Theft or Vandalism of Materials on a Building Site in Switzerland: Principle of Accession (Art. 642 CC) & Custody Transfer Protocol
Complete 8-page guide (PDF) and Word template. Materials delivered but not yet installed: who bears the theft, record of transfer of custody and storage, clause on advance payment for materials and template letters.
Interactive tool: who bears the loss, and secure-storage clause
Loading the tool…
📄 The « Brut de chantier » pack to download (free)
PDFDOCX⚖️ 'Pure Law' File
Custody Transfer Protocol & Theft of Materials on a Building Site
Complete 8-page guide (PDF) and Word template. Materials delivered but not yet installed: who bears the theft, record of transfer of custody and storage, clause on advance payment for materials and template letters.
Ownership (Art. 642 CC) and risk (Art. 376 CO): who bears what
Minutes (PV) of custody transfer and storage, down-payment clause on materials
Template letters, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted
Printable PDF document · Editable Word template (.docx)
1. Two Swiss legal truths that craftsmen discover too late
Between the supplier who reserves ownership and the contractor who bears the theft, Swiss law often leaves the craftsman alone with the loss. Two rules explain why.
1.1 Why the clause « the goods remain our property until full payment » is overridden once the materials are installed (principle of accession, Art. 642 CC)
The owner of a thing is also the owner of everything that forms an integral part of it (Art. 642 CC): as soon as a material is incorporated into the building, the supplier's retention of title no longer applies to that material. It subsists as long as the goods remain separable.
1.2 Why the theft of your materials on site over the weekend is at your expense until the work is accepted (Art. 376 CO / Art. 187 SIA 118)
The contractor in principle bears the risk of loss of the work and of the material he supplies until the work is delivered (Art. 376 CO). Your business liability insurance (RC) generally excludes your own goods: read the conditions and supplement them with suitable cover.
Consequences by party involved
Party involved
What the law says for them
Contractor
Bears the theft before acceptance (CO 376); loses the retention of title on what is incorporated (CC 642); transfers the risk through custody minutes (PV).
Subcontractor
Same risk for his materials; must ask for the site to be closed before delivery.
Client
Takes over custody from the written handover; his construction works insurance (ATC) may cover, under conditions.
2. How to legally transfer the risk of theft to the client from the delivery of costly equipment
The written transfer of custody shifts the risk: you need a signed document, a locked room and insurance that covers the equipment.
2.1 Invoicing a down payment on materials supplied (Art. 139 & 145 SIA 118) coupled with minutes (PV) of handover into the custody of the construction works insurance (ATC)
SIA 118 provides, under conditions, for a down payment on materials supplied and stored (articles to be checked in your edition). Couple it with signed minutes (PV) of handover into custody: from that handover, ownership and risk pass to the client and his insurer.
2.2 Requiring the site management to close site access provisionally before delivering a heat pump (PAC), copper or joinery
Before delivering valuable equipment, demand in writing that the site be locked and guarded. Note the serial numbers, take photographs, and have the delivery note signed by the client or his representative.
3. Frequently asked questions about theft and breakage of equipment on a building site (FAQ)
3.1 Does the client's construction works insurance (ATC) cover the theft of materials not yet fixed in place?
It depends on the policy: theft is sometimes excluded or limited to incorporated materials. Ask for the ATC conditions and have what is covered recorded in writing before delivery.
3.2 Can I dismantle and take back a boiler or doors that have already been installed if the client does not pay my invoice?
No: what is incorporated into the building has in principle become the owner's property (Art. 642 CC), and an unauthorised removal exposes you to prosecution. Use formal notice (mise en demeure) and the statutory mortgage lien (hypothèque légale) instead.
3.3 What should I do if another craftsman damages my work already installed before final acceptance (damage by unknown persons)?
Record and photograph the damage immediately, inform the site management in writing and reserve your rights. Refuse to have the damage spread across all trades through a flat-rate deduction without supporting documents.
Keywords covered: theft equipment materials building site who pays Switzerland · principle of accession art 642 Swiss civil code · retention of title clause construction materials void · construction works insurance ATC theft cover · down payment on materials supplied SIA 118 art 139 145 · custody transfer minutes PV template site delivery.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.