Acceptance of the substrate and diagnosis before painting: the execution reference framework
Aimed at team leaders, foremen and site managers in CFC 272, this section details the critical phase of preliminary diagnosis. Before opening a single tin or picking up a roller, the painter must probe cohesion, measure moisture and classify the substrates in accordance with the SIA 257 standard. Applying onto an unsuitable substrate directly engages your liability: here are the methods for inspecting, notifying reservations and setting the limits of your intervention.
- 10chapters
- 22 000words
- 6sections in the training course
- 60chapters in total
Key values to remember 4
3 °C
Mandatory margin between the substrate temperature and the dew point
60 days
Period for the client to report defects in the immovable structure
80 %
Ceiling for ambient air humidity when applying mineral paints and dispersions
5 °C
Substrate and air temperature threshold for the curing of water-based resins
Scope of the painter's work and boundaries between trades
Acceptance of substrates is the technical act that separates the applicator's risk from that of the preceding trades. Under the SIA 257 standard, the painter must examine the dryness, roughness, cleanliness and mechanical strength of the surfaces delivered. This visual and instrumental examination makes it possible to certify that the substrate is suitable to receive the paint system specified in the description, or to formally record the necessary technical reservations before any execution begins.
The role of the CFC 272 painter is to accept a substrate with a contractually defined level of finish and then coat it. It is never the painter's job to correct structural defects or flatness tolerances that contractually fall to other finishing work trades:
- Plastering and partitions (CFC 271): overall flatness, the levelling of plaster renders and the delivery of the surface finish grades (Q1 to Q4) are the plasterer's responsibility. The painter notes the grade delivered; the painter does not produce missing flatness without a formal addendum.
- External insulation and facades (CFC 221): mesh reinforcement, thermal levelling and new base renders are applied by the facade contractor. The painter deals only with maintenance, refreshing or painting on stabilised render.
- Metal construction (CFC 215): primary blasting, galvanising and workshop anticorrosion primers are the metal fabricator's responsibility. The painter takes on finishing systems on site or the overhaul of existing structures.
- Parquet and hard floor coverings (CFC 283): bare sanding, varnishing and oiling of parquet floors belong to the parquet layer.
- Screeds and industrial floors (CFC 281): assessing the load-bearing capacity or dryness of a new screed before laying heavy resin is the screed layer's responsibility; the painter measures moisture only to validate the adhesion of their own protective wall films or skirting boards.
Inspection protocol: the logical sequence of the diagnosis
To secure a construction site, the inspection of substrates must follow a rigorous sequence. One does not judge the chemical compatibility of a resin on a wall whose water content is unknown, just as one does not apply a render without having quantified the surface cohesion of the plaster or raw concrete.
- Phase 1: Physical and ambient parametersAlways measure the substrate's moisture content by mass, the air temperature and the relative humidity, and calculate the margin above the dew point. These values immediately determine whether the substrate is suitable for drying without risk of blistering or saponification.
- Phase 2: Mechanical cohesion and compatibilityCarry out simple destructive tests: cross-cut or adhesive-tape pull-off test, scraping with a painter's knife to find chalky layers, and a solvent test to identify the nature of an old film (alkyd, dispersion, acrylic or silicate).
- Phase 3: Qualification of deterioration and hygieneFind the source of infiltration before treating mould, classify cracks as either superficial crazing or structural movement that cannot be reinforced, then have historic layers analysed for lead or pollutants before any dry sanding.
- Phase 4: Contractual agreement and the reference areaCompare the quality grade received with the tender specification. Produce a reference area on the actual substrate so that the site management can validate the grain, the finish and the covering power before the overall painting is launched.
- Phase 5: The decision to stop or to proceedIf the substrate does not reach the threshold required by the SIA 257 standard, immediately issue a formal written notice of non-conformity in order to obtain a variation order or to refuse the application without engaging your ten-year warranty.
| Suspected defect | On-site test method | Decision criterion |
|---|---|---|
| Residual moisture | Dielectric moisture meter or CM method | Reject beyond the values tolerated by the binder |
| Chalking of plaster | Pull-off test with cloth adhesive tape | Apply a solvent-based fixing primer or reject |
| Unknown paint | Rubbing with a cloth soaked in denatured alcohol | Softening = acrylic; intact = alkyd or PU |
| Dynamic crack | Fitting plaster tell-tales or millimetre gauges | Applying a simple finishing filler is prohibited |
📘 Chapters in this section 10
Measure before painting: substrate humidity, air humidity and dew point
Master moisture and dew point measurements to rule out any risk of early blistering.
Substrate acceptance and diagnosis before paintingTesting adhesion: pull-off test, knife probing and chalky substrate
Identify the strength of substrates in a few seconds using standardised pull-off and cross-cut tests.
Substrate acceptance and diagnosis before paintingRepainting over old paint: identifying the existing film, compatibility and stripping
Distinguish acrylic from solvent-based alkyd so as to select the right bonding primer without delamination.
Substrate acceptance and diagnosis before paintingThe substrate received: agreed grade, skim coat due and extra cost to be notified
Defend your additional charges when the plastering grades delivered do not match what was tendered.
Substrate acceptance and diagnosis before paintingMould: treat the cause before the stain, and paint that solves nothing
Treat the biological origin of mould before applying a fungicidal film, which will not last on damp plaster.
Substrate acceptance and diagnosis before paintingSuspect old paint: lead, stripping and protection before scraping
Apply the legal framework for safe stripping of old paints loaded with toxic lead.
Substrate acceptance and diagnosis before paintingCracks: opening, reinforcing, filling, and those that are not treated
Distinguish superficial crazing from structural cracks that call for heavy intervention by the structural work trades.
Substrate acceptance and diagnosis before paintingApplication conditions: temperature, draughts, direct sunlight and drying
Adjust ventilation and sun exposure to prevent orange peel or visible lap marks.
Substrate acceptance and diagnosis before paintingThe reference area: validated colour, agreed appearance, and the discussion it avoids
Have your reference area signed off to contractually fix the final appearance and rule out any later dispute.
Substrate acceptance and diagnosis before paintingRefusing a substrate: the record, the letter, and what happens if you apply anyway
Draft the legal notice of defects that protects the painting company against non-compliant instructions.