Bad Weather, Frost & Heatwave File: Letter Extending the Deadline (Art. 96 SIA 118) & SECO Time Sheet (ICI)
Complete 7-page guide (PDF) and Word template. Site delays, contractual penalties, bad weather, frost and heatwave: notice of impediment, extension of time, challenging a penalty, formal notice (mise en demeure) with a grace period and an Excel statement sheet.
Interactive tool: cut-off date for filing with the fund, waiting period and notification text
Loading the tool…
📄 The « Brut de chantier » pack to download (free)
DOCXXLSXPDF
Site Delays, Penalties, Bad Weather & Heatwave File (CO / SIA 118)
Complete 7-page guide (PDF) and Word template. Site delays, contractual penalties, bad weather, frost and heatwave: notice of impediment, extension of time, challenging a penalty, formal notice (mise en demeure) with a grace period and an Excel statement sheet.
Delays, late-completion penalties and grace period (CO, SIA 118): legal basis, deadlines and procedure
Bad weather, frost, heatwave: reference points and bad-weather compensation (Art. 42 LACI), Excel calculation sheet
Letters (notice of impediment, extension, challenge of a penalty, formal notice), evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted
Editable Word template (.docx) · Excel workbook (.xlsx) with formulas · Printable PDF document
1. The 2 mandatory and independent steps when weather stops work on site
A weather stoppage triggers two separate steps: one protects your deadlines, the other your wages. Forgetting either one has a price.
1.1 Step no. 1 (contractual): immediately notify the site management in writing to extend your deadlines and block the late-completion penalties (Art. 96 SIA 118)
Inform the site management in writing on the very day of the impediment: weather conditions, readings, photos. This notice is the basis for extending the contractual deadlines and allows you to challenge the late-completion penalties linked to that impediment (Art. 96 SIA 118, to be checked in your edition).
1.2 Step no. 2 (financial): declare the lost hours to the unemployment fund by the 5th of the following month at the latest (Art. 42 to 50 LACI — 80% reimbursement after 2 or 3 waiting days)
Bad-weather compensation is 80% of the insured earnings, with a waiting period of 2 days, then 3 days from the 7th compensation period. The notice must reach the fund by the 5th of the following month at the latest; an unjustified delay may postpone the start of entitlement.
2. Technical thresholds for the ban on laying according to SIA standards and SUVA / cantonal directives
Beyond the weather, it is the products' technical data sheets and the standards that set the limit: laying prohibited below a certain temperature threshold.
2.1 Frost (+5 °C / 0 °C / -3 °C): why applying render, paint or waterproofing in freezing weather voids the materials warranty (SIA 242 / 243 / 271 / 262)
Many products require a minimum temperature of about +5 °C when applied; at 0 °C or below, concrete, plasters, exterior paint and waterproofing risk defects that the manufacturer's warranty does not cover. Read the technical data sheet before working in cold weather.
2.2 Who must pay for the tarpaulin covering and the winter heating if the client demands that the site continues despite the frost?
If the client demands to continue despite the frost, the winter measures (tarpaulin covering, heating) are an additional service to be invoiced, to be agreed by change order (avenant) before execution. Without agreement, have the impediment recorded in writing.
3. Frequently asked questions about stoppages for bad weather and heatwave in Switzerland (FAQ)
3.1 What happens if I send my bad-weather compensation form (ICI) to the unemployment fund on the 6th of the following month instead of the 5th?
An unjustified delay may postpone the start of entitlement to compensation, according to our sheets: it is a deadline rule, not an automatic forfeiture. Send the form on time, and in case of delay, attach a written reason.
3.2 What are the rules for stopping a site in case of a heatwave (≥ 33 °C) and ozone peak in the cantons of Vaud and Geneva?
There is no single legal threshold for stopping: our sheets use reference points (breaks and water from 30 °C, reassessment of the stoppage from 33 °C). The cantons and SUVA publish recommendations: consult them, and document the temperatures recorded.
3.3 From what wind speed (in km/h) does SUVA require tower cranes and roof work to stop?
We have not found a single regulatory value: thresholds depend on the manufacturer's manual (for example around 45 km/h for work platforms and 72 km/h for cranes depending on the case). Apply the manual of each machine.
Keywords covered: template letter extension of deadline site bad weather SIA 118 art 96 · bad-weather compensation form ICI SECO · deadline declaring bad weather 5th of the following month unemployment fund · waiting days employer 2 days 3 days LACI · minimum temperature concreting render frost SIA standard · site stoppage heatwave 33°C Vaud Geneva SUVA.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.