🧱 CFC 282Substrate acceptance and preparationChapter 1 of 10 in the section

The document first: required moisture reading read and understood, and refusal to install without it

This chapter details the procedure for checking the substrate documentation before starting work. You will learn how to analyse the calcium carbide moisture measurement report according to the type of binder, identify the critical thresholds defined by professional standards, and write the notice of refusal to carry out work when the document is missing or shows a non-compliant value.

Key takeaways

  • The tiler does not measure moisture but demands the official report drawn up by the screed layer.
  • Maximum residual moisture thresholds differ strictly between cement binder and calcium sulphate screed.
  • Installing without a written document transfers full liability for future defects onto the tiling company.
  • In the absence of a compliant reading, immediately notify your refusal to carry out work in writing to the site management.

The CM measurement report: permissible thresholds and critical reading according to the binder

On a Swiss construction site, the tiler does not perform the destructive moisture measurement of the screed. This operation is the exclusive responsibility of the screed layer, in accordance with the technical requirements of standard SIA 251. On the other hand, the tiler has a duty to demand this document, check its authenticity, and interpret its values before rolling out a single waterproofing membrane or spreading the adhesive. Laying tiles or natural stone without holding the official reading is equivalent to tacitly approving the substrate and assuming liability for incomplete drying.

Maximum permissible residual moisture thresholds for tile installation according to standard SIA 251 and standard SIA 248
Screed binder typeWithout underfloor heating (CM measurement)With underfloor heating (CM measurement)
Cement-based screed (CT)2.3% to 2.5% CM1.5% CM
Calcium sulphate / anhydrite screed (CA)0.5% CM0.3% CM

Reading the control sheet requires methodical rigour. A cement-based screed tolerates higher residual moisture than a calcium sulphate screed. The latter, which is particularly sensitive to water, suffers a loss of mechanical strength and irreversible structural softening if it remains confined under watertight tiling with excess water. On fluid anhydrite screed with underfloor heating, the limit value drops to 0.3% CM: the slightest exceedance leads to the sheer detachment of the tiles due to the formation of secondary ettringite at the cement adhesive interface.

Before engaging your team members, also check the date of the reading. A report dating back more than seven to ten days, or carried out before a period of bad weather on an unheated or unventilated building, becomes void. If the building has suffered water infiltration or very high indoor humidity phases, the screed may have reabsorbed ambient water vapour, distorting the initial results.

Absence of reading or value out of tolerance: notify the written refusal to carry out work

The pressure exerted by the progress schedule frequently pushes site management to demand the start of installation when documents from the previous trade are missing. Yielding to this request places your company in a perilous contractual situation. The Code of Obligations and the professional rules of standard SIA 118 require the tradesperson to notify the client of any defect likely to compromise the proper execution of the work. The lack of material proof of dryness constitutes a major defect of the substrate.

  1. Note the documentary deficiencyVerify during the preliminary site inspection that the CM report signed by the screed layer and the heating engineer's heat-up protocol are not in the site file.
  2. Draft the notice of interruptionSend a formal writing (registered mail or email with acknowledgement of receipt) to the site management and the client, citing the absence of a CM reading compliant with standard SIA 251.
  3. Define the suspension of servicesExplicitly declare the postponement of the start of tile installation (CFC 282) until delivery of the document certifying dryness below the limit values of standard SIA 248.
  4. Formally reserve deadlinesIndicate in the notification that schedule slippage or personnel downtime costs cannot be attributed to the tiling company.

The drafting of the notification must remain strictly factual and neutral. For example, formulate: "During our inspection upon resuming work on the substrate today, the calcium carbide moisture measurement protocol required by standard SIA 251 was not transmitted to us by site management. In the absence of written justification certifying that the residual water content complies with the tolerances of standard SIA 248, tile installation and waterproofing work under tiles cannot start without the risk of subsequent damage. Our work is suspended until receipt of a compliant moisture reading."

The technical interface file: documents to demand before any intervention

On a construction site in Switzerland, the boundary of liability between the screed layer and the tiler is materialized by the delivery of compliant technical documents. Laying tiles or natural stone on a screed without holding the official calcium carbide (CM) moisture reading amounts to assuming all risks related to the drying of the substrate. By starting gluing or applying waterproofing under tiles without this report, the tiler tacitly approves the received substrate. Any subsequent cracking, shearing, or detachment caused by trapped residual water will then be attributed to them as a failure of preliminary verification.

Essential documents for substrate acceptance according to standards SIA 251 and SIA 248
Required documentIssuing tradeRequired technical contentRole for the tiler
CM moisture measurement reportScreed layer (CFC 281)Moisture content in %, exclusive CM method, date, depth, and location of samplingValidate substrate suitability according to the moisture threshold specific to the binder
Temperature-adjustment protocolHeating engineer (CFC 241)Dates of heat-up phase, maximum temperature plateau, and gradual coolingEnsure thermal purging and water evacuation of the heating system
Location plan of control pointsSite management / Screed layerPrecise positioning of sampling areas without integrated heating pipesVerify sample reliability without risk of damaging pipes

Standard SIA 251 governs requirements applicable to screeds, and standard SIA 248 governs the execution of tilework. Permissible thresholds depend on the nature of the binder used. For a cement screed, adhered installation requires residual moisture less than or equal to 2.0% CM without underfloor heating, and 1.5% CM on heated floors. On calcium sulphate screed, tolerances are much stricter: the threshold must not exceed 0.5% CM without heating, and drops to 0.3% CM in the presence of underfloor heating for ceramic tiles with low permeability. Capacitive or electronic surface measurements have no acceptance value: only the CM method is authentic. The tiler does not perform this destructive core drilling themselves: they demand the document, analyse it, and refuse to intervene if normative criteria are not met.

