Key takeaways
- The water test must be carried out strictly before starting any tile adhesive application work.
- The minimum water loading duration makes it possible to verify the behaviour of critical joints.
- Inspection of the lower level confirms the absence of seepage through the raw concrete slab.
- The signed report with timestamped photos protects the company against subsequent disputes on the construction site.
Water filling protocol and test duration on a bonded waterproofing system
Waterproofing under tiles allows for no shortcomings: once the adhesive and tiles are laid, any leak detection requires complete demolition of the finish. On Swiss construction sites subject to trade rules and the SIA 248 standard, the water filling test is the mandatory technical hold point to validate the continuity of the membrane or liquid-applied system (LAS). This verification takes place when the cross-linking time specified by the manufacturer is fully reached, on a structure cleaned of all plaster residues, grains of sand or construction dust.
- Water filling test under tiles
- Watertightness test consisting in temporarily sealing the drainage outlets of a wet area to maintain a static layer of water, in order to check for the absence of infiltration at upstand junctions, corners and drainage flanges before tile installation.
- Mechanical sealing of the drainage outletRemove the grate from the floor drain or shower channel connected by the sanitary installations. Insert an inflatable shut-off bladder or a mechanical plug with an O-ring directly downstream of the waterproofing sleeve, without placing mechanical stress on the perimeter adhesive bead.
- Installation of temporary damsIf the shower area does not have a masonry step, install a temporary watertight dam at the threshold using a rigid profile sealed with polymer mastic, in order to confine the volume without spilling over onto the adjacent dry screed.
- Progressive fillingFill with clean cold water up to a minimum height of 20 millimetres at the highest point of the test area, remaining 10 millimetres below the upper edge of the wall waterproofing upstands.
- Marking the initial levelFix a graduated measuring rod or draw an indelible level line on a sacrificial reference piece. Note the ambient temperature and the exact start time of the test.
The water retention duration must cover a complete cycle of at least 24 hours, increased to 48 hours when the water area is located above sensitive rooms or already occupied dwellings. During this period, a minimal drop in level may be caused by natural room evaporation. In case of doubt about an abnormal water loss, the tiler installs a reference container filled to the same level next to the test basin: if the drop in the shower exceeds that of the reference container, an invisible leak is proven.
Visual inspection of the lower level, photographic traceability and report
Observing no drop in water on the surface is not enough to guarantee the conformity of the work. Water can migrate along technical service ducts, accumulate under acoustic insulation or slip under the screed without immediately appearing on the surface. The tiler or their site foreman must imperatively organise access to the rooms located directly below the tested area: lower apartment, technical basement or underground car park.
| Inspected element | Observation area | Defect indicator | Required action |
|---|---|---|---|
| Slab penetration | Lower ceiling / core drilling | Droplets, dark watermark, efflorescence | Stop test, drying, sleeve repair |
| Drain surround | Underside of concrete floor | Moisture to the touch, seepage | Replacement of watertight clamping flange |
| Perimeter upstands | Skirting boards adjacent partitions | Capillary rise on plasterboard | Reworking of corner reinforcement tapes |
| Waterproofing surface | Upper test basin | Delamination, bubbling of the mat | Local cutting, gluing of a patch |
The inspection under the floor must be carried out at three points in time: two hours after loading, in the middle of the test, and immediately before the final draining. For occupied condominium or rental premises, this access requires prior coordination with site management and the property management, recorded in the site logbook. A powerful spotlight and a contact hygrometer with pins or induction make it possible to detect moisture variations on the raw concrete before visible droplets appear.
- General photograph of the room showing the sealing system in place and the water level at hour zero.
- Macroscopic shot of the graduated measuring rod or timestamped level mark using a calibrated digital camera.
- Photographs under the lower ceiling showing the raw concrete slab perfectly dry at the duct penetrations.
- Final shot before water evacuation certifying the maintenance of the level without external top-up.
After complete evacuation of the water, the horizontal surfaces must be sponged and ventilated to regain a surface moisture content compatible with the application of the chosen tile adhesive. Tiling can then begin on a substrate whose watertightness is irrefutably demonstrated and archived in the work file.
Water loading according to SIA 248 standard: sealing, threshold and observation duration
The water filling test of a waterproofing system under tiles constitutes the decisive technical hold point on a tiling construction site. Once the first porcelain stoneware tile is glued, the bonded waterproofing system becomes inaccessible without total demolition of the work. In accordance with trade rules and the requirements of the SIA 248 standard, this static test is carried out on the thoroughly dry waterproofing assembly, after complete hardening of the resins or waterproofing tapes and before any spreading of tile adhesive.
