1. Why you are responsible for normal wear if you do not hand over a written maintenance instruction against signature (SIA 469 / SIA 118)
The warranty covers defects in the work, not lack of maintenance. You must still be able to prove that the owner knew what he had to do: that is the role of the signed maintenance instruction.
1.1 The critical case of flexible joints (silicone / hybrid sealant): « maintenance joints » to be checked every 12 months excluded from the 2-year warranty if the client is informed in writing
The elastic joints in wet rooms age: they must be checked and redone regularly (at least every year). The signed instruction informs the client of this check and establishes that damage due to lack of maintenance is his responsibility. Note: the revision of the CO voids clauses that exclude in advance the repair of defects in a private building work; the clause targets only the client's failure to maintain.
1.2 Flat roofs (SIA 271), exterior woodwork, oiled parquet floors and technical filters: the owner's annual inspection obligations
Cleaning gutters and roof outlets twice a year, visual inspection of facades, maintenance of woodwork and parquet floors, changing ventilation filters: the instruction by CFC lists these actions with their reference interval (to be adapted to the technical data sheets).
2. How to turn every site acceptance into a recurring and profitable annual maintenance contract
The maintenance instruction protects your warranty; it also opens a lasting relationship with the client.
2.1 Proposing on the acceptance minutes (PV) an annual flat fee for an inspection visit and preventive maintenance (SIA 469)
When handing over the keys, propose an annual inspection visit (joints, roof, woodwork, filters) for a flat fee. The client stays covered, you keep a recurring income and you check the condition of the work before damage occurs.
3. Frequently asked questions about the DOE and the SIA 469 maintenance booklet (FAQ)
3.1 What is the legal warranty period of a silicone joint in Switzerland if there is no mention in the contract and no maintenance instruction?
A joint that is defective from the outset falls under the work warranty (2 years under SIA 118, 5 years of limitation under Art. 371 CO for a building work). A joint that ages normally and is not maintained is the owner's responsibility, which must be provable by an instruction.
3.2 Is an architect entitled to block payment of the final balance as long as the As-Built File (DOE) has not been handed over?
If the contract provides for handing over the DOE as a condition of acceptance or of the balance, the client may withhold payment until it is handed over. Check the clause: otherwise the retention can be challenged. Hand over the DOE at acceptance to remove the issue.
3.3 What technical documents make up a complete DOE for the technical lots and the building envelope in Switzerland?
As-built drawings, electrical and plumbing diagrams, manuals and warranties for appliances (heating, heat pump, ventilation, kitchen), inspection certificates, list of products used and signed maintenance instructions. Our key handover sheet lists them.
Keywords covered: template as-built file DOE Switzerland word pdf · building maintenance instruction standard SIA 469 · warranty exclusion silicone joints sealant annual maintenance Switzerland · flat roof maintenance contract SIA 271 gutters · lack of maintenance owner loss of warranty 2 years SIA 118 · key handover maintenance instructions by CFC.
General information based on Swiss law in force — does not replace personalised legal advice.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.