Art. 837 CC Tool 3.2 Online

Deadline Calculator for the Statutory Mortgage Lien of Craftsmen (hypothèque légale) (4-Month Period — Art. 837 CC)

Calculate the deadline to register a craftsman's legal mortgage and act before it expires.

Interactive tool

2 Nature of the last work carried out that day

3 Your role on the site

CHF

Fatal deadline: entry in the Land Register at the latest on

Emergency backward schedule: 4 critical dates

    Claim and default interest (5% per year, art. 104 CO)

    Interest to date
    Interest to the deadline
    Claim + interest today

    Simple interest over a year of 365 days, from the due date to the date indicated. For a contract subject to SIA 118, the usual bank rate may apply after formal notice (art. 190 para. 1).

    The 4-month period is a forfeiture period of the Civil Code (art. 839 para. 2 CC): it is not extended and the cut-off date is calculated from date to date (art. 77 CO). Indicative information: get advice without delay from a lawyer or the Swiss Association of Contractors in your region.

    Embed this calculator on a website page

    Paste this code into the page, or write [outil code="3.2"] in the content of a page on the site.

    📄 Files and templates linked to this tool (free)

    Move from calculation to full management

    Keep your references at hand, then automate them in your quotes, bids and final statements.

    ⚡ Automate this calculation in our ERP / Soumission software (Trial)

    Technical reference guide

    The fatal 4-month rule (Art. 839 para. 2 CC): why a single day's delay makes you lose your claim

    The statutory lien of craftsmen and contractors 4-month deadline is the last security of an unpaid tradesman: it allows a charge to be registered on the property where they worked. The rules are in the Civil Code, at art. 837 to 841: searching "art 837 839 Swiss civil code" leads to these articles. The 4-month period is a forfeiture period: it is not suspended, not interrupted, and a single day's delay extinguishes the right to registration.

    1. What counts is not sending the application to the court, but the actual entry in the Land Register journal before midnight on the last day!

    Registration must take place at the latest within 4 months of completion of the work (art. 839 para. 2 CC). Sending the application is not enough: the court must have ruled and the Land Register must have entered the charge in the journal. Hence the importance of the provisional ex parte registration land register: if time is short, the civil court of the place where the property is located may order provisional registration by ex parte measures (art. 265 CPC), generally without hearing the owner, within a few days.

    The period is calculated from date to date: work completed on 15 March gives a deadline of Wednesday 15 July 2026. If the last day is 31 October, the deadline falls on the last day of February (Sunday 28 February 2027 for completion on 31 October 2026). When the cut-off date falls on a Saturday or Sunday, do not count on a postponement: aim for the last working day before, and never wait for the last day.

    2. Which date starts the 4-month period? Essential completion work vs mere warranty touch-ups or cleaning

    The starting point is the completion of work last essential performance: the date of your last important contractual performance (commissioning, final installation). According to the case law of the Federal Supreme Court, mere touch-ups of defects, warranty work, cleaning, replacing a defective part or issuing the invoice do not push back this starting point.

    • Counts: completion of the main works provided for in the contract, commissioning, essential final installation.
    • Does not count: warranty touch-ups, cleaning, replacing a small part, sending the final statement.
    • If in doubt: start from the earliest plausible date, and file the application without delay.

    You are a subcontractor of a General Contractor (EG) who does not pay you or goes bankrupt: your absolute protection

    The general contractor bankruptcy subcontractor double payment is the classic scenario: the general contractor collects the price from the client, does not pay its subcontractors, then goes bankrupt. The statutory lien is then the subcontractor's only security on the property. This protection remains subject to the conditions of the law: the 4-month period, the amount of the lien established by the judge or acknowledged by the owner, and the owner's ability to provide sufficient security.

    1. Why you can encumber the owner's plot even if the owner has already paid the General Contractor (the client's risk of double payment)

    Article 837 para. 1 no. 3 CC gives the right to the statutory lien to craftsmen and contractors who work for a general contractor or another contractor: you do not need a contract with the owner. That the owner has already paid the general contractor changes nothing: the owner risks paying twice, once to the general contractor, a second time to free the land. The owner can avoid the registration by providing sufficient security, including default interest for a period of ten years (art. 839 para. 3 CC in its revised version).

