Cash-Release Pack: Retention Release Letter & Guide to the Joint and Several Surety (Art. 181 SIA 118)

Complete 6-page guide (PDF) and Word template. Replacing the cash retention with a surety to recover your cash flow: amounts, comparison of retention / bank guarantee / surety insurance, content of the surety and three letters.

Interactive tool: surety premium over 2 years and cash immediately released

Loading the tool…

📄 The « Brut de chantier » pack to download (free)

DOCXPDF

Cash-Release Pack: Joint and Several Surety (SIA 118 Art. 181)

Complete 6-page guide (PDF) and Word template. Replacing the cash retention with a surety to recover your cash flow: amounts, comparison of retention / bank guarantee / surety insurance, content of the surety and three letters.

  • Calculation of the retention and the surety (standard's reference points, to be confirmed (*))
  • Comparison: cash retention, bank guarantee, surety insurance
  • Three letters including the request for release of the retention, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted

Editable Word template (.docx) · Printable PDF document

1. How to calculate the exact amount of the guarantee surety under Article 181 of the SIA 118 standard?

The amount of the surety is calculated on the total sum of the final account, not by tranches. Calculating by tranches is the most frequent confusion.

1.1 The official rule: 10% of the final account up to 300'000 CHF, and 5% of the total sum as soon as the account exceeds 300'000 CHF (with a minimum of 30'000 CHF and a maximum of 2 million CHF)

According to the rule applied by our tools: 10% of the total sum when it does not exceed 300'000 CHF; 5% of the total sum beyond, with a minimum of 30'000 CHF and a cap of 2'000'000 CHF. A final account of 450'000 CHF therefore gives 30'000 CHF (and not 37'500 CHF).

1.2 How to use our Word letter to demand immediate payment of the 5% or 10% held back in cash as soon as the surety certificate is handed over

The letter transmits the surety (number, amount, validity) and requests release of the guarantee retention within 10 days, by bank transfer, subject to default interest. Hand it over against acknowledgement of receipt.

2. Bank surety vs surety insurance vs trades cooperative: what to choose?

Three instruments fulfil the same function, with a different cost and effect on your cash flow. The premiums in our comparison are indicative.

2.1 Why surety insurance or the surety cooperative preserves your bank credit line

A bank guarantee is often pledged or reduces your credit limit; surety insurance or a surety cooperative does not touch your line. Compare written offers: annual premiums of about 0.8% to 1.2% of the amount guaranteed in our example.

2.2 Legal warning: never accept an « abstract first-demand guarantee » in place of the « joint and several surety Art. 496 CO / Art. 181 SIA 118 »

The joint and several surety (Art. 496 CO) is accessory to the guaranteed debt: it presupposes a right of the client. The « first-demand » guarantee is abstract and is called without proving a defect. It is far more dangerous for you: refuse it if the contract provides for a surety.

3. Frequently asked questions about the release of guarantee retentions (FAQ)

3.1 At what precise moment must the client pay me the site guarantee retention (Art. 152 and 181 SIA 118)?

According to our sheets, the retention falls due at acceptance, at the final account and at handover of the surety (Art. 152 and 181 SIA 118, to be checked). As soon as you hand over the surety, you can demand release of the cash retention.

3.2 What is the legal duration of the joint and several surety after acceptance of the works (2 years under Art. 181 para. 3 SIA 118)?

The surety must cover at least the 2-year warranty period of SIA 118: ask for a validity that covers this period. Check the paragraph in your edition of the standard and the text of the surety before it is issued.

3.3 Why does the « first-demand guarantee » allow the client to take the money from the bank without even proving a defect?

Because it is autonomous: the bank pays on a simple compliant demand, without examining the underlying dispute. The client can therefore draw the amount, and you then have to recover it through legal action. An accessory joint and several surety requires a right of the client.

Keywords covered: template letter request release guarantee retention SIA 118 · joint and several surety guarantee for defects art 181 SIA 118 · threshold 300000 CHF surety 10% 5% minimum 30000 CHF · replace cash retention with bank surety or insurance · difference joint and several surety and first-demand guarantee · release cash SME building acceptance of works.

General information based on Swiss law in force — does not replace personalised legal advice.

The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.

📥 Ready-to-use pack · free

Download the document

The file is displayed on screen right away and we also send it to you by e-mail.

Your address is used to send you this file. See our privacy policy.