Official Price Escalation Calculator (KBOB / SIA 122 / SIA 123)
Calculate price escalation using the KBOB, SIA 122 and SIA 123 methods.
Interactive tool
Standard: 20 %, i.e. 80 % subject to price escalation (factor 0,80).
Result: production cost index method
- Index change (I₁ − I₀) / I₀
- Subject factor (1 − fixed share)
- Net price escalation rate
- Amount of price escalation excl. TVA (HT)
Result: parametric method with cost model
- Price escalation coefficient
- Share due to wages
- Share due to materials and energy
- Amount of price escalation excl. TVA (HT)
Reference date: date of submission of the tender, unless an earlier date is set by the tender documents (art. 62 SIA 118). The ICP indices and the KBOB indices are published quarterly: enter those of your contract. Price escalation is not due on a fixed price expressly designated as such (art. 41 and 64 SIA 118).
Embed this calculator on a website page
Paste this code into the page, or write [outil code="3.5"] in the content of a page on the site.
📄 File linked to this tool (free)
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
How to bill lawfully for the rise in wages and materials between the tender and the site (art. 62–65 SIA 118)?
The calculation of construction price escalation in Switzerland according to KBOB rests on a simple principle: the contractor calculates the tender on the costs and prices in force on the date of submission of the tender; if the wages, charges or prices of the calculation basis then rise or fall, the remuneration varies accordingly (art. 62 and 64 SIA 118). The tender reference date art. 62 SIA 118 is the date of submission of the tender, unless an earlier date is set by the tender documents. The parties choose the method; failing agreement, the standard adopts the production cost index for the main construction sector and the parametric method for the finishing trades (art. 65 para. 2).
1. The Production Cost Index method (ICP — Standard SIA 123 / SSE) and the deduction of the 20 % fixed, non-indexed share (factor 0,80)
The production cost index ICP SIA 123 tracks the trend in construction costs by type of work. The tool's formula is: net rate = 0,80 × (I₁ − I₀) / I₀; escalation = P₀ × net rate. The 20% fixed share and the 80% rule for escalation means that 20 % of the price is not indexed (fixed costs) and only 80 % follows the index. Example: progress claim of 200'000.00 CHF, index of 108,4 at the reference date and 113,2 in the quarter of execution: net rate 3,542 %, escalation of 7'084.87 CHF, i.e. 207'084.87 CHF billable.
2. The parametric method (Standard SIA 122): customised weighting between Labour (f_S), Materials (f_M) and Fixed costs (f_F = 0,20)
The parametric method SIA 122 (sliding price formula) breaks the price down into shares: fixed costs f_F (0,20), wages f_S and materials / energy f_M, with f_F + f_S + f_M = 1. Coefficient = f_S × ΔS + f_M × ΔM; escalation = P₀ × coefficient. Example on 100'000.00 CHF: f_S = 0,45 and a wage rise of 2,5 %, f_M = 0,35 and a rise in the KBOB materials index of 6,8 %: coefficient of 3,505 %, i.e. 3'505.00 CHF.
| Criterion | Production cost index (SIA 123) | Parametric method (SIA 122) |
|---|---|---|
| Principle | One index per type of work, compared with the reference date | Price broken down into fixed costs, wages and materials, with rises specific to each share |
| Fixed share | 20% (factor 0,80) | f_F = 0,20 |
| Formula | 0,80 × (I₁ − I₀) / I₀ | f_S × ΔS + f_M × ΔM |
| Default method (art. 65 para. 2 SIA 118) | Main construction sector | Finishing work and supply to the main sector |
The indices are published quarterly (ICP indices, KBOB materials indices). Enter those of your contract. Indicative information: the parties may agree on another fixed share or on the supporting-documents method.
Difference between a unit-price/lump-sum contract (escalation due) and a fixed-price contract (escalation excluded)
The fixed price differs from the lump-sum price in that the provisions on price variations do not apply to it; it must be expressly designated as such in the tender documents (art. 41 SIA 118). In a unit-price or lump-sum contract, escalation is on the other hand due (art. 64 para. 1). For daywork with an indicative estimate, it applies only if it was agreed (art. 56 para. 4), and it is calculated according to art. 68: either with the contract method from the tariff in force on the date of the tender, or on the tariff in force at execution (default rule).
- Unit prices or lump sums: escalation due, per progress claim, according to the agreed method.
- Fixed price: escalation excluded, unless an express clause provides otherwise.
- Additional prices and variation orders: escalation also applies to additional prices (art. 66); see the variation order calculator (art. 86 SIA 118) and the daywork report generator.
Frequently Asked Questions about the Calculation of KBOB Price Escalation (FAQ)
1. What is the reference date and why is it decisive?
In a tender with unit prices, lump sums or fixed prices, the contractor calculates its prices on the costs and prices in force on the date of submission of the tender: this is the reference date (art. 62 para. 1 SIA 118). The tender documents may set an earlier date. Escalation is calculated from this base: index I0 is that of the reference date.
If the wages, charges or prices of the calculation basis then vary, the contractor's remuneration varies accordingly (art. 64 para. 1).
2. Which method to apply: production cost index or parametric method?
The parties choose the method. Failing agreement, SIA 118 adopts the production cost index method (ICP, SIA 123) for the main construction sector and the parametric method (SIA 122) for the finishing trades and the supply of the main sector; without agreement on the method, the supporting-documents method applies (art. 65 para. 2).
The recommendations of the KBOB, the conference of public clients, refer to these index methods (SIA 122, 123 and 125); the fixed share of 20 % (factor 0,80) is the one adopted for the production cost index.
3. What share of the price is indexed?
With the production cost index, a fixed share of 20 % is not indexed: only 80 % of the price follows the index (factor 0,80). Example: 200'000 CHF, index of 108,4 at the reference date and 113,2 in the quarter of execution: net rate = 0,80 × (113,2 − 108,4) / 108,4 = 3,542 %, i.e. 7'084.87 CHF of escalation and 207'084.87 CHF billable.
With the parametric method (shares for wages, materials and a fixed share of 20 %), the same principle applies: on 100'000 CHF, +2,5 % wages (share of 45 %) and +6,8 % materials (share of 35 %) give 3'505.00 CHF.
4. Is escalation due on a fixed price?
No. The fixed price differs from the lump-sum price in that the provisions on price variations do not apply to it, and it must be expressly designated as such in the tender documents (art. 41). Escalation is on the other hand due in unit-price or lump-sum contracts (art. 64 para. 1), as well as for daywork if the indicative estimate provides for it (art. 56 para. 4).
So check the nature of the price in your contract before submitting a claim with escalation.
Indicative information prepared from the text of standard SIA 118 (2013 edition) and the KBOB recommendations; standards SIA 122 and SIA 123 prevail for the detail of the methods.