Public Procurement Thresholds Comparator (AIMP 2026) by Canton & Simap Checklist
Compare the procedure thresholds (direct award, invitation, open procedure) by canton and prepare the Simap file.
Interactive tool
A Calculator for the mandatory legal procedure (annexes 1 and 2 AIMP)
1 Nature of the contract
Used to check the threshold of the international agreements (8'700'000 CHF for works) and the de minimis clause (lots up to 2'000'000 CHF, 20% of the structure at most).
Mandatory procedure
Applicable thresholds excl. TVA (HT):
| Lot amount excl. TVA (HT) | Procedure |
|---|
B Interactive Simap prequalification checklist: the 10 documents to gather
- To request from: AVS compensation fund of your company · Validity: Less than 3 months
- To request from: Your accident insurer (SUVA or private insurer) · Validity: Recent, with premiums up to date
- To request from: Your pension institution · Validity: Recent, with no contribution arrears
- To request from: FAR foundation (Structural Work) or RESOR (Western Swiss Finishing Trades) · Validity: According to the agreement applicable to your company
- To request from: Joint professional commission of your trade · Validity: Certificate for the current period
- To request from: Cantonal (and municipal) tax administration · Validity: Less than 3 months as a general rule
- To request from: Federal Tax Administration (AFC) · Validity: Recent, with no arrears
- To request from: Debt Enforcement Office of the company's registered office · Validity: Less than 3 months
- To request from: Form attached to the contracting authority's tender file · Validity: To be signed for each bid
- To request from: Cantonal commercial register (zefix.ch) · Validity: Recent (less than 3 months as a general rule)
Your ticks stay on this device (in the browser) and are not sent anywhere. The exact list and the validity dates are those in the contracting authority's tender file.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="1.5"] in the content of a page on the site.
📄 Files and templates linked to this tool (free)
- XLSXPDF Quote & Bid Template by CFC A ready-to-fill quote: SIA 118 cover page, bill of quantities by CFC chapters and summary with discounts, cash discount, prorata and TVA 8.1%. See the file, its mini-tool and the pack →
- PDFDOCX ⚖️ Pure Law Secured Consortium Agreement (simple partnership) & Status Report (PV) at End of Lot Complete 6-page guide (PDF) and Word template. Bidding together as two without paying alone for the other's mistakes: full internal agreement, liability towards the client, default, exits, letters and end-of-lot report. See the file, its mini-tool and the pack →
- XLSXPDF KBOB Life-Cycle Assessment & Carbon Summary by CFC (SIA 2032) Compare materials by CO2 emissions, embodied energy and UBP points. See the file, its mini-tool and the pack →
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
Official 2026 table of procedure thresholds (AIMP / LMP): Direct Award, By Invitation, Open Procedure
The public procurement thresholds Swiss construction 2026 determine the procedure the contracting authority must follow: direct award, invitation procedure or open (or selective) procedure. The AIMP intercantonal agreement public procurement sets these values for cantons and municipalities (annex 2 for contracts that do not fall under the international agreements, annex 1 for those that do). The amounts are understood excluding VAT (TVA).
| Nature of the contract | Direct award | Invitation procedure | Open or selective procedure |
|---|---|---|---|
| Works: structural work | less than 300'000 CHF | 300'000 to 499'999 CHF | from 500'000 CHF |
| Works: finishing work | less than 150'000 CHF | 150'000 to 249'999 CHF | from 250'000 CHF |
| Services (architects, engineers) | less than 150'000 CHF | 150'000 to 249'999 CHF | from 250'000 CHF |
| Supplies | less than 150'000 CHF | 150'000 to 249'999 CHF | from 250'000 CHF |
Source: communication of the Intercantonal Authority for Public Procurement (DTAP) of 28 November 2023 on the 2024/2025 threshold values, renewed unless otherwise notified: check the most recent communication before relying on it. For supplies, the direct-award value of 150'000 CHF is that of the revised AIMP of 2019.
