Key takeaways
- The minimum fall of two percent guarantees smooth water drainage towards the gully trap.
- The screed layer pulls the bulk of the fall, the tiler compensates for millimetric surface defects.
- A fall profile without counter-fall prevents water retention responsible for joint degradation.
- The watering test before tiling definitively validates the conformity of the drainage profile.
Demarcation of responsibilities and fall values according to the SIA 248 standard
The step-free zero-threshold shower is a particularly sensitive area regarding water infiltration and usage defects. In Swiss construction, the transition between the heated bathroom floor and the shower tray area requires perfect geometry. When the fall profile is absent or insufficient, water stagnates in the centre of the shower area, forms a slippery limescale film and saturates the mineral joints. The SIA 248 standard governs tiling work and specifies the permissible tolerances as well as the required geometry for surfaces intended to drain runoff water.
Responsibility for the fall profile depends on the bill of quantities and the received rough substrate. As a general rule, the screed layer belonging to CFC 281 constructs the rough fall profile during the pouring of the screed mortar, adapting to the upper rim of the gully body sealed by the sanitary installer. The tiler accepts this work before applying the bonded waterproofing system. If the screed has been pulled flat or if its fall is less than 1.5%, the tiler must not mask the problem with an excessive thickness of tile adhesive: they report the defect and agree on substrate remediation or execute a specific fall levelling layer.
| Drainage configuration | Minimum required fall | Recommended fall | Planeness tolerance under the 2 m straightedge |
|---|---|---|---|
| Central point drain (4 cut-out planes) | 1.5% (15 mm/m) | 2.0% (20 mm/m) | Less than 2 mm |
| Linear shower channel against wall | 1.5% (15 mm/m) | 2.0% (20 mm/m) | Less than 2 mm |
| Recessed wall channel | 1.5% (15 mm/m) | 1.8% to 2.0% | Less than 1.5 mm |
| Adjacent clearance area | 0.5% to 1.0% | 1.0% (10 mm/m) | Less than 3 mm |
The planeness tolerance under the two-metre straightedge must not exceed two millimetres within the shower volume. A localized hollow of one and a half millimetres under the straightedge, combined with an insufficient fall of 1.0%, is enough to create a permanent puddle of several decilitres. The tiling follows the shape of the substrate; its role is not to straighten a defective screed.
Construction of the drainage profile and water testing protocol
When the tiler takes charge of creating or correcting the fall, they use fast-setting, shrinkage-compensated levelling mortars specially formulated for wet rooms. The method varies according to the drainage kinematics chosen during technical coordination with the sanitary installer: a single slope inclined towards a wall-mounted linear channel or a diamond point with four ridges converging towards a central square or circular drain.
- Mechanical cleaning and bonding primerRemove any residual cement laitance from the screed by diamond sanding, vacuum thoroughly with an industrial vacuum cleaner and apply a bonding primer adapted to the porosity of the mineral substrate.
- Setting out benchmarks and fall gaugesFix the guide pins or metal screeding rails maintaining a continuous fall of 2.0% from the outer edge of the shower to the edge of the gully connection flange.
- Pulling the shaping mortarMix the thixotropic rendering mortar according to the manufacturer's recommendations. Pull the mortar with the bevelled straightedge, pressing the paste firmly to ensure intimate contact without air pockets.
- Fine smoothing and levellingFloat and then smooth the surface with a small plasterer's trowel to obtain a smooth, regular surface state free from ripples likely to retain water under the tiling.
Before starting the installation of the bonded composite waterproofing under tiling and tile fixing, a water drainage check is mandatory on the prepared substrate. This preventive check consists of continuously pouring about ten litres of clean water using a watering can from the peripheral high points of the shower. The team leader observes the trajectory of the flow: the water must converge spontaneously and rapidly towards the grating without deviating towards the side walls or the threshold of the wet room. After five minutes of natural draining, no stagnation greater than the thickness of a sheet of paper must persist. In the event of water retention, the tiler rectifies the surface by localized sanding or application of fine mortar before applying the waterproofing membrane.
Residual puddle in the walk-in shower: water physics and installation tolerances
On a tiled walk-in shower, the presence of a film of water or small retentions after use regularly gives rise to complaints from the client. However, the complete and instantaneous evacuation of every droplet remains impossible on a tiled floor. The surface tension of the liquid, the roughness of the glaze or porcelain stoneware, as well as the joint grid create natural hydraulic resistance. According to professional rules and the SIA 248 standard, a residual puddle of millimetric thickness that evaporates within a reasonable time does not constitute an execution defect, provided that the general fall effectively directs the main sheet of water towards the drainage point.
