Wage dumping, undeclared work and unlawful staff leasing in Swiss construction: recognise, protect yourself, report
A site can lose money without a single wall being badly built: wages paid below the collective labour agreement (CCT), workers “arranged” without declaration, a crew lent by a company that calls itself a subcontractor, a very low bid made up for afterwards by change orders. This page helps you recognise these three situations, recalls what the undeclared-work act, the employment-services and staff-leasing act, the posted-workers act and the Code of Obligations say, and tells you where to report. A signal is not proof: only the authority and the judge characterise the facts.
PDFDOCX
The guide: Wage dumping, undeclared work and staff leasing (LSE)
The detailed guide for this page in PDF and Word: legal basis, steps to follow, template letters and evidence checklist.
An e-mail address is requested: the guide is displayed immediately and is also sent to you by e-mail (signed links valid for 7 days).
How the trap works and which warning signs to look for
The mechanism on the ground in French-speaking Switzerland
Undeclared work, family arrangements, under-grading (anomaly 15). According to the SECO, undeclared work covers various forms of failing to meet the notification and authorisation obligations of social insurance law, foreigners’ law and withholding tax. On a site: wages paid in cash or in part without a payslip, a worker not declared to the compensation fund, a relative of the employer “arranged” without a contract, a skilled worker placed in a lower wage category than the one in the collective labour agreement (CCT). Even within a family, the simplified accounting procedure does not apply to the employer’s spouse and children working in the business (Art. 2 para. 2 let. b LTN).
Fake subcontracting and staff lending (anomaly 16). A contract for work promises a work; staff lending places workers at the disposal of a company that directs them. The ordinance speaks of staff leasing where the company receiving the workers obtains the essential powers of direction, and this can be inferred in particular if the workers are integrated into its organisation, use its tools or if it bears the risk of defective performance (Art. 26 OSE). Clue: a “subcontract” invoiced by the hour, with workers who take their orders from the head of the main company.
“Suicide” bid and change orders (anomaly 17). A very low bid is not unlawful in itself. The signal appears when the company chosen then claims unordered extras and makes continuing the work conditional on their payment. The -25 % gap in the user’s example is not a legal threshold.
Warning signs (Red Flags) to check before and during the works
None of these facts proves an offence on its own; some have an ordinary explanation. They justify asking for documents in writing, checking an authorisation in the official register and comparing what you see on site with the contracts and the staff lists. Tick the ones you observe in the mini-diagnosis that follows.
Workers present on site appear on no staff list and no contribution certificate, or are paid in cash.
The hourly wage stated by a worker is below the CCT category that corresponds to their actual role.
A “subcontracting” contract is invoiced by the hour, and the workers take their orders from the head of the main company, with its tools and equipment.
The company that supplies staff does not appear in the official register of authorised companies, or refuses to show its authorisation.
A bid is clearly lower than all the others, with no explanation of quantities, method or costs.
Shortly after the award, extras are claimed with no written order, with the threat of stopping the site if they are not paid.
The documents requested (staff list, wage categories, certificates) are not provided, or inspectors are refused access.
Mini-diagnosis: how many signals do you spot?
Tick what matches your case. The result is a simple count: nothing is sent or saved.
Do you see signals of undeclared work, staff lending or a bid with change orders?
Tick what matches your case. Nothing is sent or saved: the result is a simple count of signals.
This is neither a diagnosis nor proof: a signal calls for a check, not an accusation.
Wage dumping, undeclared work and unlawful staff leasing in Swiss construction: recognise, protect yourself, report · https://art-construction.ch/en/outils/dossiers/dumping-salarial-travail-au-noir-location-services-lse/
Tick the signals you have observed: the result appears here, box by box.
