Earthworks, foundations and compaction: the execution standard

This technical section details Swiss rules for earthworks, subgrade preparation and soil stabilisation for external works professionals. Intended for team leaders, foremen and site managers, it brings together the execution parameters for excavating to the correct levels, constructing an unbound granular layer in accordance with VSS standards and validating bearing capacity prior to laying external surfacings, while guaranteeing safety on the construction site.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

OTConst art. 68

1 m 50

Maximum depth of an unbraced excavation before legal obligation for battering or shoring

norme SIA 318

2,0 %

Minimum crossfall of the subgrade to ensure drainage of infiltration water

VSS standards

30 cm

Current maximum thickness of an unbound granular layer before roller compaction

construction work ordinance

50 cm

Minimum clear width free of any material storage along a shored excavation crest

Scope of the landscape earthworker and trade interfaces

The field of the landscape contractor under CFC 411 exclusively concerns external works carried out on natural or modified ground of a private plot. It encompasses topsoil stripping, excavation of private access roads, preparation of fall slopes for surface rainwater drainage and installation of compacted granular structures. This scope of work stops strictly at the boundaries of structural work and building trade interfaces.

  • Building excavations, general bulk earthworks, heavy trench shoring and perimeter drainage bonded against basement walls: works falling under structural work CFC 201.
  • Reinforced concrete load-bearing structures, calculated foundation rafts and structural slabs: works falling under the mason CFC 211.1, with the landscaper limiting their masonry structures to freestanding or prefabricated low walls.
  • Bituminous or synthetic waterproofing applied to roofs, underground car park slabs and roof terrace upstands: interventions associated with CFC 226.
  • Mineral surfacings bonded with mortar on an external screed: services assigned to the tiler CFC 282, with external laying under CFC 411 always carried out dry on a granular bedding layer or on pedestals.
  • Buried collector networks beneath buildings and connections to the main public pressure sewer: works under the responsibility of the sanitary fitter CFC 250.

The management of landscape earthworks requires absolute execution rigour to prevent subsequent differential settlement under paving or flagging. In accordance with art. 365 CO, the contractor must notify the client without delay of any geotechnical defect observed in the ground or any geological anomaly likely to compromise the final stability of external works. If the subgrade exhibits excessive softness, abnormal moisture content or unforeseen contamination, work must be suspended locally to adapt the foundation structure.

Chronological sequence of operations and chapter logic

The success of external earthworks relies on an orderly sequence of technical steps and preliminary checks. Intervening without a method exposes the company to ruptures of underground pipes, the decline of surrounding vegetation or rapid structural subsidence under traffic. Reading the ten chapters follows step-by-step the actual progress of a landscaping construction site.

  1. 1. Initial reconnaissance and securingBefore engaging the excavator bucket, the team consults utility provider plans, locates live buried services by detection or manual trenching, demarcates the root protection zones of protected trees and assesses the environmental integrity of the ground in order to avoid forced site stoppage due to contaminated soil.
  2. 2. Management of excavated material and excavationMeticulous stripping separates the arable topsoil layer from mineral excavation materials in accordance with soil protection requirements. The main excavation is then set to the millimeter according to the final use of the work, taking frost susceptibility and cross-fall drainage into account.
  3. 3. Interface treatment and subgradeOn soft or clayey soil, the interposition of an anti-contaminant geotextile blocks the migration of fines while ensuring water filtration. For specific areas such as steep garage ramps, reinforced anchorage of the formation level prevents any sliding of the structure.
  4. 4. Replenishment and methodical compactionThe unbound granular foundation is leveled in controlled-thickness lifts adapted to the weight of the roller or vibrating plate. Methodical compaction is carried out by moving gradually from the edges towards the center or the crown.
  5. 5. Geotechnical validation and handoverPrior to implementing the bedding layer for paving or asphalt, the bearing capacity of the platform is certified by a static or dynamic plate bearing test, recorded in a joint inspection report.

Collective safety governs each of these stages. In accordance with art. 68 OTConst, excavation walls and earthworks deeper than 1 m 50 that are not shored or braced must be provided with a batter suited to soil cohesion to eliminate any risk of fatal cave-in.

📘 Chapters in this section 10

Earthworks, foundation and compaction

Excavation depth: depending on usage, pedestrian, vehicular, and in-situ soil

Calculate precisely the required formation level depth according to expected traffic and in-situ soil.

Earthworks, foundation and compaction

Gravel: particle size distribution, layer thickness, and compaction in successive layers

Select the ideal aggregate grading and master layer thickness to prevent rutting.

Earthworks, foundation and compaction

Proving compaction: plate loading test, target value and test report

Interpret the plate modulus of elasticity and provide an impeccable bearing capacity report.

Earthworks, foundation and compaction

Geotextile: separation of a fine-grained soil, fine particle pumping and sheet overlap

Neutralise the pumping of fines using the suitable separation geotextile and take care of overlaps.

Earthworks, foundation and compaction

The garage ramp: concentrated load, gradient, enhanced compaction and subsidence

Prevent the subsidence of pavers on steep slopes through a notched foundation and reinforced compaction.

Earthworks, foundation and compaction

Reuse on site: topsoil sorting, excavation material and storage

Organize sorting and topsoil windrows to reuse excavated materials without financial penalty.

Earthworks, foundation and compaction

Before the excavator: utility plans, detection, manual trial pits and severed pipes

Precisely locate pipes and live cables before the first mechanical bucket strike.

Earthworks, foundation and compaction

Suspicious soil: odour, unknown fill, stop work and analysis before disposal

Adopt the right safety and traceability reflexes as soon as suspicious soil appears.

Earthworks, foundation and compaction

The tree to keep: root zone, manual trenching, and the tree that dies three years later

Excavate around a remarkable tree without damaging its vital root system.

Earthworks, foundation and compaction

Driving on a slab: permissible load, load-distribution plates and written authorisation

Secure the crossing of a basement by your machinery by validating the decking and permissible load.