1. Construction works — Structural Work (up to 300'000 CHF excl. VAT (HT) by direct award, up to 500'000 CHF by invitation, from 500'000 CHF by open procedure)
For structural work (earthworks, reinforced concrete, masonry, carpentry, civil engineering), the direct award threshold structural work 300000 CHF finishing trades 150000 CHF means that a structural work lot of less than 300'000 CHF excl. VAT (HT) can be awarded directly. Between 300'000 and 499'999 CHF, the invitation procedure 500000 CHF (up to this limit) requires at least 3 bids, with no compulsory publication. From 500'000 CHF, the open or selective procedure applies, with publication on Simap.ch.
When the value of the structure reaches 8'700'000 CHF, the WTO threshold OMC 8700000 CHF works is crossed: the structure falls under the international agreements (OMC / AMP) and the open or selective procedure becomes compulsory, with the longest deadlines.
2. Construction works — Finishing Trades (up to 150'000 CHF excl. VAT (HT) by direct award, up to 250'000 CHF by invitation, from 250'000 CHF by open procedure)
For finishing trades (facades, roofing, electrical, heating, ventilation, plumbing, plastering, painting, flooring), the thresholds are lower: direct award under 150'000 CHF excl. VAT (HT), invitation procedure from 150'000 to 249'999 CHF, open or selective procedure from 250'000 CHF. The threshold of the international agreements is the same as for structural work, because it is assessed on the value of the whole structure.
3. Architect and engineer services (up to 150'000 CHF by direct award, up to 250'000 CHF by invitation) and international WTO (OMC) thresholds
Architecture, engineering and site supervision services follow the same thresholds as finishing trades: direct award under 150'000 CHF, invitation up to 249'999 CHF, open or selective procedure from 250'000 CHF. The international agreements apply to services from 350'000 CHF for cantons, municipalities and districts, and to supplies from the same amount; they apply to construction works from 8'700'000 CHF of structure value.
Use the tender radar to find contracts and the SIA 451 converter to open the bill of quantities.
The legal ban on "salami slicing" of public orders (Art. 15 AIMP)
A contracting authority cannot split a project into small contracts to stay under a threshold: article 15 of the AIMP forbids dividing a contract in order to circumvent the award rules. The value of the contract is assessed by adding up services of the same nature, and VAT (TVA) is not included in the calculation.
1. How is the total contract value calculated (lot-addition rule and 20% de minimis clause)?
For a construction structure, the value to use is that of the whole structure, all lots combined. A regulated exception exists for structures that reach 8'700'000 CHF: under the de minimis clause, a lot that does not exceed 2'000'000 CHF can be awarded according to the national thresholds, as long as all the lots treated this way together do not exceed 20% of the structure's value.
| Step | Example |
|---|---|
| Total value of the works (excl. TVA) | 14'000'000 CHF |
| De minimis margin (20 %) | 2'800'000 CHF |
| A lot of 1'500'000 CHF | At most 2'000'000 CHF and within the margin: procedure according to the national thresholds |
| A lot of 2'500'000 CHF | More than 2'000'000 CHF: open or selective procedure subject to the international agreements |
Rule applied according to the City of Lausanne's note on threshold values and the de minimis clause (6 January 2023). The simulator on this page applies it: enter the value of the structure and the amount already awarded under de minimis.
Checklist of the 10 compulsory certificates so that your Simap bid is never disqualified for a formal defect
A missing or expired document is enough to exclude a bid, even the cheapest. The checklist tender file simap certificates on this page gathers the ten supporting documents requested in most Romandy tenders, with their usual validity. The tender file prevails: some documents are to be submitted with the bid, others only at the contracting authority's request.