Swiss legal framework, evidence and template letters
Legal bases: CO, CC, CP, LP and SIA 118
Four blocks of rules: undeclared work (LTN, LAVS), collective labour agreements (CO, LECCT), staff leasing (LSE, OSE) and contracts and procurement (LMP, CO). Texts read on Fedlex on 2026-11-07. For order changes, the SIA 118 standard is not needed here; its article numbers are not confirmed (*) and are not cited.
The rules at a glance
Rule
Article
What the text says
Undeclared work: inspection and exclusion
Art. 1, 6, 7, 8 and 13 LTN
The cantonal body checks notification and authorisation (access, information, documents); after a final conviction, exclusion from public contracts for up to five years.
Simplified accounting procedure
Art. 2 para. 2 LTN
Not applicable to capital companies, nor to the employer’s spouse and children working in the business.
Contributions and foreigners
Art. 14 and 87 LAVS ; Art. 117 LEI
Contributions withheld at each payday; offences of evading contributions or employing an unauthorised foreigner.
CCT: mandatory effect
Art. 357, 341 CO ; Art. 1 LECCT
Agreements less favourable than the CCT are void; no waiver during the contract and one month after.
Staff leasing
Art. 12, 19, 22 and 39 LSE ; Art. 26 and 28 OSE
Cantonal authorisation required; without it, contracts void; fine up to 100 000 francs for the lender, 40 000 for the employer who knew.
Subcontracting chain
Art. 5 LDét
The contracting contractor answers for its subcontractors; it is relieved by proving its diligence.
Abnormally low bid
Art. 38 and 44 LMP
Request for information mandatory; exclusion possible if the company does not prove it meets the conditions.
Fixed price and extras
Art. 373, 374, 375 and 6 CO
No increase of a fixed price, except in extraordinary circumstances; silence may sometimes amount to acceptance.
Contractual shield and evidence to gather
The complete subcontracting contract, with its proof of wage compliance, is described in our file on joint liability (LDét); change orders are covered in the file on the quote. Here are the reflexes specific to this page.
Before access to the site, demand the staff list with wage categories, the certificate from the joint body and the contribution certificates (letter 1).
Check in the official register that a company supplying staff is authorised; read in the contract who directs the workers and who supplies the equipment.
Prohibit chain subcontracting in writing without your consent and demand the same proof at each level.
Refuse in writing any unordered additional work (letter 2) and ask for a quantified justification; do not let your silence amount to acceptance.
Before awarding, ask the author of a very low bid to explain its quantities, its method and its labour, and record the answer.
Report the facts (letter 3) to the competent body, without characterising anyone, and consult a lawyer before any termination of the contract.
Template letter models
Letter 1: request for supporting documents and authorisation before access to the site (main company)
[Place], [date] · registered mail and e-mail
Subject: site [name], package [..], proof of wage compliance and, where applicable, staff-leasing authorisation
Dear Sir or Madam,
Before your staff access the site, please send us by [date, 5 working days]: the list of the persons assigned with their wage category; the certificate from the joint body of the applicable CCT; the payment certificates for your social contributions; and, if your workers are placed under the direction of our site manager, your staff-leasing authorisation. Without these documents, we cannot authorise access. We reserve all our rights.
Yours faithfully. [Name, position, signature]
Letter 2: refusal of an unordered extra and request for justification (owner)
[Place], [date] · registered mail and e-mail
Subject: contract of [date], fixed price of CHF [..], extra announced of CHF [..], refusal and request for justification
Dear Sir or Madam,
The contract sets a fixed price; the contractor cannot in principle claim any increase, even if the work has required more labour or expense than expected (Art. 373 para. 1 CO). We did not order in writing the additional work announced on [date] and we do not accept this extra. Please tell us in writing, by [date, 10 days], the nature of each item of work, the quantities, the unit price and the reason why it would not be included in the fixed price. Please continue the work according to the contract. We reserve all our rights.