Practical execution requires the watertight damming of access thresholds and the mechanical sealing of drainage bodies. Floor drains or shower channels are blocked using pneumatic inflatable shut-off devices or screwed expandable flange plugs, positioned downstream of the connection collar to subject the membrane-sleeve joint to water pressure. A temporary mortar bead or a stop profile sealed with elastomer mastic blocks the threshold of the area without damaging the perimeter upstands.
| Tested area | Minimum water height | Retention duration | Critical points under load |
|---|---|---|---|
| Walk-in shower at floor level | 20 mm at the highest point of the slope formation | 48 hours | Drainage collar, floor-wall corners, threshold connection |
| Complete bathroom with masonry shower tray | 30 mm above the finished level of the drain | 48 hours | Recessed pipe penetrations, door frame bases, corner tape |
| Technical room or utility room without lowered threshold | Level set to 10 mm below the edge of the provisional dam | 24 to 48 hours | Perimeter skirting boards, riser sleeves |
During the 48 hours of testing, the drop in the water level must be interpreted rigorously. In a building undergoing thermal drying or under forced ventilation, natural evaporation reduces the level by a few millimetres without there being a leak. To isolate this phenomenon, the tiler immerses a flat-bottomed reference container filled with water to the same level as the room: if the water loss of the basin exceeds the drop measured in the reference container, infiltration through the waterproofing system is proven.
Findings at the lower level, safe draining and probative file
- Joint inspection of the lower floorThe team leader meticulously inspects the underside of the reinforced concrete slab at the neighbour's or in the underlying technical room. The examination targets the immediate periphery of core drillings, suspended pipe hangers and structural concrete cracks, assisted by glancing light and a dielectric moisture tester.
- Timestamped photographic recordingTaking high-resolution shots showing the immersed metal rule at a fixed time (initial filling, 24-hour step, 48-hour term) and overall photographs of the dry lower ceiling, incorporating an immutable visual reference of the construction site.
- Drafting and signing of the reportDrawing up the official document recording dates, times, water head height and the non-leak finding, counter-signed by the tiler and site management to validate the stage hold point.
- Decompression and controlled drainingGradual removal of the pipe plug by slow deflation or partial unscrewing to prevent any backflow under pressure or water hammer in the building's downpipe.
After water evacuation, the waterproofed substrate must dry completely before applying the tile adhesive. The presence of a residual water film on the surface would disrupt the hydration of the tile adhesive polymers and compromise the mechanical adhesion of the tiles. Fine dust or residues brought by the test water are removed with a damp sponge, and the surface is then protected from traffic by other trades using non-perforating rigid panels until ceramic installation actually starts.
Management of defects: technical remedial work after a leak and re-test
The discovery of a moisture trace on the lower ceiling or an abnormal drop in the water level immediately brings the test to an end. In this critical situation, the tiler carries out controlled draining of the basin without rushing the evacuation, then dries the surface completely. No adhesive or tiles may be applied until the origin of the damage is formally identified and treated. The waterproofing defect is mostly located at the junction between the waterproofing sleeve and the floor drain body, or along a corner joint where the elastomer tape has suffered a fold or a lack of smoothing.
Once the repair has been carried out in accordance with the manufacturer's technical datasheets and trade rules, the complete drying and cross-linking time must be scrupulously respected before any new hydraulic stress. The classic mistake is to rush the refilling to catch up with site delays. An uncured liquid-applied waterproofing system degrades instantly upon prolonged contact with stagnant water.
The complete test protocol is then repeated in its entirety: watertight sealing of the drain, filling to the specified level, water retention duration identical to the first phase, and a new joint inspection of the underside with site management and the owner of the lower floor. Acceptance of the substrate for tile installation can only be pronounced after validation of a new written report, supplemented by a timestamped photographic file certifying the total absence of seepage.
Frequently asked questions
How to differentiate a real leak from natural evaporation during water retention?
Evaporation lowers the water level by one to three millimetres per day depending on the room's humidity and ventilation. To clear up any doubt without compromising the test, place an evaporation reference container on site: a cylindrical vessel filled with water to the same level as the basin. If the drop in the basin exceeds that observed in the reference container, infiltration is proven, requiring an immediate check of the lower ceiling.
What should be done if the neighbour downstairs refuses access to check their ceiling?
The tiler cannot forcefully enter a third party's property. In case of refusal of access, immediately report the obstacle to site management in writing. The contractor formally records the situation on the test report, takes timestamped photos of the stable water level over twenty-four hours, and asks management to coordinate access or assume responsibility in writing for validating the test under their own liability.
Can water filling be carried out directly after gluing the corner tapes?
No. Hydraulic loading before complete drying emulsifies the waterproofing systems under tiles and destroys the mechanical bond of the elastomer tape. Depending on the temperature and site ventilation, a minimum waiting period of twenty-four to forty-eight hours after the last bridging coat is required. Systematically consult the manufacturer's technical datasheet instructions to validate the curing time.
What type of plug should be used to block the drain during the test?
Never use rags, adhesive tape or plastic bags, as these makeshift fixes give way under pressure or leak insidiously. The tiler must use a mechanical expandable rubber screw plug adapted to the exact diameter of the drain pipe, or an inflatable pneumatic shut-off bladder equipped with a pressure gauge. Only this equipment guarantees the perfect watertightness of the drain throughout the observation period.
Texts and standards cited
- SIA 248Waterproof finishes under bonded tiles, installation requirements and watertightness tests