Interactive Subcontractor Verification Checklist (Art. 5 LDet — Joint Liability)
Compile the verification file for your subcontractors under Art. 5 LDet, canton by canton.
Interactive tool
A Due-diligence auditor (Art. 5 LDet) and verification file generator
1 Subcontractor profile
4 Checklist of evidence of the "duty of care" (art. 8b and 8c ODét)
-
Certificate from the joint bodies stating that the subcontractor has been inspected and that no infringement was found, or entry in a recognised trade register (CCT certificate ISAB). Check the date and the trade covered.
-
Certificate from the subcontractor's compensation fund: contributions paid and up to date. In practice required by most contracting authorities.
-
Certificates from the accident insurer (LAA) and from the daily sickness allowance insurance (IJM, according to the CCT): premiums paid, cover in force.
-
Certificate from the pension fund (since 1 January 2023 it states whether an inspection took place and whether the conditions are met) and proof of membership of the trade's early retirement scheme (FAR for structural work, RESOR for finishing trades).
-
Debt enforcement extract less than 3 months old and Commercial Register extract (date of registration: a Swiss subcontractor registered for less than two years must in addition have filed its declarations with the joint bodies).
-
Signed guarantee declaration, accompanied where necessary by the staff list and workers' certificates. SECO offers separate declaration templates for subcontractors established in Switzerland and abroad.
-
The contract must regulate chain subcontracting: any subcontracting subject to your written consent, the right to obtain the same evidence for each link, and an overview of the site (organisational measures: list of the companies present).
-
Confirmation of the posting notification: in construction, notification is compulsory whatever the duration and work may begin only eight days after notification (except in urgent cases). Proof of payment of the security deposit if the CCT requires it.
Financial risk verdict
- Minimum wages at stake (contract amount × labour share): order of magnitude
- Possible sanctions if the duty of care is not met
Your liability is subsidiary: the worker must first pursue his employer (art. 5 para. 2 LDet). The amount above is an estimate of what you might have to pay if the exemption is refused.
Evidence still to be obtained
The file is based on SECO's recommendations and declaration templates; it is not a document issued by SECO. Indicative information, which does not replace a lawyer's advice.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="3.7"] in the content of a page on the site.
📄 Files and templates linked to this tool (free)
- PDFDOCX ⚖️ Pure Law Bankruptcy Protection Kit on Site Complete 7-page guide (PDF) and Word template. What to do when a subcontractor, the general contractor or the client shows signs of insolvency: security, withdrawal from the contract, bankruptcy, double payment and four letter templates. See the file, its mini-tool and the pack →
- PDFDOCX ⚖️ Pure Law "Bogus Self-Employment" Shield File & Unpaid Social Charges Complete 6-page guide (PDF) and Word template. Protecting yourself when an "independent" subcontractor is reclassified as an employee or does not pay their contributions: criteria, liability, duty of care, a secured contract and letters. See the file, its mini-tool and the pack →
- DOCXPDF Joint Liability of Subcontractors Pack (LDet) Complete 7-page guide (PDF) and Word template. A subcontracting agreement and the list of supporting documents to demand before letting a subcontractor on site: duty of care, wage-compliance clause, payment retention and letters. See the file, its mini-tool and the pack →
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
What is the joint and several liability of the contracting entrepreneur in Switzerland (Art. 5 LDet)?
The joint and several liability subcontracting construction Switzerland is provided for by the Posted Workers Act (LDét, RS 823.20), strengthened on 15 July 2013. When construction, civil engineering or finishing works are entrusted to subcontractors, the contracting entrepreneur (total, general or main contractor) is civilly liable for these subcontractors' failure to comply with the net minimum wages and working conditions set by the generally binding collective agreement. The rule applies whether the subcontractor is established in Switzerland or abroad, and whatever the size of the site.
1. Why you can be ordered to pay your subcontractor's unpaid wages and social charges (and those of its own subcontractors down the chain!)
The contracting entrepreneur is jointly and severally liable for all the subcontractors who follow it in the contractual chain: the subcontractor of your subcontractor, and the next one. This subcontracting chain building can have four or five links, whose companies you do not always know. Its liability is however engaged only on a subsidiary basis: it is liable only to the extent that the subcontractor has first been pursued in vain or cannot be pursued (art. 5 para. 2 LDét).
What the law puts on you are the net minimum wages and working conditions (art. 2 para. 1 LDét): hours, holidays, allowances provided for by the agreement. Unpaid social contributions (AVS, SUVA, pension fund) follow separate rules, but a subcontractor who does not pay wages generally does not pay its charges either: the financial risk is overall. On a contract of 250'000 CHF with 45% labour, the order of magnitude of the wages at stake is 112'500 CHF.