Documentary deficiency: formal notice and formalisation of refusal

Faced with the paces imposed by the work schedule, site management may attempt to initiate installation before the CM reading is provided or despite a rate out of tolerance. The tiler is bound by their duty to notify to immediately report any obstacle compromising the durability of the structure. Installing without a written document exposes the tradesperson to costly remediation work without any recourse against the screed layer. If the reading is not provided during the site meeting, the foreman must formalise the blockage with a notification of refusal to install and suspend their team.

  1. Immediate observation and written request for documentsFrom theoretical access to the premises, record in the site logbook and notify by email the absence of the CM reading and the temperature-adjustment certificate.
  2. Notification of refusal to carry out workIf the documents are not produced, send without delay a formal notice of defects indicating that the screed is not accepted and that installation work is blocked.
  3. Formal suspension of the contractual scheduleNotify the client in writing that tile execution deadlines are suspended as long as the substrate is not qualified by a compliant moisture report.
  4. Resumption exclusively after production of a compliant readingOnly authorise the start of gluing after delivery of a CM report signed by the screed layer and site management, certifying values below normative limits.

A verbal order to install never protects the contractor. If the client nevertheless demands the progress of work, the risk only shifts via an express written waiver, by which they declare to assume full responsibility for degradation related to residual moisture. However, on a damp calcium sulphate screed, the application of watertight porcelain stoneware causes irreversible degradation of the interface due to secondary ettringite formation. Even with a waiver, the advised tiler maintains their refusal to intervene, as Swiss courts often consider that a professional cannot execute work destined for technical failure.

Management of schedule pressures and formalisation of refusal to carry out work

On site, the tiler frequently faces the injunction to start installation to keep the general schedule, even though the calcium carbide (CM) measurement protocol has not been produced. Laying a single tile without having this official reading legally amounts to endorsing substrate compliance and assuming the entire risk of detachment or cracking due to differential shrinkage. Visual assessments, plastic sheet tests, or capacitive electronic devices do not constitute admissible evidence under standard SIA 251.

  • Immediate observation: notify site management in writing and record in the site logbook the failure to deliver the CM measurement report.
  • Reminder of admissibility criteria: recall the limit values imposed by standard SIA 251 according to the binder, i.e., a maximum of 2.3% CM for a cement screed (1.5% on heated floors) and 0.5% CM for a calcium sulphate screed (0.3% on heated floors).
  • Maintenance of work stoppage: declare the technical impossibility to install, suspend the delivery of tiles, and formally warn of the postponement of contractual deadlines according to the rules of standard SIA 118 without penalties attributable to the installer.

Work can only resume upon receipt of the cross-check analysis document signed by the screed layer, attesting to sampling carried out in the lower third of the thickness. This technical protocol locks the division of responsibilities between the screed trade and the tiling trade.

Frequently asked questions

Site management demands immediate installation and proposes a written waiver: should it be accepted?

No. In Swiss construction law, a waiver does not cancel the liability of the tiler who installs on a manifestly unfit substrate. Good workmanship and standard SIA 248 prohibit installation on a damp substrate. If tiles detach or the sulphate screed degrades, insurance will refuse coverage for deliberate misconduct. The tiler must maintain their formal notice of refusal to intervene until a compliant reading is obtained.

Can a non-destructive electronic capacitive test replace the screed layer's CM reading?

No. The capacitive device only allows qualitative location of the dampest areas to guide sampling. Only the chemical method using the calcium carbide bomb is authentic according to standard SIA 251. The screed layer must sample material across the entire thickness of the substrate, grind it, and record the pressure obtained in an official report. Installing without this document directly engages the tiler's liability.

What are the residual moisture thresholds that authorise tile installation?

According to standard SIA 251, the threshold depends on the binder and the presence of heating. For a cement screed, the maximum permissible is 2.3% CM, reduced to 1.5% CM on underfloor heating. For a calcium sulphate (anhydrite) screed, the requirement is much stricter: 0.5% CM without heating and 0.3% CM with underfloor heating. The tiler refuses to intervene if these values are exceeded.

How to formalise the refusal to intervene without risking delay penalties?

The tiler drafts a notice of unacceptable substrate sent by registered mail or tracked email to site management, with a copy to the client. They expressly cite the absence of the CM report prescribed by standard SIA 251 and standard SIA 248. They indicate that the stoppage of their services stems from an impediment not attributable to their company, which freezes contractual deadlines in accordance with standard SIA 118.

Texts and standards cited

  • SIA 251Sets execution requirements, testing, and maximum residual carbide moisture thresholds for floating and bonded screeds.
  • SIA 248Governs tiled finishes and defines the obligation to inspect and accept the substrate before installation.
  • SIA 118Regulates general conditions relating to the execution of construction work and the management of notices of defects of the substrate.