| Ceramic cladding | Drainage profile | Main origin of retentions | Recommended technical layout |
|---|---|---|---|
| Mosaic and small formats (less than 10 x 10 cm) | Four falls in a diamond point towards a point drain | Water braking by the relief of the numerous mortar joints | Joint filling flush with the tile, without depressions or excess thickness |
| Medium format (15 x 15 cm to 30 x 60 cm) | Two or four cut-out planes depending on setting-out | Local height differences forming transverse barriers | Installation with a calibrated notched trowel with buttering-floating to crush the ridges |
| Large panels (from 60 x 120 cm) | Unidirectional fall towards wall-mounted linear channel | Tile's own camber and rigidity preventing curvature | Full-width channel and rectilinear laying plan without breaks |
Correction of the fall profile by the tiler: mortars and watertight connection
When the screed layer delivers a shower area with insufficient, flat or uneven fall with hollows, the tiler must not lay their cladding in the hope of compensating for the gradient with the adhesive bed. The permissible thickness of a standard tile adhesive does not allow for creating a fall profile without risking differential settlement, incomplete drying under the tiling and delamination under service load. If the correction remains of small thickness, the tiler intervenes using a thixotropic levelling mortar or a rapid rendering screed compatible with the waterproofing under tiling that will cover the whole assembly.
- Profile diagnosis and mechanical strippingCheck the existing fall using a two-metre straightedge and an electronic level. Sand or mill the area to remove all cement laitance and open the pores of the underlying screed. Vacuum dust thoroughly.
- Application of the bonding bridgeApply a specific bonding primer or spread a fresh cement slurry enhanced with a bonding resin, to ensure a monolithic bond between the load-bearing screed and the fall overlay.
- Pulling the thixotropic fall mortarApply a shrinkage-compensated, fast-setting reprofiling mortar. Pull the material with the bevelled straightedge respecting the minimum target fall value towards the drainage body, feathering to zero at the periphery of the gully or channel.
- Clean water drainage testAfter complete hardening of the shaping mortar, pour a bucket of water at the high point of the shower before applying the liquid applied waterproofing system or the bonded membrane. Observe the trajectory of the fluid: no water must stagnate outside the drainage area of the gully.
Once the fall profile has been corrected and verified by a dynamic drainage test, the installation of the waterproofing under tiling can begin. The tiler then rigorously transfers this geometric profile when laying the ceramics, ensuring that the tile adhesive bed has a constant thickness of no more than three to five millimetres so as not to deform the achieved fall.
Procedure in case of non-compliant fall and responsibility management
When the preliminary straightedge check or water test reveals a counter-fall, a retention zone or a general fall below the tolerances of the SIA 248 standard, installation must never begin. Laying tiles on a defective shape effectively transfers liability for the damage to the tiler. As soon as a geometric defect is observed on the rough screed, the tiler must send their notice of defects in writing to the site management and the client, in accordance with the rules of the Code of Obligations and the SIA 118 standard. This report must precisely describe the deviations noted, supported by photos and level measurements, quantifying the depression or counter-fall value measured under the two-metre straightedge. A report refusing intervention freezes the technical situation and protects the company against subsequent claims related to water stagnations.
Two treatment paths then open up depending on the magnitude of the deviation observed and the remaining clearance level at the threshold. If the height available below the finished level of the adjacent room permits, the tiler can propose rectifying the planeness using a specific fast-setting fall levelling compound, subject to a written order and financial coverage of the modification works. This intervention requires mechanical sanding of the surface laitance and the application of a suitable primer. On the other hand, if the counter-fall is structural or if the clearance is insufficient to guarantee the drop without creating an obstruction at the threshold, the rectification is the responsibility of the screed layer. The latter must demolish the non-compliant area and redo the fall profile according to the rules of their trade. The tiler resumes their waterproofing membrane installation work only after complete drying of the rectified substrate and a new joint inspection validated by the site manager.
Frequently asked questions
Who is responsible if a puddle remains in the shower after the tiling is laid?
If the tiler laid their tiles on a screed already presenting a counter-fall without issuing a written notice of defects according to the SIA 118 standard, their liability is engaged for accepting a non-compliant substrate. If the screed respected the fall shape but the tiler created a hollow during the execution of the tiling or joints, complete remediation falls exclusively on them at their own expense.
What is the minimum fall to demand upon handover of the rough fall profile?
According to professional technical rules and the SIA 248 standard, a minimum fall of 1.5 to 2% is required towards the drain. Below 1.5%, the risk of water retention by surface tension on the tiling increases sharply. The tiler must refuse any rough substrate displaying less than 1.5% gradient, as normal tiling execution tolerances do not allow guaranteeing drainage without a persistent puddle.
Can a local basin on the screed be corrected before applying the waterproofing under tiling?
Yes, for localized defects not exceeding a few millimetres, the tiler can apply a fast-setting, thixotropic mineral reprofiling mortar compatible with the planned composite waterproofing system. The substrate must be vacuumed, freed from all dust and treated with an appropriate bonding primer. This correction does not exempt from re-verifying the final fall with the straightedge and level before laying the waterproofing membrane.
How to jointly prove the absence of fall before tiling?
The tiler performs a clean water drainage test in the presence of the site management or the site manager. They pour a calibrated volume of water over the entire shower area and observe the drainage towards the gully or channel. Residual puddles stagnating after ten minutes are marked with a construction crayon, measured in depth and recorded in a joint report signed on the spot by the parties.