2. How to free yourself legally from this liability: proof of the "duty of care" (Art. 8b and 8c ODet)
Article 5 LDet duty of care lets you exempt yourself if you prove that you carried out your duty of care to the extent required by the circumstances. It is deemed to have been carried out if the subcontractor has credibly shown, on the basis of documents and supporting evidence, that it complies with wages and working conditions. The ordinance specifies the method: documents to be presented by the subcontractor (art. 8b ODét) and contractual and organisational measures on your side (art. 8c ODét).
Article 8b ODet documents subcontractor cites in particular the posting certificate (foreign company), the subcontractor's guarantee declaration accompanied where necessary by staff lists, the certificate from the joint bodies and entry in a trade register. Article 8c covers the contract (regulation of chain subcontracting, prior consent) and the organisation (overview of the companies present on the site). The higher the risk (large site, low-margin sector, unknown subcontractor), the more thorough the expected diligence.
The 8 compulsory certificates to require and archive BEFORE the subcontractor enters the site
"Compulsory" is meant here in the practical sense: the ordinance cites some of them (art. 8b and 8c ODét), the others are good practice that strengthens your file. The tool groups them in a list of 8 items of evidence, with a compliance score from 0% to 100%. For a site inspection joint commission Unia FVE or that of another joint commission (for example, in the canton of Vaud, the joint trade commissions that work with the FVE and Unia), ask the subcontractor for the inspection certificate of its trade: it is the strongest evidence.
| No. | Evidence to archive | Legal basis | Who is it for? |
|---|---|---|---|
| 1 | Up-to-date CCT certificate / trade register (ISAB / joint commission) | Art. 8b para. 1 ODét | All subcontractors |
| 2 | Certificate of payment of AVS / AI / APG / AC contributions (less than 3 months old) | good practice (not expressly required by the ODét) | All subcontractors |
| 3 | Certificate of payment of SUVA (LAA) premiums and IJM sickness | good practice | All subcontractors |
| 4 | Certificate of payment of LPP pension (2nd pillar) and early retirement (FAR or RESOR) | art. 8b para. 1 ODét; CCT of the trade | All subcontractors |
| 5 | Extract from the Debt Enforcement Office and the Commercial Register | Art. 8b para. 3 ODét; good practice | All subcontractors |
| 6 | Written declaration signed by the subcontractor (SECO template) guaranteeing compliance with CCT minimum wages, working time and meal / travel allowances | Art. 8b para. 1 and 2 ODét | All subcontractors |
| 7 | Contractual clause prohibiting second-tier (chain) subcontracting without prior written consent | Art. 8c ODét | All subcontractors |
| 8 | (Foreign company) Online notification 8 days before the start of works and proof of payment of the CCT security deposit | art. 6 LDét; art. 6 ODét; art. 2 para. 2ter LDét (security deposit) | Foreign company |
1. Subcontractor with registered office in Switzerland (Trade registers ISAB / SIPAC, AVS, SUVA, LPP, FAR/RESOR, collective agreement CCT)
For a Swiss company, first ask for the CCT certificate ISAB (the construction alliance's information system, launched in 2019 by the employers' associations and the unions) or the certificate of the competent joint commission, then the certificates of payment of AVS, SUVA and IJM contributions, the LPP pension and the trade's early retirement scheme (FAR for structural work, RESOR for finishing trades), the debt enforcement and commercial register extract, and the subcontractor's signed declaration. A Swiss subcontractor registered in the commercial register for less than two years, and not yet inspected by a joint commission, must in addition have filed its declarations with the joint bodies (art. 8b para. 3 ODét). The cantonal register to approach depends on the canton of the site: the tool displays it for the 26 cantons.
The tool's specifications cite "SIPAC" for Geneva and "Bâtiment-Service" for Vaud: these names could not be confirmed in the official sources consulted. In Geneva, the sources indicate the Geneva joint commission for structural work (Commission paritaire genevoise du gros œuvre); in Vaud, the joint trade commissions with the FVE and Unia. Confirm the right contact with the commission of your trade.
2. Foreign subcontractor posting staff to Switzerland (8-day advance notice, CCT security deposit, declaration of Swiss minimum wages)
In construction, civil engineering and finishing trades, every posting must be notified, whatever its duration, and work may begin only eight days after notification, except in urgent cases (art. 6 LDét and art. 6 ODét). For each posted worker declaration: the notification covers identity, gross hourly wage, start date and duration, type of works and exact place of work. Require confirmation of the notification before entry on site, the signed declaration guaranteeing Swiss minimum wages, and proof of payment of the security deposit if the extended collective agreement provides for one (art. 2 para. 2ter LDét). The amount of the deposit results from the agreement: the tool's specifications cite 10'000 to 20'000 CHF, to be confirmed with the joint commission.