1. Certificates AVS, SUVA, LPP, FAR/RESOR, taxes, Debt Enforcement Office extract (< 3 months) and compliance with equal pay / CCT
| No. | Document | To be requested from | Usual validity |
|---|---|---|---|
| 1 | AVS / AI / APG certificate (less than 3 months old) | AVS compensation fund of your company | Less than 3 months |
| 2 | Accident insurance certificate LAA (SUVA or other insurer) | Your accident insurer (SUVA or private insurer) | Recent, with premiums up to date |
| 3 | Occupational pension (LPP) certificate (2nd pillar) | Your pension institution | Recent, with no contribution arrears |
| 4 | Early retirement FAR / RESOR | FAR foundation (Structural Work) or RESOR (Western Swiss Finishing Trades) | According to the agreement applicable to your company |
| 5 | Joint trade fund (CCT compliance) | Joint trade commission of your sector | Certificate for the current period |
| 6 | Cantonal and municipal taxes, withholding tax | Cantonal (and municipal) tax administration | Generally less than 3 months |
| 7 | VAT (TVA): certificate from the Federal Tax Administration (AFC) | Federal Tax Administration (AFC) | Recent, with no arrears |
| 8 | Extract from the Debt Enforcement Office with no certificates of unpaid debts (less than 3 months old) | Debt enforcement office at the company's registered office | Less than 3 months |
| 9 | Declaration of commitment to comply with equal pay for women and men (H/F) and with working conditions | Form attached to the contracting authority's tender file | To be signed for each tender |
| 10 | Extract from the commercial register | Cantonal commercial register (zefix.ch) | Recent (generally less than 3 months) |
Frequently Asked Questions on AIMP Thresholds and Appeals in Public Procurement (FAQ)
1. From what amount must a public construction contract be published on Simap?
For a contract that is not subject to the international agreements, the open or selective procedure, with publication on Simap.ch, is compulsory from 500'000 CHF excl. VAT (HT) in structural work and from 250'000 CHF excl. VAT (HT) in finishing trades. Below that, the contract can be awarded by invitation (at least 3 bids, with no compulsory publication): up to 499'999 CHF in structural work and 249'999 CHF in finishing trades. Direct award is possible under 300'000 CHF in structural work and under 150'000 CHF in finishing trades.
As soon as the value of the structure reaches 8'700'000 CHF, the international agreements (OMC / AMP) apply. All these thresholds are understood excluding VAT (TVA).
2. Can a site be split into several lots to stay under a threshold?
No. Article 15 AIMP forbids dividing a contract to circumvent the award rules: lots of the same nature are added up to assess the value of the contract. A regulated exception exists for structures subject to the international agreements: the de minimis clause allows lots that exceed neither 2'000'000 CHF each nor 20% of the structure's value in total to be handled according to the national thresholds.
The simulator above applies this rule: enter the total value of the structure and, where needed, what has already been awarded under de minimis.
3. Which documents must be attached to a public bid?
Romandy files generally request ten supporting documents: certificates of AVS, accident insurance LAA (SUVA), LPP pension, FAR or RESOR early retirement, joint fund (CCT), taxes, VAT (TVA), a Debt Enforcement Office extract with no certificates of unpaid debts less than three months old, a declaration of commitment to comply with equal pay between women and men and with working conditions, and an extract from the Commercial Register.
The exact list and the validity dates are always those of the tender file: the checklist on this page serves as a guide, not as a substitute.
4. Can an award decision be appealed, and within what time limit?
Yes, as a general rule: the award of a contract placed by open, selective or invitation procedure can be appealed to the competent cantonal court within 20 days of its notification (art. 56 AIMP). This period is counted in calendar days and there are no court holidays in public procurement matters. The ordinary direct award (art. 21 para. 1 AIMP) cannot be appealed.
An appeal does not in principle have automatic suspensive effect: it must be requested from the appeal authority. Get advice from a lawyer as soon as you receive the decision.
Indicative information that does not replace the text of the AIMP, the cantonal implementing law or a lawyer's advice.