1. Cantonal matrix: which works can start on a simple notification versus a 30-day public notice?
General rule, to be confirmed with the municipality before any work. Not all cantonal thresholds have been re-read in the texts: the « verified » mention in our table exists only for a few values.
1.1 Like-for-like replacement, interior renovation without touching load-bearing elements and rooftop solar installations (Art. 18a LAT)
Ordinary maintenance work and interior renovation without touching load-bearing walls or the use are generally exempt from permit; well-integrated rooftop solar installations are subject to simple notification (Art. 18a LAT), except on a cultural property of cantonal or national importance.
1.2 The traps that always require a permit: change of colour or of window division, external heat pump (PAC), roadside fences and attic conversion
A change of external appearance (colour, window division), an external heat pump (noise certificate), a roadside fence or an attic conversion generally require a notification or a permit. The municipal regulations and the cantonal law set out the details.
2. How to turn the preparation of the municipal notification file / APA into a billed service (450 to 900 CHF)
The novice client fears the administration: taking it on is a service, which is billed. It also avoids starting a site without a permit, the financial consequences of which often fall back on the craftsman.
2.1 Unlocking the signature of the quote by taking on the administrative formality for the owner
Offer, in the quote, the preparation of the notification or permit file (form, plans, certificates, colour samples) for a flat fee of the order of 450 to 900 CHF. The owner saves time and you avoid starting without a permit.
3. Frequently asked questions about building permits in French-speaking Switzerland (FAQ)
3.1 What is the difference between an Accelerated Procedure Authorisation (APA) and a Definitive Application (DD) in Geneva?
The APA is a simplified procedure for works of lesser importance (Art. 3 LCI according to our sheets), handled more quickly and without a full public notice; the definitive application (DD) follows the ordinary procedure with public notice and preliminary opinion. The authority assigns the procedure according to the project.
3.2 In which cantons can an external air/water heat pump now be subject to a simple notification procedure?
In the canton of Vaud, an air/water or air/air heat pump (PAC) in an existing building is exempt from a permit with notification to the municipality and a certificate of compliance with the noise requirements (Art. 68c RLATC according to our sheets). Other cantons: enquire with the cantonal office.
3.3 Is the signature of an architect entered in the register (REG / MPQ) compulsory to file a simplified application?
It depends on the canton and the nature of the project: a simplified procedure often does not require an architect, whereas a more complex application does. Ask the municipality which documents and which signatories are required.
Keywords covered: list works without building permit vaud valais geneva pdf · simplified procedure APA geneva exemption public notice CAMAC vaud · building permit external heat pump noise circle · replacement windows blinds facade protected zone permit · maximum height fence pergola garden shed without permit municipality · invoicing flat fee municipal notification file craftsman.
The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.