Wood and room hygrometry: the execution reference standard

This section covers climate and hygrometric checks prior to parquet flooring installation in accordance with SIA 253. It is intended for foremen and site managers who must validate wood stability, check building drying and formalise work suspension if ambient conditions or screed readings fall outside permissible tolerances.

  • 10chapters
  • 22 000words
  • 6sections in the training course
  • 60chapters in total

Key values to remember 4

norme SIA 253

18 to 22 °C

Minimum ambient room temperature during installation and adhesive curing

norme SIA 253

35 to 65 %

Permissible relative air humidity range in living areas

norme SIA 253

9 % ± 2 %

Reference moisture content of wood upon delivery for multi-layer elements

norme SIA 253

27 °C

Maximum permissible surface temperature of finished parquet flooring over a heated screed

Technical scope of application and limits of the flooring contractor's intervention

The success of a parquet flooring project relies on a strict physical balance between the moisture content of the wood, the relative humidity of the ambient air and the residual dryness of the substrate. Under Swiss contracts governed by SIA 253, the flooring contractor assumes direct responsibility for the hygrometric state of the boards they install, their storage on the construction site and the indoor climate prevailing at the time of gluing or mechanical fixing. This section brings together all the rules of the art required to measure, record and arbitrate the feasibility of the installation, from the initial room climate check to the maintenance instructions handed over to the operator.

The flooring contractor's role must not, however, be confused with that of other trades working on the building envelope and interior floors. Screed preparation, the management of its drying process, the execution of the initial heating-up protocol and the measurement of the reference calcium carbide moisture content are the responsibility of the screed layer (CFC 281). The flooring contractor does not carry out this destructive sampling: they request, analyse and archive the official measurement report before any intervention. If this document is missing or indicates a value outside tolerance, the tradesperson suspends their work in application of their obligation to notify the client without delay, in accordance with art. 365 CO.

  • What this section covers: measuring room temperature and relative humidity, checking board moisture content, acclimatisation cycles, critical analysis of screed moisture reports, seasonal dimensional behaviour, adaptation to underfloor heating systems and drafting notices of non-conformity.
  • What this section excludes: screed pouring and their reference CM measurement (CFC 281), the installation of skirting boards or fittings by the joiner (CFC 273), the installation of tiling and waterproofing membranes (CFC 282), the application of floor paints or resins (CFC 272) as well as the adjustment of underfloor heating manifolds (CFC 241).

Logical reading order and operational progression on the construction site

A methodical approach to hygrometry requires strict adherence to the construction site chronology. The first chapter covers room climate (U1-01): it details the target temperature and ambient air relative humidity values required by SIA 253 to start work on the construction site. The second chapter examines internal wood moisture (U1-02), equilibrium values to be respected and the handling of the pin moisture meter. The third chapter deals with the acclimatisation of packaged goods (U1-03), demonstrating why uncontrolled unpacking or keeping items under sealed wrapping leads to immediate damage.

The sequence continues with the verification of structural work prerequisites. The fourth chapter explains how to read the substrate report (U1-04), the strict thresholds applicable to wood compared to ceramics, and the essential written documents required to authorise commencement. The following chapters cover the physics of the material in service: normal seasonal movements and the appearance of winter gaps (U1-05), the management of excessively dry air associated with mechanical ventilation systems (U1-06), as well as the specific constraints of heated floors in terms of wood species and surface temperatures (U1-07).

  1. Evaluate the product and its environmentCompare the dimensional stability of solid wood versus engineered wood (U1-08) in order to select the assembly suited to the thermo-hygrometric stresses of the building.
  2. Organise logistics on the construction siteApply the rules for flat storage, off the ground and protected from residual moisture sources from drying plasters or paints (U1-09).
  3. Formalise work suspension if necessaryDraft a formal notice of defect and assert the interruption of work in the face of untenable schedule demands from project management (U1-10).

📘 Chapters in this section 10

Moisture in timber and in the room

Room climate: temperature range, relative humidity range and measurement before installation

Master ambient thermo-hygrometric ranges to secure installation before any unpacking of wooden elements.

Moisture in timber and in the room

Wood moisture content: delivery rate, equilibrium moisture content and core measurement

Check the exact moisture content of the boards upon receipt to prevent irremediable warping and post-installation deformations.

Moisture in timber and in the room

Acclimatisation: duration, stacked or unpacked boards, and the mistake of leaving them under plastic film

Stabilise packaged goods according to the rules of the art without trapping moisture under sealed wrappings.

Moisture in timber and in the room

Substrate inspection: stricter threshold than for tiling, required document and refusal

Demand the screed layer's CM measurement protocol to formally refuse to work on a damp screed.

Moisture in timber and in the room

Wood breathes: joints that open in winter, close in summer, and why this is normal

Anticipate the seasonal dimensional play of the boards to distinguish normal behaviour from a contractual defect.

Moisture in timber and in the room

Excessively dry air: heating, humidity below the threshold, and instructions left for the client

Prevent critical winter shrinkage by documenting humidification instructions passed on to the client.

Moisture in timber and in the room

On underfloor heating: stable timber species, limited thickness and surface temperature

Select wood species and thicknesses compatible with the thermal reduction imposed on a heated floor.

Moisture in timber and in the room

Solid or engineered wood: stability, potential number of sandings and actual price over twenty years

Technically arbitrate between solid and engineered wood depending on the required stability and lifespan.

Moisture in timber and in the room

Storage: flat, dry, away from cold walls, and not before wet trades are finished

Store packages protected from water and ventilated to prevent any moisture reabsorption before assembly.

Moisture in timber and in the room

Refusing: records, reasoned letter, and what happens if the client insists

Draft an immediate work suspension notice to formally release oneself from liability in the face of the client's injunctions.