Civil and administrative sanctions (fine of up to 30'000 CHF and exclusion from public contracts for up to 5 years)
Under civil law, you can be sued by the workers of the subcontractor or its chain, on a subsidiary basis (art. 5 para. 2 LDét), for the net minimum wages and working conditions not complied with. Under administrative law, the cantonal authority may sanction the contracting entrepreneur who has not met its duty of care: a fine of 5'000 CHF at most or a ban on offering its services in Switzerland of one to five years, and the charging of inspection costs (art. 5 para. 4 and art. 9 para. 2 let. d and g LDét).
The fine of up to 30'000 CHF targets the employer who violates the minimum working and wage conditions (art. 9 para. 2 let. b LDét), and may be combined with the ban on offering its services in the case of a particularly serious infringement. Sanctions that have become final appear on a public list kept by SECO; contracting authorities may take them into account and exclude the companies concerned from public contracts (see the AIMP thresholds comparator). Also compare the deductions that some general contractors impose on you with the general contractor agreement auditor.
Frequently Asked Questions on Subcontracting in Construction in Switzerland (FAQ)
1. Who is the "contracting entrepreneur", and for which works is it liable for its subcontractors?
Article 5 LDét covers construction, civil engineering and finishing works: the contracting entrepreneur (total, general or main contractor) is there civilly liable for its subcontractors' failure to comply with the net minimum wages and working conditions of article 2 para. 1 LDét (minimum remuneration, working and rest time, holidays, safety at work, protection of certain categories of persons, non-discrimination).
The law speaks only of net minimum wages and working conditions: social contributions follow their own rules (compensation funds, insurers). As the subcontractor may be Swiss or foreign, the check applies in both cases.
2. Can the unpaid wages of my subcontractors' subcontractors be claimed from me, and in what order?
Yes: the contracting entrepreneur is jointly and severally liable for all the subcontractors who follow it in the contractual chain, but only to the extent that the subcontractor has first been pursued in vain or cannot be pursued (art. 5 para. 2 LDét). The worker must therefore first turn to his own employer: your liability is subsidiary.
It remains real as soon as a subcontracting company disappears or goes bankrupt. Hence the value of prohibiting chain subcontracting by contract without your written consent (art. 8c ODét).
3. Which documents are enough to prove my duty of care?
You exempt yourself by proving that you carried out your duty of care to the extent required by the circumstances (art. 5 para. 3 LDét). The ordinance cites in particular the certificate from the joint bodies, entry in a trade register, the subcontractor's guarantee declaration and, for a foreign company, the posting certificate (art. 8b ODét), as well as contractual and organisational measures (art. 8c ODét). SECO provides declaration templates.
In the tool, 6 items out of 8 ticked for a foreign company give a score of 75%: exemption possible but fragile. Merely gathering documents is not always enough: you must assess all the elements at your disposal.
4. What does the contractor who did not check its subcontractors risk?
In addition to the obligation to pay the minimum wages at stake (the tool's order of magnitude: 112'500 CHF for a contract of 250'000 CHF with 45% labour), the cantonal authority may impose on the contractor who failed in its duty of care a fine of 5'000 CHF at most or a ban on offering its services in Switzerland of one to five years, and make it bear the inspection costs (art. 5 para. 4 and art. 9 para. 2 let. d and g LDét).
The fine of up to 30'000 CHF targets the employer who violates the minimum conditions (art. 9 para. 2 let. b). Sanctions that have become final appear on a public SECO list, which contracting authorities may consult: exclusion from public contracts is possible under the applicable law.
5. Must a foreign subcontractor be notified and provide a security deposit?
In construction, civil engineering and finishing trades, notification of posted workers is compulsory whatever the duration of the assignment, and work may begin only eight days after notification, except in urgent cases (art. 6 LDét; art. 6 ODét). Ask for confirmation of the notification before entry on site.
If the extended collective agreement provides for it, the foreign employer must also lodge a financial guarantee (art. 2 para. 2ter LDét): the law sets no amount, it results from the agreement (the tool's specifications cite 10'000 to 20'000 CHF: to be confirmed with the joint commission).
Indicative information prepared from the LDét, the ODét and SECO's recommendations; it replaces neither a lawyer's advice nor that of the joint commission of your trade.