Yours faithfully. [Name, position, signature]
Letter 3: report to the inspection body or the joint commission (facts only)
[Place], [date] · registered mail
Subject: report of facts observed on the site [name, address] and request for inspection
Dear Sir or Madam,
We bring to your attention the following facts, observed on [dates]: [persons present with no known notification / wage stated by the person concerned / company supplying the staff and direction exercised on site]. We do not characterise these facts and make no accusation. Documents available: [dated photos, contract].
Yours faithfully. [Name, position, signature]
Where to report
Checking notification obligations falls to the cantonal body for inspecting undeclared work; wages in the sector, to the joint commission (generally binding CCT) or the tripartite commission; staff leasing, to the competent cantonal authority; a criminal offence, to the police or the public prosecutor’s office.
SECO: cantonal tripartite commissions and joint bodies: List of cantonal tripartite commissions (PDF of 5 November 2026); in sectors with a generally binding CCT, joint commissions check the agreement. (address read on 7 November 2026)
Protect yourself with the ACIP index and the Soumission software, frequently asked questions
How to lock down your site with the ACIP index and Soumission
A low price is judged on costs, not on an impression. Before awarding, price your quotes by CFC with the ACIP 2026 prices (Art Construction Indice de Prix) on our platform, with the Soumission software, and ask the company proposing a much lower price to explain its quantities, its method and its labour. This benchmark proves nothing: it grounds a written question.
No. The figure of 25 % is an example of a situation, not a legal threshold: neither the LMP nor the CO sets a price gap. In public procurement, the contracting authority must ask for the relevant information when the total price is abnormally low compared with the other bids (Art. 38 para. 3 LMP) and may exclude a company that, invited to explain itself, does not prove it meets the participation conditions and offers no assurance of conforming performance (Art. 44 para. 2 let. c LMP). In a private contract, a low bid is lawful; it is the fixed-price contract that protects afterwards (Art. 373 para. 1 CO).
What is the difference between subcontracting and staff leasing?
The subcontractor carries out a work or a package under its own direction and at its own risk. The staff lender places a worker at the disposal of a company, handing it the essential powers of direction (Art. 26 para. 1 OSE). Among the clues: integration of the worker into the borrowing company’s organisation, use of its tools, risk of defective performance borne by it (Art. 26 para. 2 OSE). If the leasing requires authorisation, the cantonal labour office must have granted it (Art. 12 para. 1 LSE). The specific case is characterised by the cantonal authority.
What does a company risk if it takes on staff lent by a company without authorisation?
Without authorisation, the staff-leasing contract is void (Art. 22 para. 5 LSE), and so is the lender’s employment contract with the worker (Art. 19 para. 6 LSE). An employer that intentionally uses a lender it knew was not authorised faces a fine of up to 40 000 francs (Art. 39 para. 2 let. a LSE); the lender itself, up to 100 000 francs (Art. 39 para. 1 let. a). These are penalties provided for by law, not convictions: prosecution is up to the cantons (Art. 39 para. 6).
Can a worker accept in writing a lower wage than the CCT’s?
Not validly. For employers and workers bound by the agreement, its clauses have direct and mandatory effect, and agreements departing from them to the worker’s detriment are void and replaced by those clauses (Art. 357 para. 1 and 2 CO). The worker cannot waive, during the contract and one month after, claims arising from mandatory provisions or a CCT (Art. 341 para. 1 CO). A generally binding CCT applies to the whole sector (Art. 1 para. 1 LECCT). Limitation periods are to be checked with a lawyer.
Can a contractor demand an extra after a fixed price?
In principle no: where the price is fixed, the contractor cannot claim any increase, even if the work has required more labour or expense than expected (Art. 373 para. 1 CO). The judge may grant an increase or termination if extraordinary circumstances, impossible to foresee, make performance excessively difficult (Art. 373 para. 2 CO). Work actually ordered in addition is the subject of a written change order. Our file on the quote details these rules.
The articles of SIA 118, a standard that is not freely available, must be checked in the edition applicable to your contract (marked (*) when they could not be confirmed). The numerical examples on this page are fictitious.