    For the subcontractor, a contract that demands waiving the statutory lien in advance should raise an alarm: the general contractor agreement auditor lists the clauses to strike out.

    2. Which trades are entitled to the statutory lien? (Craftsmen, contractors, scaffolders, suppliers of fresh concrete or made-to-measure elements)

    Craftsmen and contractors who have supplied labour, or materials and labour, for a building or other work on a property are entitled to the statutory lien: masons, carpenters, installers, painters, scaffolders, and companies that make made-to-measure elements for the work. The mere delivery of standard materials does not in principle give the right; for fresh concrete delivered to the site or made-to-measure elements, case law accepts registration in certain cases, to be checked case by case with a lawyer.

    Emergency calendar in 4 steps: Formal notice, Ex parte measures (Art. 265 CPC) and Land Register

    Example for work completed on 15 March 2026: the four critical dates are calculated backwards from the cut-off date.

    1. D − 30 before the deadline: Monday 15 June 2026. Last reminder and registered formal notice (5 to 10 days).
    2. D − 15 before the deadline: Tuesday 30 June 2026. Putting the file together: contract or quote, measurements, invoices, Land Register extract of the plot, exact identity of the landowner.
    3. D − 7 before the deadline (critical threshold): Wednesday 8 July 2026. Filing of the application for ex parte measures (art. 265 CPC) with the civil court of the place where the property is located.
    4. Final cut-off date (4 months): Wednesday 15 July 2026. Actual provisional registration in the Land Register journal.

    The SIA 118 and Code of Obligations comparator complements this calendar for warranty periods. Default interest: 5% per year (art. 104 CO) from the due date of the claim.

    ⚡ Track your unpaid invoices in Soumission

    Frequently asked questions about the legal mortgage of craftsmen (FAQ)

    1. From when does the 4-month period of the craftsmen's statutory lien run?

    It runs from completion of the work: the last essential contractual performance (commissioning, final installation). According to the case law of the Federal Supreme Court, mere touch-ups, warranty work, cleaning or sending the invoice do not push back the starting point.

    The period is counted from date to date: work completed on 15 March gives a deadline of Wednesday 15 July 2026. If the last day falls on a Saturday or Sunday, do not count on a postponement: aim for the last working day before.

    2. Must the application be filed, or the registration obtained, within 4 months?

    Registration must take place at the latest within 4 months (art. 839 para. 2 CC): merely filing the application is not enough. In practice, the judge must have ruled (if necessary by ex parte measures, art. 265 CPC) and the Land Register must have entered the charge in the journal before the deadline. The amount of the lien must be established by the owner's acknowledgement or by the judge; provisional registration is enough to safeguard the right.

    Hence the tool's backward planning: file ready at D − 15, application filed at D − 7 at the latest, court of the place where the property is located.

    3. Can a subcontractor encumber the plot if the owner has already paid the general contractor?

    Yes. Article 837 para. 1 no. 3 CC gives the right to the statutory lien to craftsmen and contractors who work for a general contractor or another contractor, and not only to those who contracted with the owner. The owner who has paid the general contractor therefore risks paying twice.

    The owner can avoid the registration by providing sufficient security to the creditor, including default interest for a period of ten years (art. 839 para. 3 CC in its revised version, FF 2025 18).

    4. What default interest can be claimed on the unpaid invoice?

    The statutory default interest rate is 5% per year (art. 104 CO), from the due date or formal notice depending on the case. Example: CHF 50'000 unpaid for 90 days bears CHF 616.44 of interest (simple calculation, year of 365 days).

    The tool calculates interest up to today and up to the cut-off date; for a contract subject to SIA 118, the client in default must pay interest at the usual bank rate (art. 190 para. 1), which may be higher.

    Indicative information: a forfeiture period forgives nothing. Consult a lawyer or your trade association's legal service without delay.