention. Manage approval workflows between the workshop drawing approved for fabrication and the erection drawing intended for steel erectors.
📘 Chapters in this section 10
Steel grade: what separates S235 from S355 and why substitution is prohibited
Distinguish the mechanical limits of S235 and S355 to eliminate any risk of failure under load.
Steel: grades, sections and execution classesExecution class EXC2 or EXC3: requirements for workshop and testing
Identify welding and non-destructive testing requirements imposed by upgrading to EXC3.
Steel: grades, sections and execution classesMarking and traceability: linking a section to its test report
Instantly link beam markings to their 3.1 material certificate upon unloading.
Steel: grades, sections and execution classesRolled or plate girder: when standard sections are no longer enough
Optimise framework weight by choosing between standard rolled sections and welded plate girders.
Steel: grades, sections and execution classesStructural stainless steel: which grade for which environment
Select the appropriate stainless steel grade to guarantee structural durability against salt spray.
Steel: grades, sections and execution classesManufacturing Tolerances: Straightness, Length and Straightening
Measure deflection and twist tolerances to straighten components effectively without damaging the material.
Steel: grades, sections and execution classesSteel cutting: oxy-fuel, plasma or laser, and resulting edge quality
Check edge taper and hardness after thermal cutting prior to any welded assembly.
Steel: grades, sections and execution classesBolt holes: drilling or punching, diameter and allowable clearance
Verify allowable hole clearances to ensure proper transmission of connection loads.
Steel: grades, sections and execution classesStoring steel on the construction site: bearers, drainage slope and surface corrosion
Organise site blocking and drainage to prevent premature oxidation of unfinished sections.
Steel: grades, sections and execution classesWorkshop drawing and erection drawing: two documents, two uses, two approvals
Distinguish sign-offs on workshop drawings and erection drawings to prevent bottlenecks.