Fire on a Construction Site in Switzerland: Legal Liabilities (Art. 376 CO vs SIA 118) & Template of an AEAI Hot-Work Permit

Complete 7-page guide (PDF) and Word template. Who bears the loss of the work in case of fire before the keys are handed over: insurance, a ready-to-fill hot-work permit, damage claim and letters to the insurer and the client.

Interactive tool: who bears the loss, and template of a named hot-work permit

Loading the tool…

📄 The « Brut de chantier » pack to download (free)

PDFDOCX ⚖️ 'Pure Law' File

Fire Prevention & Fire Loss Pack on Site + Hot-Work Permit

Complete 7-page guide (PDF) and Word template. Who bears the loss of the work in case of fire before the keys are handed over: insurance, a ready-to-fill hot-work permit, damage claim and letters to the insurer and the client.

  • Who pays what: CO, SIA 118, building insurance, civil liability (RC) and construction works insurance
  • Site hot-work permit to be filled in before any work with flame, heat or sparks
  • Loss notification and letters, evidence checklist, frequent mistakes, practical case and cases where a lawyer should be consulted

Printable PDF document · Editable Word template (.docx)

1. What does Swiss law say if the building burns down before the keys are handed over (Art. 376 CO vs Art. 187 SIA 118)?

Swiss law answers differently depending on whether the contract is governed by the Code of Obligations alone or by the SIA 118 standard. This difference, ignored at signing, is discovered on the day of the loss.

1.1 The dreaded trap of the pure Code of Obligations (Art. 376 para. 1 CO): in the event of accident before delivery, the contractor loses its work and its materials

If the work perishes by accident before delivery, the contractor can claim neither the price of its work nor reimbursement of its expenses, unless the client is in default; the loss of the material is borne by the one who supplied it (Art. 376 para. 1 and 2 CO).

1.2 How the SIA 118 standard (Art. 187-188) and partial acceptance of the work reverse the risk in favour of the craftsman

In our fact sheets, SIA 118 regulates the risk differently: from acceptance, the risk passes to the client, and partial acceptance of your package makes it pass earlier. Check the articles in the applicable edition and have each partial acceptance recorded by a dated and signed report (PV).

Consequences by party involved

Party involvedWhat the law says for them
Main contractorBears the loss of the work before delivery by accident (CO 376); limits the risk by partial acceptance (SIA 118).
SubcontractorLoses its work and its material as long as its package has not been accepted; may be prosecuted (CP 222) if it caused the fire.
ClientBears the risk from acceptance; its insurer may have recourse against the person responsible.

2. Fire caused by hot work (torch, welding, grinder): criminal law and insurance

A fire arising from work with flame or sparks engages the criminal and civil liability of whoever caused it, and often reduces the insurance cover.

2.1 Criminal prosecution ex officio for negligent arson (Art. 222 CP) and reduction of business liability (RC) benefits for gross fault

Negligently causing a fire is punished by a custodial sentence of up to one year or a monetary penalty, and up to three years if life or limb is endangered (Art. 222 CP). In the event of gross fault, your liability (RC) insurer may reduce its benefit and the building insurer may have recourse against you.

2.2 The mandatory « Hot-Work Permit » protocol (AEAI / SUVA Guidelines): extinguisher on site and inspection rounds 1 h and 2 h after the end of the shift

Before any work with flame or sparks, fill in a hot-work permit: flammable materials removed, extinguisher within reach, openings sealed, supervision designated, then two inspection rounds 1 hour and 2 hours after the end of the work. AEAI requirements vary depending on the building: ask the cantonal authority.

3. Frequently asked questions about site fires and insurance in Switzerland (FAQ)

3.1 Does the Cantonal Insurance Institution (ECA) automatically cover a building under construction or conversion?

It depends on the canton: some insurance institutions cover the building from the start of the works, others require a declaration or construction works insurance (ATC). Ask for a written certificate of cover before opening the site.

3.2 Who compensates the other craftsmen whose works or tools burned because of the fault of another trade?

Each craftsman in principle bears the loss of his own work as long as it has not been accepted (Art. 376 CO), with possible recourse against the person responsible for the fire, or its liability insurance (RC). Check whether your insurance covers your tools and goods on site: this is often excluded.

3.3 What minimum ceiling of business liability (RC) cover must be taken out in construction in Switzerland (CHF 10 million)?

Federal law sets no single ceiling for a construction company. Clients and public procurement often require several million, sometimes CHF 10 million: read the tender documents and compare with your policy.

Keywords covered: fire construction site who is liable Switzerland · article 376 CO loss of the work before delivery · difference art 376 CO and SIA 118 art 187 · hot-work permit template site AEAI SUVA pdf · article 222 criminal code negligent arson · ECA recourse business liability RC insurance hot work.

General information based on Swiss law in force — does not replace personalised legal advice.

The articles of the Code of Obligations (CO), the Civil Code (CC), the Criminal Code (CP), the Debt Enforcement Act (LP), the AVS Act (LAVS), the Accident Insurance Act (LAA) and the Posted Workers Act (LDet) cited were re-read on Fedlex on 6 November 2026. The articles of the SIA 118 standard, which is not freely available, are given according to our fact sheets and must be checked in the edition applicable to your contract. Updated: 7 November 2026.